ABSTRACT OF OFFERS - CONSTRUCTION

2. Date Issued: 6/25/2020 3. Date Open:

8/10/2020 Page No.

4. Issuing Office Name and Title of Certifying Official Typed/Signature/Date

Sharla Goforth, Contract Specialist

5. Project Title

6. Number of Amendments Issued: B. Bid Security: Yes B. Bid Security: Yes B. Bid Security: Yes B. Bid Security: Yes B. Bid Security: Yes B. Bid Security: Yes B. Bid Security: Yes

1 Amendments Acknow-ledged Yes Amendments

Acknow-ledged Yes Amendments Acknow-ledged Yes Amendments

Acknow-ledged Yes Amendments Acknow-ledged Yes Amendments

Acknow-ledged Yes Amendments Acknow-ledged Yes

7A. Item No.

7B. Description of Offered Item

7C Est Quantity E. Unit Price F. Est.

Amount E. Unit Price

F. Est.

Amount

E. Unit Price

F. Est.

Amount

E. Unit Price

F. Est.

Amount

E. Unit Price

F. Est.

Amount

E. Unit Price

F. Est.

Amount

E. Unit Price

F. Est.

Amount

Site 1

1 Mobilization 1 $2,000.00 $2,000.00 $5,000.00 $5,000.00 $14,000.00 $14,000.00 $8,100.00 $5,000.00 $5,000.00 $5,500.00 $5,500.00 $7,393.28 $7,393.28

2 Rock Riprap, Installed 173 $52.00 $8,996.00 $121.30 $20,984.90 $42.00 $7,266.00 $96.88 $52.00 $8,996.00 $76.00 $13,148.00 $67.77 $11,724.21

3 Riprap Bedding, Installed 30 $41.00 $1,230.00 $86.53 $2,595.90 $31.30 $939.00 $1,500.00 $275.00 $8,250.00 $50.00 $1,500.00 $107.20 $3,216.00

4 Crusher Run 20 $28.00 $560.00 $41.88 $837.60 $28.25 $565.00 $1,000.00 $34.00 $680.00 $45.00 $900.00 $86.25 $1,725.00

5 Debris Removal 1 $1,200.00 $1,200.00 $2,505.00 $2,505.00 $12,800.00 $12,800.00 $3,000.00 $2,000.00 $2,000.00 $4,000.00 $4,000.00 $4,435.97 $4,435.97

Site 2

6 Mobilization 1 $2,000.00 $2,000.00 $5,000.00 $5,000.00 $14,000.00 $14,000.00 $8,100.00 $3,917.00 $3,917.00 $5,500.00 $5,500.00 $16,265.22 $16,265.22

7 Rock Riprap, Installed 680 $52.00 $35,360.00 $61.76 $41,996.80 $42.00 $28,560.00 $38,080.00 $52.00 $35,360.00 $76.00 $51,680.00 $56.68 $38,542.40

8 Riprap Bedding, Installed 123 $41.00 $5,043.00 $42.78 $5,261.94 $31.30 $3,849.90 $6,150.00 $95.00 $11,685.00 $50.00 $6,150.00 $69.00 $8,487.00

9 Crusher Run 40 $28.00 $1,120.00 $34.80 $1,392.00 $28.25 $1,130.00 $2,000.00 $34.00 $1,360.00 $45.00 $1,800.00 $77.63 $3,105.20

10 Debris Removal 1 $1,200.00 $1,200.00 $3,480.00 $3,480.00 $12,800.00 $12,800.00 $3,000.00 $2,500.00 $2,500.00 $4,000.00 $4,000.00 $11,829.25 $11,829.25

Site 10

11 Mobilization 1 $2,000.00 $2,000.00 $5,000.00 $5,000.00 $14,000.00 $14,000.00 $8,100.00 $3,100.00 $3,100.00 $5,500.00 $5,500.00 $9,241.60 $9,241.60

12 Rock Riprap, Installed 332 $52.00 $17,264.00 $90.86 $30,165.52 $42.00 $13,944.00 $18,592.00 $52.00 $17,264.00 $70.00 $23,240.00 $62.84 $20,862.88

13 Riprap Bedding, Installed 47 $41.00 $1,927.00 $73.80 $3,468.60 $31.30 $1,471.10 $2,350.00 $165.00 $7,755.00 $50.00 $2,350.00 $86.25 $4,053.75

14 Crusher Run 20 $28.00 $560.00 $46.60 $932.00 $28.25 $565.00 $1,000.00 $34.00 $680.00 $45.00 $900.00 $86.25 $1,725.00

15 Debris Removal 1 $1,200.00 $1,200.00 $3,200.00 $3,200.00 $12,800.00 $12,800.00 $3,000.00 $1,815.00 $1,815.00 $4,000.00 $4,000.00 $7,393.28 $7,393.28

CR1200 & Waresha Creek

16 Mobilization 1 $2,000.00 $2,000.00 $5,000.00 $5,000.00 $14,000.00 $14,000.00 $8,100.00 $3,100.00 $3,100.00 $5,500.00 $5,500.00 $44,359.69 $44,359.69

17 Rock Riprap, Installed 2876 $46.00 $132,296.00 $44.50 $127,982.00 $42.00 $120,792.00 $161,056.00 $62.00 $178,312.00 $76.00 $218,576.00 $56.68 $163,011.68

18 Riprap Bedding, Installed 684 $38.00 $25,992.00 $23.11 $15,807.24 $31.30 $21,409.20 $34,200.00 $107.00 $73,188.00 $55.00 $37,620.00 $66.54 $45,513.36

19 Crusher Run 30 $28.00 $840.00 $48.08 $1,442.40 $28.25 $847.50 $1,500.00 $34.00 $1,020.00 $50.00 $1,500.00 $81.33 $2,439.90

20 Debris Removal 1 $3,500.00 $3,500.00 $6,938.00 $6,938.00 $12,800.00 $12,800.00 $7,780.00 $2,300.00 $2,300.00 $4,000.00 $4,000.00 $25,137.16 $25,137.16

Grand Total $246,288.00 $288,989.90 $308,538.70 $316,704.88 $368,282.00 $397,364.00 $430,461.83

ERS Inc. Consolidated Construction & Eng

1635 Lelia Drive, Suite 202 101 Lakeforest Bldv, Suite 270 Jackson, MS 39216 Gaithersburg, MD 20877Fort Necessity, LA 71243

Osage County EWP - Package 1

PO Box 863 Stillwater, OK 74076

Meridian Contracting, Inc.

17500 S. Sooner Rd Norman, OK 73071

1121 S. Main St.

Elk City, OK 73644

405 Executive Drive Langhorne, PA 19047

824 Chester Rd

Offers

ECW

USDA-FPAC Business Center Acq Division - Operations Branch - Section 3

1400 Independence Ave SW, RM 6801-S, Washington, DC 20250

1. Solicitation Number:

12FPC220B0008

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

MK Excavation, LLC WP Construction Academy Consulting, LLC abstract

2020-08-29T17:05:09-0500
SHARLA GOFORTH