S02 Upgrade Sanitary Sewer SOW 2021128 rev1.pdf
PDF 204 KB Posted
- Attached to
- Z2NZ--631-21-003 Upgrade Sanitary Sewer Phase 2
- Solicitation number
- 36C24122B0003
About this file
This statement of work outlines requirements for an upgrade sanitary sewer project at the Edward P. Boland VA Medical Center campus in Leeds, Massachusetts. The contractor will remove and replace approximately 6,000 linear feet of exterior sanitary sewer piping and conduct associated manhole work according to the contract documents over a 450-day period of performance. The contractor must provide a project superintendent with at least 10 years of construction experience and 5 years as a superintendent on similar projects. Additional requirements include following VA, OSHA, EPA, and state regulations; obtaining necessary permits; adhering to safety, access, parking, storage, and waste removal protocols; and attending weekly progress meetings. The solicitation number for this opportunity is 36C24122B0003.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Edward P. Boland VAMC, Central Western Massachusetts Healthcare System
421 N Main Street
Leeds, MA 01053 December 21, 2021
631-21-003-SOW-C Page 1 of 10
Construction Statement of Work for Upgrade Sanitary Sewer Phase 2
Project Number: 631-21-003
Location(s):Edward P. Boland Campus VAMC CWM – Campus Wide
1 Overview
1.1 General Intent
The Contractor provide professional services to include all labor, transportation, materials, apparatus, tools, equipment and permits necessary to in accordance with this design scope of work.
All work must meet VHA, OSHA, EPA, and Mass DEP standards
1.2 Project Specific Scope of Work - Upgrade Sanitary Sewer Phase 2
After award, but prior to the start of any field work, the contractor shall contact the Project Engineer/Manager (i.e. COR) to review proposed methods and plans for completion of work and to review infection control procedures, interim life safety procedures, above ceiling and wall penetration permits and hot permits. Field work may not commence until these plans have been approved as detailed below.
The project consists of removing and replacing approximately 6000 LF of exterior sanitary sewer piping as well as associated manhole work as described in the contract documents. All sewer lines will require temporary bypass during construction. The project also includes limited relining of sewer pipes, see contract documents for details.
Provide project superintendent with a minimum of [10] years of experience in construction with at least [5] of those years as a superintendent on projects similar in size and complexity.
The individual must be familiar with the requirements of OSHA and have experience in the areas of hazard identification and safety compliance in addition to safety training requirements indicated elsewhere in the project documents. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The project superintendent shall be dedicated to this project only and not assigned on other contracts. The Contractor shall submit resume showing proof of qualifications to the Contracting Officer within 10 days of NTP.
1.3 General Scope Items
The following is a list of general scope considerations:
1. Meet with VA Facilities staff, review existing drawings and estimates, and perform field work necessary to determine required materials and equipment
631-21-003-SOW-C Page 2 of 10
2. When conflict exist between documents the order of precedence shall be specifications then drawings. Any conflicts shall be identified to the COR and be resolved using the RFI process to allow for proper documentation and correction as necessary.
3. Permitting (external to VA):
a. City of Northampton permits, and waivers are the responsibility of the contractor. The contractor must be prepared to attend City of Northampton committee meetings as required.
b. All Massachusetts Department of Environmental Protection permits, and waivers are the responsibility of the contractor. This includes, but not limited to all environmental and hazardous material permits.
c. Contractor is required to notify Dig Safe and to secure an excavating permit from Engineering, or other applicable agency as designated by the Contracting Officer before proceeding with any exterior on-site excavating or digging. The Engineer must have a minimum of 72 hours’ notice from the Contractor prior to permit being secured or as applicable by Government agencies.
4. All field work shall be scheduled at least 72 hours in advance with VA Facilities Management.
5. The site shall be left clean of all construction debris and hazardous materials. At the end of each workday, the contractor shall clean up the work and storage areas and stack all materials in a manner approved by the Contracting Officer or his/her designated representative.
6. At the end of each day work areas must be made safe and/or secured.
7. Upon completion of a project, the contractor shall ensure that all dirt, trash, and debris resulting from the construction operations are removed from the work area. Unless directed otherwise in the contract or by the Contracting Officer, disposal of debris shall be made at the contractor’s expense and shall be delivered to a state approved disposal site located off the VA grounds. Debris shall not be left in such a manner that wind or other weather conditions can cause the debris to be scattered outside the work area or inside the facilities via local foot traffic. The hauling and disposal of excess fill material including rock, gravel, sod, broken concrete or asphalt, plaster, etc., shall be the responsibility of the contractor. Disposal shall be in accordance with applicable state and local regulations.
