This Request for Proposals (RFP) issued by the City of Santa Fe, Central Purchasing Division and Santa Fe Regional Airport seeks qualified vendors to develop and produce a complete Airport Certification Manual (ACM), Airport Emergency Plan (AEP), and Snow and Ice Control Plan (SICP) for Santa Fe Regional Airport in compliance with 14 CFR Part 139 requirements. The selected consultant will conduct initial review and gap analysis of existing airport documents, conduct onsite meetings with airport personnel and stakeholders, facilitate document review periods, coordinate with the FAA throughout development, and deliver final professionally formatted documents in editable electronic and PDF formats. Key project phases include reviewing existing procedures, coordinating with airport departments and external agencies, developing comprehensive ACM reflecting current operations and certification programs, creating SICP addressing winter operations and snow removal procedures, and completely rewriting the AEP with coordination across local, state, and federal emergency response agencies. The proposal due date is December 4, 2026, at 3:00 PM, with evaluation scheduled for December 7, 2026, Best and Final Offers due December 14, 2026, contract finalization by December 16, 2026, and final award anticipated January 29, 2027. The resulting contract will be a Professional Services Contract with a one-year term and an option to extend to two years. Contractors must not commence work until receiving a Purchase Order from the City.
Pricing is evaluated based on a cost response formula where the lowest responsive offeror's cost is divided by each offeror's cost and multiplied by 75 points, with all charges requiring justification and documentation of need. The evaluation is conducted on a point-based system with 1,000 total possible points: Organizational Experience (450 points), Organizational References (100 points), Mandatory Specifications (375 points), and Cost Proposal (75 points). Local preference of 3–6 percent is available to certified resident businesses located within Santa Fe municipal limits, requiring a State of New Mexico Taxation and Revenue Department-issued Resident Business certificate. Contractors must comply with the City of Santa Fe's Living Wage Ordinance and applicable prevailing wage rates. Offerors must submit Campaign Contribution Disclosure Forms, Non-Collusion Affidavits, Conflict of Interest Statements, and evidence of no debarment or suspension. The RFP encourages submission of proposals with professional certifications including Accredited Airport Executive (AAE), Certified Member (CM), Airport Certified Employee (ACE)–Operations, Certified Emergency Manager (CEM), and Federal Emergency Management Agency Incident Command System certifications (ICS-100, ICS-200, ICS-300, and ICS-400). A protest deadline of 15 calendar days applies following notice of award, with protests directed to Travis Dutton-Leyda, Chief Procurement Officer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 14_CFR_Part_139_(up_to_date_as_of_11-04-2026).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The City of Santa Fe (City), Central Purchasing Division (CPD)
AND
Airport
REQUEST FOR PROPOSALS (RFP)
RFP#: FY27-TRFP-033 - Santa Fe Regional Airport, Airport
Certification Manual, Airport Emergency Plan, and Snow and Ice
Control Plan Rewrite
Table Of Contents
1. INTRODUCTION
2. CONDITIONS GOVERNING THE PROCUREMENT
3. RESPONSE FORMAT AND ORGANIZATION
4. SCOPE OF WORK
5. EVALUATION
6. EVALUATION PHASES
7. VENDOR RESPONSE
8. ATTACHMENTS
Attachments:
A - 14 CFR Part 139 (up to date as of 11-04-2026)
I. INTRODUCTION
PURPOSE OF THIS RFP
The Santa Fe Regional Airport (SAF) is seeking qualified and experienced vendors to develop and produce a complete and comprehensive Airport Certification Manual (ACM.) for Santa Fe Regional Airport. The selected vendor shall also develop a complete and derivative Snow and Ice Control Plan (SICP) and Airport Emergency
Plans (AEP) that is consistent for current classification, certificate limitations, exemptions, and any further applicable requirements for FAA-certificated Part 139 airports. The purpose of this project is to develop new, comprehensive, accurate, and operationally functional ACM that reflects the current operations, facilities, equipment, personnel, policies, procedures, and regulatory requirements of Santa Fe Regional Airport. The consultant will be responsible for verification that the completed manual and plans are designed correctly for the Santa Fe Regional Airports procedural assignments and responsibilities reflect current Airport Operations.
SCOPE OF PROCUREMENT
The resulting contract will result in a Professional Services Contract with a term of one (1) year with the option to extend to two (2) years. The SAF is in need of a firm to rewrite a comprehensive ACM, AEP, and SCIP, that will be ready for full review by the Federal Aviation Administration (FAA). The current manuals and plans are outdated and require revisions to meet current FAA Advisory Circulars (14 CFR Part 139). This revision process will require communication with the SAF Operations Manager and possible onsite coordination.
PROCUREMENT MANAGER
Sebastian Gallegos has assigned a Procurement Manager who is responsible for the conduct of this procurement whose name, telephone number, and email address are listed below:
Sebastian Gallegos, Airport Project Manager
505-695-3538 sfgallegos@santafenm.gov mailto:sfgallegos@santa
1. Any inquiries or requests regarding this procurement should be submitted via the OpenGov
Procurement Portal at https://procurement.opengov.com/portal/santafenm/projects/324046.
DEFINITION OF TERMINOLOGY
This section contains definitions of terms used throughout this procurement document, including appropriate abbreviations:
A. “Addendum” means a written or electronic document issued by the City to modify, clarify, or supplement the information in the original RFP prior to the proposal due date. This may also be called
Amendment or RFP Amendment.
