This document is a Statement of Work (SOW) for the replacement of the nurse call system and overhead paging system at the Hot Springs VA Health Care System (HSVAHCS) in Hot Springs, South Dakota.
The SOW outlines the scope of work, which includes replacing the existing nurse call system and overhead paging system throughout the facility. The work is to be completed within 270 calendar days from the Notice to Proceed. The contract will be a Firm-Fixed-Price Task Order. The contractor is required to submit a detailed work plan, shop drawings, and maintain a set of as-built drawings. Environmental considerations include recycling materials where feasible. Any changes to the SOW must be approved in writing by the Contracting Officer.
The related federal contract opportunity is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside, solicitation number 36C26324B0005, issued by the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 23. Only verified SDVOSB firms registered in the Veteran Small Business Certification (VetCert) database at the time of bid submission will be deemed responsive.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26324B0005 0004.docx | DOCX document | |
| 36C26324B0005 0003.docx | DOCX document | |
| AS06_Site Visit Sign In Sheet.pdf | ||
| 36C26324B0005 0002.docx | DOCX document | |
| AS06_Solicitation Questions and Answers_10 Pages.pdf | ||
| 36C26324B0005 0001.docx | DOCX document | |
| S02 NARA Language for Contracts.pdf | ||
| S02_VA6500 Appendix C 1 - 1 page.pdf | ||
| S02_SAFETY and EMR INFORMATION.pdf | ||
| S02_WDOL_General Decision Number_7 Pages.pdf | ||
| S02_Drawings_Set 20240715_72 Pages.pdf | ||
| S02_Specs_426 Pages.pdf | ||
| 36C26324B0005_1.docx | DOCX document | |
| S02 TMS 20939 VA Privacy Training - 3pp.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Replace Hot Springs Nurse Call and Overhead Paging System
HOT SPRINGS, SD
PROJECT #: 568A4-23-204
1. Background:
1.1. The Hot Springs VA Health Care System (HSVAHCS) requires the replacement of existing nurse call system in Building 12 Hospital and the overhead paging system thought the facility.
2. General
2.1. Title of Project: Replace Hot Springs Nurse Call and Overhead Paging System
2.2. Scope of Work: The contractor shall provide all resources necessary to accomplish the deliverables described in this scope of work (SOW).
Construction shall be completed according to the construction documents, specifications, and drawings.
Background: The project is located at the Hot Springs VA campus. The address for the facility is 500 N 5th St, Hot Springs, SD 57747-1480.
History:
A Rauland Borg nurse call system was installed in the basement 2009 serving three restrooms.
This system shall be replaced.
A Dukane system was installed in Primary Care (exact date unknown) that shall be replaced under this project.
There are restrooms on Pharmacy and X-Ray (both on Ground floor of hospital), installation dates unknown. These systems will be replaced.
A Rauland Borg nurse call system was installed on Ward 1 East Building 12 in 2006, approximately 50 stations. This system shall be replaced.
There is a stand-alone nurse call system on the first floor North Wing (Eye and Audiology clinics). This system will be replaced.
There is one restroom located in the Dental wing (South wing of the first floor of the hospital) that is interfaced with the 1 East nurse call system.
A Rauland Borg system was installed on the 2 North in 2007. This system shall be replaced.
A nurse call system was installed on the second-floor South wing around 1997. At the time this ward was intended as an in-patient unit. This majority of this system has been removed, only bathrooms are still on the system. This system will be replaced.
The overhead paging system is a Dukane system. There are four Dukane master control panels located in the Building 2 Electrical Room, Building 12 IT Room, Building 18 Boiler Plant and Building 43. These panels will be replaced under the project.
The following is a list of overhead paging zones and areas that will be replaced per the contract drawings.
ZONE BLDG # TYPE SECTION SERVICE
01 12 HOSPITAL WARD 1-NORTH NURSING
01 12 HOSPITAL WARD 1-EAST NURSING
01 12 HOSPITAL WARD 2-SOUTH NURSING
01 12 HOSPITAL WARD 3-NORTH NURSING
02 12 HOSPITAL AREA 3-SOUTH BIOMED
02 12 HOSPITAL AREA 4th FLOOR LABORATORY
02 12 HOSPITAL AREA 1-SOUTH DENTAL
02 12 HOSPITAL GROUND NORTH RADIOLOGY
02 12 HOSPITAL BASEMENT REHAB MEDICINE
02 12 HOSPITAL HALL BASEMENT MAIL ROOM AREA
02 12 HOSPITAL S.P.S. S.P.S.
02 53 EDUC 53 EDUCATION
02 53 EDUCAT. 53 BASEMENT EDUCATION
02 53 EDUCAT. 53 GROUND EDUCATION
02 53 EDUCAT. 53 FIRST EDUCATION
02 53 EDUCAT. 53 FIRST EDUCATION
02 43 LAUNDRY LAUNDRY EMS
02 2 DOM EMS EMS
02 65 IT IT IT
02 DOM DOM ARCADE DOM LOWER LEVEL
03 12 HOSPITAL LOBBY MEDICAL SERVICE
03 12 HOSPITAL CANTEEN CANTEEN SERVICE
03 12 HOSPITAL GROUND EAST PRIMARY CARE
03 12 HOSPITAL GROUND SOUTH PHARMACY
03 12 HOSPITAL LOADING DOCK OUTSIDE
04 12 HOSPITAL SURGERY SURGERY
05 DOM ALL UPPER FLOORS LIVING QUARTERS
05 2 DOM DINING ROOM DOM DINING ROOM
05 2 DOM SATP SATP/PSYCHIATRY
06 3 DOM BASEMENT VOLUNTARY SVC.
