JUSTIFICATION FOR SOLE SOURCE PROCUREMENT (OPEN MARKET OR GSA)

UNDER $250,000

Sole source acquisitions may be used on a limited basis and only when the Contracting Officer’s Representative (COR)/Program Official has provided sufficient justification and the Contracting Officer has determined that the circumstances warrant such action. The content for a justification must contain detailed facts and rationale to justify the sole source acquisition. Soliciting from a single source must be done in accordance with FAR 13.106-1(b) or 8.405-6. At a minimum, the following information must be included:

Identification of Program Office, Contracting Activity, and Proposed Requirement, Justification and Program Office Certification:

A. Program Office:

National Center for Immunization and Respiratory Diseases, Division of Viral Diseases 1600 Clifton Road, Bldg. 24 Centers for Disease Control and Prevention Atlanta, GA 30329

B. Contracting Activity:

Centers for Disease Control and Prevention Office of Financial Resources Infectious Disease and International Acquisition Branch (HCAJEWB)

C. Identification of Requirement:

1. Nature of Action to be Approved by Contracting Officer:

a. Sole source acquisition of: Purchase of laboratory supplies

b. Procurement Request (PR) Number (if available): 00HCVGE1-2023-72324 - DVD_A&A 26615_New_Mesa Laboratories

2. Proposed Vendor and Estimated Procurement Amount (if available):

a. Proposed Vendor: Mesa Laboratories, Inc.

b. Estimated Procurement Amount: $

3. Is the requirement on GSA Schedule? ☐ Yes ☒ No

If yes, provide schedule number: Click here to enter text.

D. Justification:

Rev. 5/14/19

1. The justification for this non-competitive action is:

☒ In accordance with FAR 13.106-1(b)(1), “only one source [is] reasonably available” which states that, “For purchases not exceeding the simplified acquisition threshold. (i) Contracting officers may solicit from one source if the contracting officer determines that the circumstances of the contract action deem only one source reasonably available (e.g., urgency, exclusive licensing agreements, brand-name or industrial mobilization). (ii) Where a single source is identified to provide a portion of a purchase because that portion of the purchase specifies a particular brand-name item, the documentation in paragraph (b)(1)(i) of this section only applies to the portion of the purchase requiring brand-name item. The documentation should state it is covering only the portion of the acquisition which is brand- name.”

☐ Urgency ☐ Exclusive licensing agreements/Proprietary data ☐ Brand name required ☐ Industrial mobilization ☒ Other (only one source)

☐ In accordance with FAR 8.405-6 “Limiting Sources” which states that, “the only circumstances that may justify the action are – (A) An urgent and compelling need exists, and following the procedures would result in unacceptable delays; (B) Only one source is capable of providing the supplies or services required at the level of quality required because the supplies or services are unique or highly specialized; or (C) In the interest of economy and efficiency, the new work is a logical follow-up to an original Federal Supply Schedule order provided that the original order was placed in accordance with the applicable Federal Supply Schedule ordering procedures. The original BPA must not have been previously issued under sole-source or limited-sources procedures.”

☐ Urgency ☐ Only One Source ☐ Logical Follow Up ☐ Brand name required

2. Other facts supporting sole source procurement:

a. What can this product/service do that other products/services cannot do?

MESA Laboratory, Inc is the only contractor that can provide the sensors as they are required for the equipments that are already installed within the laboratory from the same vendor.

b. What other products/services were considered and why did they not meet the need?

To ensure continuity of the supplies and equipment within the lab, no other products were considered

3. Program Office efforts to seek potential offerors:

Research was conducted in GSA Advantage to see if there was a possibility that an additional vendor was able to provide the supplies with the required specifications, however, Program was unsuccessful due to the specific requirements of the equipments that are already installed.

Rev. 5/14/19

E. Program Office Certification:

I have reviewed this sole source justification and certify the justification is true and accurate to the best of my knowledge and adequate to support other than full and open competition.

Center/Institute/Office COR/Program Official Name/Title: Christa Joseph

3/29/2023

X Christa Joseph

Signed by: Christa O. Joseph -S Center/Institute/Office COR/Program Official Signature:

Certification Date: Click here to enter a date.

F. Contracting Office Certification:

I have fully relied on the information provided herein and hereby certify that this justification is accurate and complete to the best of my knowledge and belief:

Contracting Officer Name: Click here to enter text.

Contracting Officer Signature:

Certification Date: Click here to enter a date.

2023-03-29T08:20:44-0400
Pellumbeshe Hoxhaj -S