B. “Amended Proposal” means a revised and complete version of a proposal submitted by an Offeror prior to the proposal due date, clearly labeled as superseding the original submission.
C. “Authorized Purchaser” means an individual authorized by Santa Fe Regional Airport to place orders against this contract.
D. “Award” means the point at which the contract document has been fully executed. See also “Contract” and “Final Award".
E. “Best and Final Offer” or “BAFO” means a final revised proposal submitted by an Offeror, upon request by the City, to provide updated pricing or other proposal elements.
F. “Business Hours” means the normal business hours of the Requesting department; 8:00 AM through
5:00 PM Mountain Standard or Daylight Time, whichever is in effect on the date given.
G. “Central Purchasing Division” or “CPD” means the City office responsible for overseeing and managing the procurement of tangible personal property, services, and construction, including ensuring compliance with applicable procurement laws, policies, and procedures.
H. “Chief Procurement Officer” or “CPO” means that person within the CPD who is responsible for the control of procurement of items of tangible personal property, services, or construction.
I. “City” means the City of Santa Fe, New Mexico which in the procurement context may act through the
Finance Director, City Manager, or Governing Body. City align expectations, mitigate risk, and finalize project understanding prior to contract execution..
J. “Confidential” means confidential financial information concerning Offeror’s organization and data that qualifies as a trade secret in accordance with the Uniform Trade Secrets Act NMSA 1978, Sections
57-3-A-1 through 57-3A-7. The following items may not be labelled as confidential: Offeror’s submitted
Cost response, Staff/Personnel Resumes/Bios (excluding personal information such as personal telephone numbers and/or home addresses), and other submitted data that is not confidential financial information or that qualifies under the Uniform Trade Secrets Act.
K. “Contract” means any agreement or Price Agreement for the procurement of items of tangible personal property, services, or construction.
L. “Contractor” means any business having a contract with the City of Santa Fe.
https://procurement.opengov.com/portal/santafenm/projects/324046
M. “Department” means the Requesting Department sponsoring this Procurement.
N. “Determination” means the written documentation of a decision of a procurement officer including findings of fact required to support a decision. A determination becomes part of the procurement file to which it pertains.
O. “Desirable” the terms “may,” “can,” “should,” “preferably,” or “prefers,” identify a desirable or discretionary item or factor.
P. “Electronic Submission” means a successful submittal of Offeror’s proposal consisting of text, images or both readable on computers or other electronic devices.
Q. “Evaluation Committee” means a body appointed to perform the evaluation of Offerors’ proposals.
R. “Evaluation Committee Report” means a report prepared by the Procurement Manager and the
Evaluation Committee to support the Committee’s recommendation for contract award. It will contain scores and written evaluations of all responsive Offeror proposals.
S. “Final Award” means the point at which the contract(s) resulting from this RFP have been fully executed through the final required signature—either by the City Manager or City Mayor, depending on the contract amount—thereby making the contract(s) legally binding. See also “Contract.”
T. “Finalist” means an Offeror who meets all the mandatory specifications of this RFP and whose score on evaluation factors is sufficiently high to merit further consideration by the Evaluation Committee.
U. “Hourly Rate” means the proposed fully loaded maximum hourly rates that include travel, per diem, fringe benefits and any overhead costs for contractor personnel, as well as subcontractor personnel if appropriate.
V. “Living Wage” means the minimum hourly wage established by the City of Santa Fe’s Living Wage
Ordinance, which contractors must comply with, as posted at https://santafenm.gov/economic-development/business-resources/living-wage-information.
W. “Mandatory” the terms “must,” “shall,” “will,” “is required,” or “are required,” identify a mandatory item or factor. Failure to meet a mandatory item or factor may result in the rejection of the
Offeror’s proposal.
X. “Minor Irregularities” means anything in the proposal that does not affect the price, quality and/or quantity, or any other mandatory requirement.
Y. “Offeror” means any person, corporation, or partnership who chooses to submit a proposal.
Z. “OpenGov” means the City of Santa Fe’s official electronic procurement platform used to post solicitations, receive vendor proposals, facilitate communication with Offerors, and manage procurement activities in a transparent, streamlined, and auditable manner.
AA. “Procurement Manager” or “PM” means any person authorized by both the CPD and the
Requesting Department to facilitate the procurement process and/or administer the resulting contract(s).
The Procurement Manager is responsible for managing all aspects of the procurement, including https://santafenm.gov/economic-development/business-resources/living-wage-information planning and coordinating all related events; ensuring that all required information is provided to potential offerors, the Evaluation Committee, and CPD; and preparing and processing the Evaluation
Committee Report. The Procurement Manager ensures compliance with all applicable requirements and serves as the primary point of contact throughout the procurement lifecycle. The Procurement Manager is the sole point of contact for all communication related to the procurement. Potential offerors, City staff, and CPD must direct all questions or information through the PM. Staff in the Requesting
Department must rely on the PM to serve as the liaison between their department and CPD to maintain consistency, transparency, and compliance. When questions, challenges, or issues arise during the procurement process, the Procurement Manager should consult with CPD for guidance. CPD is available to support and facilitate the RFP process and to assist the Procurement Manager in ensuring a smooth, fair, and compliant procurement.
BB. “Project” means a temporary process undertaken to solve a well-defined goal or objective with clearly defined start and end times, a set of clearly defined tasks, and a budget. The project terminates once the project scope is achieved, and project acceptance is given by the project executive sponsor.
