About this file

This document is an Estimated Construction Schedule for the Riverview Avenue Landslide Remediation project, involving Slide S1 and Slide S3 in the 26th Ward - Perry North, City of Pittsburgh, Allegheny County, Pennsylvania (City Project Nos. 220054 & 220055). The comprehensive schedule spans 158 total construction days, starting from the bid opening on 3/31/2025 and concluding on 11/7/2025. Key project activities include designing traffic management plans, road closure notices, utility protection, excavation and construction of geosynthetic reinforced soil (GRS) slope fill structures, roadway repaving, guiderail installation, seeding, tree planting, and site demobilization.

The project timeline details critical milestones such as material ordering (28 days), traffic control (107 days), and the primary construction phase of excavating and constructing GRS slope fill structures (55 days). The schedule demonstrates a methodical approach to landslide remediation, with specific durations allocated for each construction phase, including site preparation, infrastructure restoration, and landscaping. The project appears to be funded through the City of Pittsburgh's infrastructure budget, focusing on stabilizing and repairing critical road infrastructure affected by recent landslides in the Perry North neighborhood.

View the file

Other files

File Type Posted
RIVERVIEW_AVENUE_LANDSLIDE_REMEDIATION_-_SLIDE_S1_&_SLIDE_S3.pdf PDF
S1_S3_Gen_&_Spec_Provs_.pdf PDF
S1_PS&E_Plans_.pdf PDF
S3_PS&E_Plans.pdf PDF
PA_Prevailing_Wage_Rates-_Riverview.pdf PDF
S1_PS&E_Plans.pdf PDF
S1_S3_Gen_&_Spec_Provs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3/10/2025

RIVERVIEW AVENUE LANDSLIDE REMEDIATION - SLIDE S1 & SLIDE S3

26TH WARD - PERRY NORTH, CITY OF PITTSBURGH

ALLEGHENY COUNTY, PENNSYLVANIA

CITY PROJECT NOS. 220054 & 220055

ID Task Name Duration, Days

Start

Date

Finish

Date

1 Bid Opening 0 3/31/2025 3/31/2025

2 Notice To Proceed 0 6/2/2025 6/2/2025

3 Prepare Narrative Schedule(s) 1 6/2/2025 6/3/2025

4 Order and Obtain Material 28 6/3/2025 7/1/2025

5 Design MPT 45 6/3/2025 7/18/2025

6 Notice and MPT for Road Closure 5 7/18/2025 7/23/2025

7 Traffic Control 107 7/23/2025 11/7/2025

8 Verify and Protect Existing Utilities. 1 7/23/2025 7/24/2025

9 Mobilize 4 7/24/2025 7/28/2025

10 Establish Survey Control & Work Limit Controls 10 7/28/2025 8/7/2025

11 Remove and Dispose of the Existing Guide Rail 2 8/7/2025 8/9/2025

12 Install E&SPC Devices 3 8/9/2025 8/12/2025

13 Clear and Grub Site 2 8/12/2025 8/14/2025

14 Sawcut and Remove Existing Bituminous Pavement 2 8/14/2025 8/16/2025

15 Excavate and Construct the GRS Slope Fill Structures (Slide S1 & Slide S3) 55 8/16/2025 10/10/2025

16 Prepare the Subgrade and Install the Granular Subbbase 2 10/10/2025 10/12/2025

17 Mill and Repave the Roadway with Bituminous Concrete 10 10/12/2025 10/22/2025

18 Install Type 31-S Guiderail 2 10/22/2025 10/24/2025

19 Provide Seeding and Soil Supplements,and Mulch 1 10/24/2025 10/25/2025

20 Planting Trees 10 10/25/2025 11/4/2025

21 Line Painting 1 11/4/2025 11/5/2025

22 Remove Traffic Control Devices and Reopen Travel Lanes 1 11/5/2025 11/6/2025

23 De-Mobilize 1 11/6/2025 11/7/2025

Total Construction Duration 158 6/2/2025 11/7/2025

ESTIMATED CONSTRUCTION SCHEDULE