Scope of Work for B9166 Floor
1) Objective:
Procure materials/services to apply an epoxy floor coating on a portion of the flooring in Building 9166 at NASA-Stennis Space Center. The area to be coated is 102ft by 30.5ft (approximately 3111 sq ft).
2) Details:
The contractor shall provide the coating materials, tools and anything else required for the proper application of the floor coatings.
The 3111 sq ft area will be free of any equipment or hardware. 120V, 15A electrical power outlets are nearby. A forklift and pallet jacks are available in the building.
The proposed floor coating for Building 9166 shall be based on the building activities which involved heavy loads and forklift traffic.
The contractor shall grind the floor to the coating manufacturer’s recommendation for surface profiling.
There are some joints in the slab that may require cleaning/degreasing since they might be lower than the prepared surface.
The contractor shall provide shelf-life data on product prior to use.
The contractor shall apply an epoxy primer coat with a light gray pigment to the recommendations of the coating manufacturer.
The contractor shall apply a base coat of commercial grade 100% solids epoxy resin with a light gray pigment to the recommendations of the coating manufacturer.
The contractor shall apply a clear satin finish, UV stabilized, heavy duty urethane topcoat, that is high abrasion resistance, to the recommendations of the coating manufacturer.
The contractor shall remove all trash generated and unconsumed materials brought onto the site.
3) Address:
NASA-Stennis Space Center Building 9166
SSC, MS 39529
4) Technical contact:
5) Site Access:
Tom Meredith will coordinate all SSC visitor access. All workers must be an US citizen. Full name of each worker, as it appears on their driver license, will be required 2 days prior to site access.
6) Delivery date: floor to be completed within 6 weeks from award.
Following 5 sheets show the building layout and photos of the work area within the building.
7A 8A 9A
Ba y
Ba y
Ba y
Ba y
Ba y
Ba y
Ba y
Ba y
Ba y
10A 4A 5A 6A 3A 2A 1A
7F 8F 9F 10F 4F 5F 6F 3F 2F 1F
Shipout
Receiving
Main Path
Room 103
Wiring Ra ck
Ra ck
Ra
B
A
102 ft
30.5 ft
B9166 Layout
File details come from the government source that posted it. Updated .