CC. “Protest” means a formal, written objection to a solicitation or contract award, submitted in accordance with NMSA 1978, Section 13-1-172 and Procurement Manual, to the Protest Manager identified in this RFP.
DD. “Request for Proposals” or “RFP” means all documents, including those attached or incorporated by reference, used for soliciting proposals.
EE. “Requesting Department” means the City Department responsible for overseeing the work or delivery of tangible personal property by a contractor.
FF. “Responsible Offeror” means an Offeror who submits a responsive proposal and who, when required, provides information and documentation demonstrating that their financial resources, production or service facilities, personnel, reputation, and experience are sufficient to ensure satisfactory delivery of the services or tangible personal property described in the proposal.
GG. “Responsive Offer” means an Offeror whose proposal conforms in all material respects to the requirements set forth in the RFP. Material aspects of the RFP include, but are not limited to, price, quality, quantity, delivery requirements, and compliance with all mandatory specifications, terms, and conditions necessary for fair and complete evaluation.
HH. “Sealed” means, in terms of electronic submission, an Offeror’s proposal and all accompanying documents have been completely and successfully uploaded into the City’s designated procurement platform—such as OpenGov—prior to the submission deadline stated in this RFP.
II. “Staff” refers to any individual employed by an Offeror, whether on a full-time, part-time, or independent contractor basis.
JJ. "Subcontractor” means any person or business entity, other than an employee of the Contractor, that performs part of the work or provides goods or services under the contract resulting from this RFP.
KK. “Written” means typewritten on standard 8 ½ x 11-inch paper. Larger paper is permissible for charts, spreadsheets, etc.
PROCUREMENT LIBRARY
A procurement library has been established. Offerors are encouraged to review the material contained in the
Procurement Library by viewing the attachment section of the solicitation. The library contains information listed below:
Electronic version of RFP, Questions & Answers, RFP Amendments, etc.
https://procurement.opengov.com/portal/santafenm/projects/324046
II. CONDITIONS GOVERNING THE PROCUREMENT
This section of the RFP contains the schedule of events, the descriptions of each event, and the conditions governing this procurement.
TIMELINE
The CPD and the Procurement Manager will make every effort to adhere to the following schedule:
Issue RFP: November 20, 2026
Deadline for Written Questions: November 25, 2026, 5:00pm
Response to Written Questions: November 26, 2026, 5:00pm
Proposals Due Date: December 4, 2026, 3:00pm
Evaluation*: December 7, 2026, 10:00am
Best and Final Offers*: December 14, 2026, 3:00pm
Finalize Contracts*: December 16, 2026
Contract Award*: January 29, 2027
*Dates indicated after "Proposals Due Date" are estimates only and may be subject to change without necessitating an amendment to the RFP.
Explanation of Events
The following paragraphs describe the activities listed in the Timeline/Sequence of Events.
The City reserves the right to:
A. Change or extend the Proposals Due Date.
B. Revise the RFP before the due date.
The city will process addenda if it is determined that modifications, clarifications, or additions to the RFP are necessary. Similar to the initial invite, addenda will be emailed to registered Potential Offerors who have selected the commodity codes for this event.
A. Issue RFQ
This RFQ is being issued on behalf of the City on the date indicated in the timeline.
B. Deadline for Written Questions
Potential Offerors may submit written questions to CPD and the Procurement Manager as to the intent or clarity of this RFQ as indicated in Section the Timeline. All written questions must be submitted via the
OpenGov Procurement Portal. Questions shall be clearly labeled and shall cite the Section(s) in the RFQ or other document which form the basis of the question.
C. Responses to Written Questions
Responses to the written questions will be provided on OpenGov, on or before the date indicated in the
Timeline.
D. Proposals Due Date
Only electronic proposal submission is allowed.
ALL PROPOSALS MUST BE SUBMITTED FOR REVIEW AND EVALUATION BY THE CPD
AND EVALUATION COMMITTEE VIA UPLOAD.
Pursuant to NMSA 1978, Section 13-1-116, the contents of proposals shall not be disclosed to competing Offerors during the negotiation process. The negotiation process is deemed to be in effect until the contract is awarded pursuant to this RFQ. Awarded in this context means approved by the City
Manager or Mayor.
E. Evaluation
An Evaluation Committee will perform the evaluation of proposals. This process will take place as indicated in the timeline, depending upon the number of proposals received. During this time, CPD or/and the Procurement Manager may initiate discussions with Offerors who submit responsive or potentially responsive proposals for the purpose of clarifying aspects of the proposals. However, proposals may be accepted and evaluated without such discussion. Discussions SHALL NOT be initiated by the Offerors.
F. Selection of FinalistsThe Evaluation Committee will select, and the Procurement Manager will notify the finalist Offerors as per the timeline or as soon as possible thereafter. A schedule for Oral
Presentation, if any, will be determined at this time. Finalists will be comprised of the Offerors receiving the highest cumulative scores in the following sections: Organizational Experience, Organizational References, and Mandatory Specifications.
G. Finalize Contracts
After approval of the Evaluation Committee Report, any contractual agreement(s) resulting from this
RFQ will be finalized with the most advantageous Offeror(s), taking into consideration the evaluation factors set forth in this RFQ, as per Section the Timeline or as soon as possible thereafter. The most advantageous proposal may or may not have received the most points. In the event mutually agreeable terms cannot be reached with the apparent most advantageous Offeror in the timeframe specified, the
City of Santa Fe reserves the right to finalize a contractual agreement with the next most advantageous
Offeror(s) without undertaking a new procurement process.