8. Coordinate with VA CWM HCS GEMS coordinator Rob Michalik at 413-584-4040 x 2330 for the signing of the waste manifests.
9. Design and installation to meet latest edition of the NEC, NFPA, and all applicable building codes.
10. Submit product data and shop drawings for all materials prior to installation. Submittals and shop drawings shall be approved by COR.
631-21-003-SOW-C Page 3 of 10
11. All work shall be performed in accordance with Massachusetts DLS regulations and OSHA codes.
12. Contractor shall submit for approval a submittal register within 30 calendar days of the NTP of the project.
1.4 Site Access and Management Requirements
The contractor shall be solely responsible for the management, including all associated labor, equipment, materials, mailing costs, and inspection, to meet the requirements of the project.
The contractor must have the following additional requirements before working on site:
1. Contractor badge must be obtained and visibly worn by contractor or representative at all times while on campus
2. Negative TB Test, within the past calendar year
3. Clear Face Shield or Safety Glasses in patient care areas
4. Annual influenza shot is required to perform work on campus.
5. Covid-19 Requirements-contractor is subject to the VHA Supplemental Contract
Requirements for Combatting Covid-19 and facility specific requirements (subject to frequent change)
a. Approved surgical or 2-layer cloth mask with no vent. Must be replaced when damaged or soiled
b. Pre and weekly negative COVID test while working (test available onsite free of charge to contractor)
c. Daily visit at check-in station for COVID and temperature screening
d. Staff experiencing any symptoms of illness will refrain from any on-site work until asymptomatic
e. Temperature checks are currently performed at Liberty Building 1. If at any time an employee of the A/E firm is found in deficiency of the listed a stop work order will be issued for safety of the campus.
These requirements are applicable to all contractor employees and subcontractors working in and around campus building unless stated otherwise by COR. The contractor is ultimately responsible for the behavior of employees and subcontractors.
Questions or concerns may be addressed by the COR.
1.5 List of Attachments
The following list of documents are attached to this SOW for Contractor use and incorporation into the project documents:
1. Upgrade Sanitary Sewer Phase 2 631-21-003 Bid Set Plans (set of 2)
2. Upgrade Sanitary Sewer Phase 2 631-21-003 Bid Set Specifications
3. RFI Form
4. Infection Control Risk Assessment and Permit
631-21-003-SOW-C Page 4 of 10
5. Hot Work Permit
6. Life Safety Risk Assessment
7. Confined Space Permit
8. Daily Construction Log (Sample Form)
9. Construction Safety Guidebook | Healthcare Environment and Facilities Programs
(va.gov) Note list is not necessarily exhaustive of necessarily exhaustive.
2 Submittals
Submittals may be sent after the notice to proceed NTP is received by the contractor.
The contractor shall provide the following submittals as soon as they are available or by the required date(s) communicated by the COR:
• All submittal items listed in the contract documents.
• Certification from the Contractor/Installer that the system(s) specified meets all applicable codes as well as manufacturer, designer, and insurance requirements as required by the Government.
• Safety Data Sheets (SDS)
• Operation and Maintenance Manuals for new equipment
• As-built drawings
• Coordination Drawing Checklist
631-21-003-SOW-C Page 5 of 10
3 Proposed Schedule
All on-site work (including cleanup) shall take place during the following times, unless otherwise approved by the COR:
07:00-16:30h Monday through Friday
Off-hour work for activities impacting normal operations or scheduling conflicts are generally 17:00-06:00 Monday- Friday and anytime Saturday and Sunday.
Holidays excepted unless other times are arranged in advance and approved in writing by the Project COR.
The total period of performance for this project is 450 calendar days; the first 45 days shall be utilized for administrative time to complete preconstruction submissions and other preparation prior to the start of construction. The remaining work shall be completed with the remaining period of performance of 405 calendar days.
3.1 Project Coordination
The following tasks are anticipated to have significant campus impact or conflicts and may require special consideration and coordination to ensure satisfactory completion:
1. Sewer shutdowns to occupied buildings.
2. Excavations impacting campus traffic.
3. Coordination with other contracts.
4. Others as determined by COR and contractor.
4 Code Requirements and Specifications
Refer to the contract documents. If the contract documents do not include an applicable specification section the VA master specification PG-18-1 can be found here VA Master Specifications (PG-18-1) | WBDG - Whole Building Design Guide. The Technical Information Library is a standard source for VA guidance found here TIL Catalog - Office of Construction & Facilities Management (va.gov).