H. Contract Awards
Upon receipt of the signed contract, the Department will award pursuant to the Timeline, or as soon as possible thereafter. The award is subject to appropriate Department and City Manager/Governing Body or Board approval. Contractors must not commence work until the Department issues them a Purchase
Order (PO) and instructions to start.
I. Protest Deadline
Any protest by an Offeror pertaining to the solicitation or award must be submitted within 15 days from the notice of solicitation or award and in conformance with NMSA 1978, Section 13-1-172 and applicable procurement regulations. As a Protest Manager has been named in this RFQ, pursuant to
NMSA 1978, Section 13-1-172 and Procurement Manual Section Y, ONLY protests delivered directly to the Protest Manager in writing and in a timely fashion will be considered to have been submitted properly and in accordance with statute, rule, and this RFQ. The 15-calendar day protest period shall begin on the day following the notice of award of contract(s) and will end at 5:00 pm MST/MDT on the
15th day. Protests must be written and must include the name and address of the protestor and the RFQ number. The protest must include a detailed statement of the grounds for the protest, along with any relevant supporting documentation. It should also clearly state the specific ruling being requested from the party listed below. The protest must be delivered to:
Travis Dutton-Leyda, CPO
City of Santa Fe purchasing@santafenm.gov
PROTESTS RECEIVED AFTER THE DEADLINE WILL NOT BE ACCEPTED.
General Requirements
A. Acceptance of Conditions Governing the Procurement
By submitting a proposal in response to this RFP, Offerors acknowledge and agree to all Conditions
Governing the Procurement, as outlined herein.
B. Incurring Cost
All costs incurred by an Offeror in the preparation, submission, transmittal, or presentation of a proposal—including any related materials—are the sole responsibility of the Offeror. Additionally, any mailto:purchasing@santafenm.gov costs associated with the setup, demonstration, or evaluation of proposed equipment, products, or systems shall be borne entirely by the Offeror.
C. Prime Contractor Responsibility
By receiving a contract resulting from this RFP, each awarded Contractor is solely responsible for fulfilling all contractual requirements with the City. The City will make payments only to the
Contractor(s) named in the executed agreement(s) and will not be responsible for any payments to subcontractors, third parties, or for any ancillary costs such as taxes, permits, or fees.
D. Subcontractors/Consent
The use of subcontractors is allowed. The prime contractor shall be wholly responsible for the entire performance of the contract whether subcontractors are used. Additionally, the prime contractor must receive approval, in writing, from the City before any subcontractor is used during the term of the resultant contract.
E. Amended Proposals
Offerors may submit amended proposals at any time prior to the Proposal Due Date. Each amended submission must serve as a complete replacement of the original proposal. Amendments may be submitted in response to changes issued by the City or to reflect revisions made independently by the
Offeror. To ensure clarity during evaluation, all amended proposals must be clearly labeled as such and must explicitly state that they supersede any previously submitted versions. The City will evaluate only the most recent, complete version submitted prior to the deadline. City staff will not merge, collate, or otherwise combine materials from multiple submissions.
F. Proposal Withdrawal
Offerors will be allowed to withdraw their proposals at any time prior to the deadline for receipt of proposals. After the deadline for receipt of proposals, the Offeror must submit a written withdrawal request addressed to the Central Purchasing Division and the Procurement Manager and signed by the
Offeror’s duly authorized representative. The approval or denial of withdrawal requests is governed by the applicable procurement regulations
G. Proposal Offer Firm
Responses to this RFP, including proposal prices for services, will be considered firm for one-hundred eighty (180) days after the due date for receipt of proposals or one-hundred eighty (180) days after the due date for the receipt of a best and final offer, if the Offeror is invited or required to submit one.
H. Disclosure of Proposal Contents
The contents of all submitted proposals will be kept confidential until the final award has been completed by the City. At that time, all proposals and documents pertaining to the proposals will be available for public inspection, except for proprietary or confidential material as follows:
1. Proprietary and Confidential information is restricted to:
a. confidential financial information concerning the Offeror’s organization; and
b. information that qualifies as a trade secret in accordance with the Uniform Trade Secrets Act, NMSA 1978, Sections 57-3A-1 through 57-3A-7.
2. An additional but separate redacted version of Offeror’s proposal shall be submitted containing the blacked-out proprietary or confidential information, to facilitate eventual public inspection of the non-confidential version of Offeror’s proposal.
IMPORTANT: The price of products offered, or the cost of services proposed SHALL NOT be designated as proprietary or confidential information.
If a request is received for disclosure of proprietary or confidential materials, the City Attorney and the CPO shall examine the request and make a written determination that specifies which portions of the proposal should be disclosed. Unless the Offeror takes legal action to prevent the disclosure, the proposal will be so disclosed. The proposal shall be open to public inspection subject to any continuing prohibition on the disclosure of proprietary or confidential information.
I. No Obligation
This RFP in no manner obligates the City to the use of any Offeror’s services until a valid written contract is awarded and approved by appropriate authorities.
J. Termination
This RFP may be canceled at any time and all proposals may be rejected in whole or in part when the
City determines such action to be in the best interest of the City of Santa Fe.
K. Sufficient Appropriation
Any contract awarded because of this RFP process may be terminated if sufficient appropriations or authorizations do not exist. Such terminations will be affected by sending written notice to the contractor. The City’s decision as to whether sufficient appropriations and authorizations are available will be accepted by the contractor as final.
L. Legal Review
The City requires that all Offerors agree to be bound by the General Requirements contained in this
RFP. Any Offeror’s concerns must be promptly submitted in writing to the attention of the CPD and the
Procurement Manager.
M. Governing Law
This RFP and any agreement with an Offeror which may result from this procurement shall be governed by the laws of the State of New Mexico.
N. Basis for Proposal
Only information supplied in writing by the CPD and the Procurement Manager or contained in this RFP shall be used as the basis for the preparation of Offeror proposals.
O. Contract Terms and Conditions
The contract between the City and a contractor will follow the format specified by the City and contain the terms and conditions set forth in the Draft Contract. However, the City reserves the right to negotiate provisions in addition to those contained in this RFP Draft Contract with any Offeror. The contents of this RFP, as revised and/or supplemented, and the successful Offeror’s proposal will be incorporated into and become part of any resultant contract.
The City discourages exceptions from the contract terms and conditions as set forth in the Draft
Contract. Such exceptions may cause a proposal to be rejected as nonresponsive when, in the sole judgment of the City (and its evaluation team), the proposal appears to be conditioned on the exception, or correction of what is deemed to be a deficiency, or an unacceptable exception is proposed which would require a substantial proposal rewrite to correct.
Should an Offeror object to any of the terms and conditions as set forth in the RFP Draft Contract strongly enough to propose alternate terms and conditions despite the above, the Offeror must propose specific alternative language. The City may or may not accept the alternative language. General references to the Offeror’s terms and conditions or attempts at complete substitutions of the Draft
Contract are not acceptable to the City and will result in disqualification of the Offeror’s proposal.
Offerors must provide a brief discussion of the purpose and impact, if any, of each proposed change followed by the specific proposed alternate wording.
If an Offeror fails to propose any alternate terms and conditions during the procurement process (the
RFP process prior to selection as successful Offeror), no proposed alternate terms and conditions will be considered later during the negotiation process. Failure to propose alternate terms and conditions during the procurement process (the RFP process prior to selection as successful Offeror) is an explicit agreement by the Offeror that the contractual terms and conditions contained herein are accepted by the
Offeror.
P. Offeror’s Terms and Conditions
Offerors must include with their proposal and/or during clarification phase a complete list of any additional/modified terms and conditions they wish to have considered for inclusion in the final contract.
Offerors must clearly identify the specific section(s) of the City’s draft contract they propose to modify and provide the exact language they wish to substitute or add. Failure to submit proposed terms at the time of proposal submission may result in the City deeming those terms waived during contract negotiations.
Q. Contract Deviations
Any additional terms and conditions, which may be the subject of negotiation (such terms and conditions having been proposed during the procurement process, that is, the RFP process prior to selection as successful Offeror), will be discussed only between the City and the Offeror selected and shall not be deemed an opportunity to amend the Offeror’s proposal.
R. Offeror Qualifications
The Evaluation Committee may make such investigations as necessary to determine the ability of the potential Offeror to adhere to the requirements specified within this RFP. The Evaluation Committee will reject the proposal of any potential Offeror who is not a Responsible Offeror or fails to submit a
Responsive Offer as defined in NMSA 1978, Sections 13-1-83 and 13-1-85.
S. Right to Waive Minor Irregularities
The Evaluation Committee, upon approval from the CPO, reserves the right to waive minor irregularities. The Evaluation Committee also reserves the right to waive mandatory requirements, if all of the otherwise responsive proposals failed to meet the same mandatory requirements and the failure to do so does not otherwise materially affect the procurement. This right is at the sole discretion of the
Evaluation Committee and CPO.
T. Change in Contractor Representatives
The City reserves the right to require a change in the contractor’s assigned representative if, in the City’s judgment, the individual is not adequately meeting the City’s needs. If multiple representatives are assigned, the City may require changes to any or all of them as deemed necessary.
U. Notice of Penalties
NMSA 1978, Sections 13-1-28 through 13-1-199, imposes civil, and misdemeanor and felony criminal penalties for its violation. In addition, the New Mexico criminal statutes impose felony penalties for bribes, gratuities, and kickbacks.
V. City’s Rights
The City, in agreement with the Evaluation Committee reserves the right to accept all or a portion of a potential Offeror's proposal.
W. Right to Publish
Throughout the duration of this procurement process and contract term, Offerors and contractors must secure from the City written approval prior to the release of any information that pertains to the potential work or activities covered by this procurement and/or City contracts deriving from this procurement.
Failure to adhere to this requirement may result in disqualification of the Offeror’s proposal or removal from the contract.
X. Ownership of Proposals
All documents submitted in response to the RFP shall become property of the City. If the RFP is cancelled, the electronic record shall be closed, and all proposals shall remain confidential.
Y. Confidentiality
Any confidential information provided to, or developed by, the contractor in the performance of the contract resulting from this RFP shall be kept confidential and shall not be made available to any individual or organization by the contractor without the prior written approval of the City.
The Contractor(s) agrees to protect the confidentiality of all confidential information and not to publish or disclose such information to any third party without the City’s written permission.
Z. Electronic Mail Address Required
A large part of the communication regarding this procurement will be conducted by electronic mail
(email). Offeror must be registered and have a valid email address to receive correspondences.