5 Warranties
See FAR clause 52.246-21.
6 Work Location and Restrictions
The work site location is at the Edward P. Boland Campus- VA Central Western Massachusetts Healthcare System. The contract work is intended to be limited to Edward P.
Boland Campus VAMC CWM – Campus Wide.
631-21-003-SOW-C Page 6 of 10
When the contractor’s work interferes with hospital functions, such as when work produces excessive noise, odors, dust, utility service interruptions, or other interferences with normal hospital operations that cannot be contained within the area of work, the contractor shall schedule said work at other than normal hours and as directed by the COR.
6.1 Project Safety
Contractor shall comply with the Construction Safety Guide of the site and other applicable standards as noted in the sections 1 and 4 and their subsections.
FAR Clause 52.236-13 subparagraph (f) is invoked:
6.2 Penetrations of Fire and Smoke Barriers
Prior to any installation of equipment, cables, power connections, conduit, piping or other work that penetrates a smoke or fire barrier, all such work must be approved by the site specific Facilities Management Service (FMS) via the COR. An above ceiling/penetration permit must be secured from FMS prior to disturbing the integrity of the barrier. The permit must be available for inspection at the project location. After the work is completed, the penetration must be repaired (sealed) according to accepted practice and utilizing materials (including UL/FM-listed through penetration fire stopping materials) that meet the original barrier construction requirements in order to restore the designed specifications for smoke and fire compartmentalization. Upon completion of any penetration repair, a visual inspection for approval must be requested from, and completed by FMS.
6.3 Interim Life Safety Protection Measures
Contractor shall participate with the VA in the preparation of an interim life safety measures and fire protection Plan that will be implemented during construction of this project. At a minimum, contractor shall comply with the following requirements of an interim life safety measures and fire protection plan:
631-21-003-SOW-C Page 7 of 10
• Ensure exits provide free and unobstructed egress for all building occupants. If required by contractor’s operations, establish and mark alternate means of egress for all building occupants.
• Contractor shall maintain escape facilities from the work area for construction workers at all times. Means of egress in construction areas will be inspected daily.
• Ensure free and unobstructed access to all areas of the project site for emergency services and for emergency forces.
• Ensure that means of egress and existing fire alarm, detection, and suppression systems are not impaired by contractor’s operations.
• Do not impair means of egress, automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Provide fire watch in accordance with NFPA standards for impairments.
Request approval of impairments from the COR in writing a minimum of 72 hours in advance.
• When required, a fire watch shall be by a qualified person provided by the contractor who shall maintain constant observation of the affected area and have no other duties. The person providing the fire watch shall be trained in fire prevention and in the use of fire extinguishers, occupant hose lines, occupant fire protection system, in sounding the building fire alarm and in notifying the local fire department, and in understanding the particular fire safety situation for the project.
• Provide written procedures and guidelines for construction personnel and post in the immediate areas of construction detailing what to do and who to call in the event of fire or emergency.
• Maintain the construction area to minimize the potential for fire or safety hazards resulting from storage of construction material, construction waste and debris during construction operations.
• All temporary construction shall be built of noncombustible/fire retardant materials and shall be smoke tight.
Contractor shall comply with the requirements and ensure efforts to prevent false fire alarms.
6.4 Parking
Parking is rigidly controlled throughout the Medical Center. Contractor parking is only allowed in designated areas (subject to change). Parking in designated patient parking areas is strictly prohibited. Parking on grass is also prohibited. Parking in roadways is prohibited.
Parking for equipment necessary to perform the work will be authorized in advance of starting the project. Parking passes will be issued by the COR.
631-21-003-SOW-C Page 8 of 10
6.5 Storage of Equipment and Materials
Security of material storage areas on the job site shall be the responsibility of the contractor.
The area shall be kept neat and orderly and free of debris. The contractor shall arrange with the COR for allocation of required workspace and for the storage of equipment and material to be used for this project. The Contractor should schedule delivery of materials to limit the amount of storage space and time. The warehouse CANNOT accept or store deliveries.
6.6 Debris Removal
The Contractor/Installer shall be required to remove waste materials and debris daily (unless otherwise authorized by COR) from the campus. All waste material and debris shall be removed off the site by the contractor and shall be disposed of in accordance with applicable State and Federal regulations.