AA. Use of Electronic Versions of This RFP
This RFP is being made available by electronic means. In the event of conflict between a version of the
RFP in the Offeror’s possession and the version maintained by the CPD, the Offeror acknowledges that the version maintained by the CPD shall govern. Please refer to:https://procurement.opengov.com/portal/santafenm/projects/324046
BB. Campaign Contribution Disclosure Form
Offeror must complete, sign, and return the Campaign Contribution Disclosure Form, as a part of their proposal. This requirement applies regardless of whether a covered contribution was made or not made for the positions of Governor and Lieutenant Governor, City Officials or other identified official. Failure to complete and return the signed, unaltered form will result in Offeror’s disqualification.
CC. Disclosure Regarding Responsibility
1. Any prospective Contractor and any of its Principals who enter a contract greater than sixty thousand dollars ($60,000.00) with any state agency or local public body for professional services, tangible personal property, services or construction agrees to disclose whether the Contractor, or any principal of the Contractor’s company:
a. is presently debarred, suspended, proposed for debarment, or declared ineligible for award of contract by any federal entity, state agency or local public body;
b. has within a three-year period preceding this offer, been convicted in a criminal matter or had a civil judgment rendered against them for:
i. the commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (federal, state or local) contract or subcontract;
ii. violation of Federal or state antitrust statutes related to the submission of offers; or
iii. the commission in any federal or state jurisdiction of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, tax evasion, violation of
Federal criminal tax law, or receiving stolen property;
c. is presently indicted for, or otherwise criminally or civilly charged by any (federal state or local) government entity with the commission of any of the offenses enumerated in paragraph A of this disclosure;
d. has, preceding this offer, been notified of any delinquent Federal or state taxes in an amount that exceeds $3,000.00 of which the liability remains unsatisfied. Taxes are considered delinquent if the following criteria apply.
i. The tax liability is finally determined. The liability is finally determined if it has been assessed. A liability is not finally determined if there is a pending administrative or judicial challenge. In the case of a judicial challenge of the liability, the liability is not finally determined until all judicial appeal rights have been exhausted.
ii. The taxpayer is delinquent in making payment. A taxpayer is delinquent if the taxpayer has failed to pay the tax liability when full payment was due and required. A taxpayer is not delinquent in cases where enforced collection action is precluded.
iii. Have within a three-year period preceding this offer, had one or more contracts terminated for default by any federal or state agency or local public body.)
2. Principal, for the purpose of this disclosure, means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity or related entities.
3. Following award, the Contractor shall promptly provide written notice to the individuals listed in the contract’s Notice section if, at any time during the term of the contract, the Contractor becomes aware that any part of its prior disclosure was inaccurate or has become inaccurate due to changed circumstances.
4. Disclosure of any relevant circumstances under this requirement will not automatically result in termination of the contract. However, such disclosures will be considered when evaluating the
Contractor’s responsibility and capacity to perform under the contract. Failure to provide a required disclosure, or to submit additional information upon request, may result in a determination that the
Offeror is nonresponsive
5. Nothing contained in the foregoing shall be construed to require establishment of a system of records to render, in good faith, the disclosure required by this document. The knowledge and information of a Contractor is not required to exceed that which is the normally possessed by a prudent person in the ordinary course of business dealings.
6. The disclosure requirement provided is a material representation of fact upon which reliance was placed when making an award and is a continuing material representation of the facts during the term of this Agreement. If during the performance of the contract, the Contractor is indicted for or otherwise criminally or civilly charged by any government entity (federal, state, or local) with commission of any offenses named in this document the Contractor must provide immediate written notice to the CPO or other party to this Agreement. If it is later determined that the Contractor knowingly rendered an erroneous disclosure, in addition to other remedies available to the
Government, the CPO may terminate the involved contract for cause. Still further the CPO may suspend or debar the Contractor from eligibility for future solicitations until such time as the matter is resolved to the satisfaction of the CPO
DD. Local Preferences
The City recognizes the value of revenue derived from local businesses and shall procure goods and/or services locally, when possible, pursuant to Ordinance and the City of Santa Fe Procurement Manual.
The city’s preferences will be applied except for purchases using state funds, federal funds, and grant funds. Applicable City, state and federal law and regulations govern procurements using City, state, or federal funds.
1. Local Preference Qualification
To qualify for a local preference, an Offeror must attach a state of New Mexico Taxation and
Revenue Department-issued, Resident Business certification of eligibility to its proposal, showing that the business is located within the Santa Fe municipal limits. If a proposal is received without a copy of the appropriate State of New Mexico Taxation and Revenue Department issued preference
Certificate, the preference will not be applied. A valid resident business certificate is issued by the
Taxation and Revenue Department pursuant to NMSA 1978, Section 13-1-22.
a. When the City makes a purchase using a formal request for proposals process, not including contracts awarded on a point-based system, the City shall award additional 3% of the total weight of all the factors used in evaluating the proposal to a local resident business. The City shall award an additional 3% of the total weight of all the factors used in evaluating the proposal to a business with all resident business subcontractors.
b. When the City makes a purchase using a formal request for proposals’ process and the contract is awarded based on a point-based system, the City shall award additional points equivalent to 3% of the total possible points to a local resident business. The City shall award an additional 3% of the total possible points to a business with all resident business subcontractors.
When city preferences apply, the maximum available local preference shall be 6%.
When state preferences apply, the maximum available preference shall be 10% and shall be applied as described in NMSA 1978, Section 13-1-21.
Additionally, only one submitted preference will be applied per solicitation, not multiple.
Applications are available for download at: http://www.tax.newmexico.gov/Businesses/in-state-veteran-preference-certification.aspx
c. Solicitations above One Million Dollars ($1,000,000)
i. The City shall deem a bid or proposal submitted by a resident business to be 6% lower than the bid submitted, if and only if at least 50% of the subcontracted services go to subcontractors who are resident businesses.
ii. The City shall deem the bid or proposal submitted by a non-local resident business to be 3% lower than the bid submitted, if and only at least 50% of the sub- contracted services go to subcontractors who are resident businesses.
The Local Preferences shall not apply if the expenditure for the resulting agreement includes federal funds.
EE. Living Wage
Compliance with the City of Santa Fe and Santa Fe County’s Minimum Wage Rate Ordinances (Living
Wage Ordinances). The vendor must comply with the current living wage rate ang requirements posted on this page https://santafenm.gov/economic-development/business-resources/living-wage-information
III. RESPONSE FORMAT AND ORGANIZATION
NUMBER OF RESPONSES
Offerors shall complete and submit only one response to this RFP through OpenGov.
http://www.tax.newmexico.gov/Businesses/in-state-veteran-preference-certification.aspx http://www.tax.newmexico.gov/Businesses/in-state-veteran-preference-certification.aspx
Confidential Information: If proposals contain confidential information, as defined in the Definition of
Terminology, Offerors must submit two (2) separate ELECTRONIC technical files. Name the files accordingly:
• One (1) ELECTRONIC version of the requisite proposals identified above as Confidential (unredacted) versions for evaluation purposes (example file name, FY26-TRFP-072 - Acme Corp – Confidential
Technical). Unredacted versions must be clearly marked as “UNREDACTED” or
"CONFIDENTIAL" on the first page of the electronic file; and
• One (1) redacted ELECTRONIC, for the public file, to facilitate eventual public inspection of the non-confidential version of Offerors' proposals. Redacted versions must be clearly marked as
“REDACTED” on the first page of the electronic file. (Example file name, FY26-TRFP-072 - Acme
Corp – Redacted Technical)
• The maximum page limit for the entire Proposal is ## pages
IV. SCOPE OF WORK
<This section is used by the department to provide a Detailed Scope of Work that will also be included in the Draft Contract and the resulting contract.>
Scope of Work
The consultant shall provide the coordination, document development, and project management necessary to complete all three documents. This effort shall include:
• Conducting an initial review and gap analysis of existing Airport documents, procedures, and applicable
FAA requirements.
• Conducting onsite meetings and interviews with Airport Operations, Airport Maintenance, Aircraft
Rescue and Firefighting (ARFF), and other applicable Airport personnel to understand existing operational practices and capabilities.
• Coordinating with Airport departments, tenants, outside agencies, and other applicable stakeholders throughout the development process.
• Facilitating document review periods, stakeholder meetings, and coordination necessary to obtain and incorporate applicable comments.
• Maintaining communication with the Airport regarding project progress, outstanding information, coordination needs, and anticipated completion dates.
• Coordinating with the FAA throughout the development process and addressing applicable FAA comments and requested revisions.
• Providing final documents in professionally formatted, editable electronic format and PDF.
• Providing final revisions and incorporating applicable Airport and stakeholder comments prior to acceptance.
Airport Certification Manual (ACM)The consultant shall develop a complete and comprehensive ACM incorporating all applicable requirements under 14 CFR Part 139 and applicable FAA guidance. The ACM shall accurately reflect the Airport's current operations, procedures, responsibilities, and certification programs, including but not limited to:
• Airport operational responsibility, succession, and assigned duties.
• Movement areas, safety areas, pavement, markings, signage, and lighting.
• Training, records, self-inspections, and airport condition reporting.
• Aircraft rescue and firefighting (ARFF) facilities, equipment, staffing, and procedures.
• Fueling and hazardous materials, vehicle and pedestrian controls, and obstruction management.
• Wildlife hazard management, public protection, construction and unserviceable areas, and navigational aid protection.
• Applicable emergency planning requirements and references to the Airport Emergency Plan.
Snow and Ice Control Plan (SICP) The consultant shall develop a complete and comprehensive SICP reflecting the Airport's current winter operations, available equipment, staffing, responsibilities, and snow removal procedures. The SICP shall include, but not be limited to:
• Review and evaluation of existing snow and ice control procedures.
• Airport snow removal priorities and designated operational areas.
• Personnel responsibilities, training, and equipment requirements.
• Snow removal procedures for movement areas, non-movement areas, ramps, and designated priority surfaces.
• Snow accumulation monitoring, reporting, and airport condition assessments.
• Coordination with airport tenants, airlines, and other affected stakeholders.
• Snow disposal locations and applicable restrictions.
• Applicable FAA requirements and coordination with the FAA, as necessary.
Airport Emergency Plan (AEP) The consultant shall perform a complete and comprehensive rewrite of the AEP. This effort shall include extensive coordination with local, state, federal, and other emergency response agencies, Airport departments, tenants, and applicable stakeholders. The consultant shall be responsible for facilitating the coordination necessary to develop an accurate, comprehensive, and operationally practical emergency plan.
The AEP development shall include, but not be limited to:
• Review and evaluation of the existing AEP and applicable FAA requirements.
• Identification of participating agencies, stakeholders, and emergency response partners.
• Coordination and facilitation of interagency meetings to establish emergency response roles, responsibilities, and procedures.
• Development and revision of emergency response procedures for applicable emergency scenarios.