Upon completion of a project, the contractor shall ensure that all dirt, trash, and debris resulting from the construction operations are removed from the work area. Unless directed otherwise in the contract or by the Contracting Officer, disposal of debris shall be made at the contractor’s expense and shall be delivered to a state approved disposal site located off the VA grounds. Debris shall not be left in such a manner that wind or other weather conditions can cause the debris to be scattered outside the work area or inside the facilities via local foot traffic. The hauling and disposal of excess fill material including rock, gravel, sod, broken concrete or asphalt, plaster, etc., shall be the responsibility of the contractor. Disposal shall be in accordance with applicable state and local regulations.
6.7 Site Utilities
The Contractor/Installer should note this scope of work does not detail all existing structures, utilities, or components that may potentially interfere with the contract work required. The contractor shall note any obstruction, utility, or condition that may hinder or interfere with the execution of this contract and the contractor shall make provisions in their contract price to resolve such interferences and other conditions that may hinder the proper completion of the work. All proposed utility relocations, reallocations, and shutdowns shall be approved by the COR prior to commencing such work. The contractor shall verify all existing utility installations and take appropriate action prior to working around any potential utility installation.
In the event a shutdown, restriction, or interruption of any utility services is required, a written request must be submitted (at least 14 calendar days in advance) and approved by the VA COR. All utility shutdowns must be reviewed and approved by the VA.
631-21-003-SOW-C Page 9 of 10
6.8 Infection Control
All work shall be performed in accordance with the Construction Specifications for Infection Control of the Edward P Boland VA Medical Center. For purposes of this project, the work shall be accomplished using the controls indicated in the specifications and on the Infection Control Construction Permit attached. No work will be allowed to proceed until an Infection Control Construction Permit has been completed and signed and all protective measures required by the permit are in place.
7 Material and Workmanship Quality
All materials and workmanship shall comply with all codes, standards, and requirements of all Authorities Having Jurisdiction (AHJ). All work shall be done in accordance with contract terms and conditions and in a professional manner according to the best trade practices and to the satisfaction of the COR. This includes work performed by subcontractors.
8 Contractor Staff and Employees
Prior to commencing on-site construction, the contractor shall provide the Contracting Officer with a telephone number and FAX number at which the contractor or his/her representative may be contacted at any time during regular working hours and an emergency number at which the contractor may be contacted in situations requiring immediate attention.
9 Scheduling of Pre-Final and Final Inspections
Notification for Pre-final. The Contractor and the Government will jointly conduct a pre-final inspection prior to any final inspection. Request for the pre-final shall be made in writing to the COR at least 7 calendar days prior to the desired date.
Pre-final Inspection. Discrepancies noted will be furnished by the Government inspector to the Contracting Officer. The COR is responsible for furnishing a complete punch list, in writing, to the Contractor. Items noted on the punch list will be completed prior to scheduling a final inspection. As-builts, real property data, warranties, manuals, etc., may be turned-in at time of final inspection.
Notification for Final Inspection. When the Contractor is ready for final inspection, he shall request so in writing to the Contracting Officer or his duly authorized representative at least 5 days prior to the desired date.
10 Keys
The Contractor shall be responsible for any Government-owned keys that have been issued to him for access to facilities or areas pertinent to this contract.
Upon completion of the work in an area, or upon request of the Contracting Officer, the key or keys relevant to the area shall be returned immediately. Keys shall be returned prior to final task order payments.
631-21-003-SOW-C Page 10 of 10
Should the Contractor Lose a Key: The Contractor shall notify the Contracting Officer, immediately and in writing, but not later than one (1) working day after he is aware of the loss. Should the key not be found before final acceptance, the final contract payment shall be reduced by the replacement cost for each key not returned and, if required by the Contracting Officer, any re-keying costs and cost of any other damages suffered by the Government.
11 Progress Meetings
A weekly meeting may be held between the Contractor, COR and Contracting Officer, if necessary, to discuss work progress, problems and potential change orders. Contractors shall attend these meetings at no additional cost to the Government and shall be responsible for publishing minutes for each meeting. Prior to specific work elements of a project, the contractor shall confer with the COR and agree on a sequence of procedures and means of access to premise and buildings; space for storage of materials and equipment; delivery of materials and use of approaches, use of corridors, stairways and similar means of passage.
A three-week look ahead schedule shall be provided at a higher level of detail than the overall project schedule and reviewed in each progress meeting.
12 Project Management Software
Submittals and RFIs shall be administered through a project management software such as Procore or equal.
**************** End SOW ****************