• Establishment of agency notification procedures, communication protocols, and emergency coordination responsibilities.
• Review of emergency response resources, equipment, airport access points, staging areas, and response capabilities.
• Coordination of agency reviews, comments, and revisions throughout the development process.
• Incorporation of agency feedback and stakeholder input into the final document.
• Development of procedures for emergency exercises, training, and ongoing plan maintenance.
• Final coordination and submission of the completed AEP to the FAA, as applicable.
Deliverables The selected consultant shall provide complete, comprehensive, and professionally organized updates and rewrites of the following Airport certification and operational documents for Santa Fe Regional Airport: the
ACM, SICP, and AEP. All documents shall incorporate applicable FAA requirements and accurately reflect the
Airport's current operations, procedures, responsibilities, resources, and programs.
V. EVALUATION
Scoring
The Evaluation Committee will evaluate and score proposals based on the information provided in this document and the Offerors’ demonstrated understanding of the RFP’s objectives. Proposals will be evaluated according to the criteria listed below, which have been identified as critical to the success of the projects.
No. Rating Criteria Points
1 Organizational Experience 450
2 Organizational References 100
3 Mandatory Specification 375
4 Cost Proposal 75
5 Local Preference 3% or 6% of the total available points*
*See local preference requirements below
TECHNICAL AND BUSINESS SPECIFICATIONS
TECHNICAL SPECIFICATIONS
1. Organizational Experience
Offeror must:
A. Provide a detailed narrative thoroughly describing how the Offeror has supplied expertise for similar contracts and must include the extent of their experience, expertise and knowledge as a provider of
ACM, AEP, and SICP per 14 CFR Part 139, Certification of Airports . All experience, expertise and knowledge as a provider of ACM, AEP, and SICP per 14 CFR Part 139, Certification of Airports provided to city, state, and private sector will be considered;
B. Provide a detailed bio of all key personnel Offeror proposes to use in performance of the resulting contract, should Offeror be awarded. Key personnel is identified as all individuals that will be tasked through the firm to have an active role in this . Offeror must include key personnel education, work experience, relevant, and certifications.
C. Describe at least two project successes of a rewrite of and ACM, AEP, and SICP that was approved by the FAA and specific airport. Include how each experience improved the Offeror’s services.
2. Organizational References
Offeror must provide a list of a minimum of three (3) references from similar projects/programs performed for private, city, state, or large local government clients within the last three (3) years.
Offeror shall include the following Business Reference information as part of its proposals:
a. Client name;
b. Project description;
c. Project dates (starting and ending);
d. Technical environment (i.e., Software applications, Internet capabilities, Data communications, Network, Hardware);
e. Staff assigned to reference engagement that will be designated for work per this RFP; and
f. Client project manager name, telephone number, fax number and email address.
Offerors are required to submit Organizational Reference Questionnaires (“Questionnaire”), to the business references it lists. The business references must submit the Questionnaire directly to the designee identified. The business references must not return the completed Questionnaire to the Offeror. It is the
Offeror’s responsibility to ensure the completed forms are submitted on or before the date indicated in the
Timeline, for inclusion in the evaluation process.
Organizational References that are not received or are not complete, may adversely affect the Offeror’s score in the evaluation process. Offerors are encouraged to specifically request that their Organizational References provide detailed comments.
3. Mandatory Specification
A. Airport Experience and Qualifications
• Provide three (3) examples of previous projects within the last ten (10) years demonstrating knowledge, qualification, experience, in rewriting an ACM for Part 139 airports.
• Provide three (3) examples of previous projects within the last ten (10) years demonstrating knowledge, qualification, experience, in rewriting an AEP for Part 139 airports.
• Provide three (3) examples of previous projects within the last ten (10) years demonstrating knowledge, qualification, experience, in rewriting an SICP for Part 139 airports.
Examples should include all elements necessary in reviewing, drafting, and completing an FAA approved
ACM, AEP, and SICP.
B. Project Schedule and Deliverables - provide three (3) examples of previous projects with the information to demonstrate adherence to key milestone and the ability to deliver a professionally prepared version of all three documents and their timelines for completion.
BUSINESS SPECIFICATIONS
BUSINESS SPECIFICATIONS
1. Cost
Offerors must complete the Cost Response Sections. Cost will be measured by a total calculated for the complete rewrite of the ACM, AEP, and SICP. All charges listed in the Cost must be justified and evidence of need documented in the proposal.
DESCRIPTION OF EVALUATION
EVALUATION FACTORS
Organizational Experience
Points will be awarded based on the thoroughness and clarity of Offeror’s response in this Section. The
Evaluation Committee will also weigh the relevancy and extent of Offeror’s experience, expertise and knowledge; and of personnel education, experience and certifications/licenses. In addition, points will be awarded based on Offeror’s candid and well-thought-out response to successes and failures, as well as the ability of the Offeror to learn from its failures and grow from its successes.
Organizational References
Points will be awarded based upon an evaluation of the responses to a series of questions on the Organizational
Reference Questionnaire. Offeror will be evaluated on references that show positive service history, successful execution of services and evidence of satisfaction by each reference. References indicating significantly similar services/scopes of work and comments provided by a submitted reference will add weight and value to a recommendation during the evaluation process. Points will be awarded for each individual response up to 1/3 of the total points for this category. Lack of a response will receive zero (0) points.
The Evaluation Committee may contact any or all business references for validation of information submitted.
If this step is taken, the Procurement Manager and the Evaluation Committee must all be together on a conference call…