06 7 DOM BASEMENT ARTS and CRAFTS
06 8 DOM BASEMENT STORAGE
07 11 DOM CALL CENTER CALL CENTER
07 11 DOM AUDITORIUM AUDITORIUM
08 5 DOM CANTEEN CANTEEN
09 14 BUILDING ENGINEERING ENGINEERING
09 14 SEC. BUILDING ENGINEERING ENGINEERING
09 10 DOM ELECTRIC SHOP ENGINEERING
09 13 BUILDING PLUMBING SHOP ENGINEERING
09 13 BUILDING PAINT SHOP ENGINEERING
09 17 BUILDING EQUIP. SHOP ENGINEERING
09 18 BUILDING BOILER PLANT BOILER PLANT
09 A/B BUILDING CARPENTAR ENGINEERING
09 66 BUILDING FIRE/POLICE FIRE/POLICE
09 30 BUILDING TRANSPORT. ENGINEERING
10 1 DOM DIRECTOR DIRECTOR
10 1 DOM CHIEF OF STAFF CHIEF OF STAFF
10 1 DOM UNKNOWN UNKNOWN
10 1 DOM PSYCHOLOGY PSYCHOLOGY
10 1 DOM PSYCHIATRY PSYCHIATRY
10 1 DOM UNKNOWN UNKNOWN
10 1 DOM H.R. H.R.
10 1 DOM DOM FIELROOM DOM FILEROOM
10 1 DOM DOM CLINIC DOM CLINIC
10 1 DOM DOM SERVICE DOM SERVICE
10 1 DOM UNKNOWN UNKNOWN
10 1 DOM QUAL. ASS. QUAL. ASS.
11 4 DOM BASEMENT CALL CENTER
11 4 DOM BASEMENT CALL CENTER
11 6 DOM BASEMENT WAREHOSUE
11 9 DOM CHAPEL CHAPEL
2.3. Scope of Construction: Replace Hot Springs Nurse Call and Overhead Paging Systems shall consist of replacement of the existing nurse call system and overhead paging system at the Hot Springs facility.
2.4. Performance Period: The contractor shall complete the work required under this SOW in 270 calendar days or less from date of Notice to Proceed (NTP), unless otherwise directed by the Contracting Officer (CO). If the contractor proposes an earlier completion date, and the Government accepts the contractor’s proposal, the contractor’s proposed completion date shall prevail.
2.5. Type of Contract: Firm-Fixed-Price Task Order contract.
3. Contract Award Meeting
3.1. The contractor shall not commence performance on the tasks in this SOW until the Contracting Officer (CO) has conducted a pre-construction meeting or has advised the contractor that a kickoff meeting is waived.
4. General Requirements
4.1. This project shall have dedicated on site superintendent managing the construction effort, IAW FAR Clause 52.236-6.
4.2. For every task, the contractor shall identify in writing all necessary subtasks (if any), associated costs by task, along with associated sub-milestone dates. The contractor's subtask structure shall be reflected in the technical proposal and detailed work plan.
4.3. All written deliverables shall be phrased in layperson language. Statistical and other technical terminology shall not be used without providing a glossary of terms.
4.4. Where a written milestone deliverable is required in draft form, the VA will complete their review of the draft deliverable within 14 calendar days from the date of receipt.
The contractor shall have 14 calendar days to deliver the final deliverable from date of receipt of the Government’s comments, unless otherwise specifically outlined in the Governments response.
5. Specific Mandatory Tasks and Associated Deliverables
5.1. Task One: After Notice to Proceed (NTP) is issued, the contractor shall provide a detailed work plan for the VA project team, which presents the contractor's plan for completing the task order. The contractor's plan shall be responsive with this SOW and describe, in further detail, the approach to be used for each aspect of the task order as defined here. Shop drawings fully describing components to be installed shall be submitted for review and acceptance.
5.2. The contractor is expected to keep a complete set of official drawings on the construction site where any/all red lines are recorded. This official red lined drawing set is to be handed in at the completion of the project for the A/E to provide a complete set of as-built drawings.
5.3. Deliverable One: A detailed work plan and briefing. Shop drawings fully describing all components and work products.
5.4. Task Two: Repair various roofs according to the construction documents, specifications, and drawings.
6. Environmental
6.1. Wherever feasible, the project will incorporate “green” environmental principles. These include recycling of materials and design of systems for energy conservation.
6.2. All materials that are recycled shall be logged and the log shall be provided to the
COR.
7. Changes to Scope of Work
7.1. Any changes to this SOW shall be authorized and approved only through written correspondence from the CO. A copy of each change will be kept in a project folder along with all other products of the project. Costs incurred by the contractor through the actions of parties other than the CO shall be borne by the contractor.
8. Confidentiality and Nondisclosure
8.1. It is agreed that:
The preliminary and final deliverables, all associated working papers, and other material deemed relevant by VA and generated by the contractor in the performance of this task order, are the exclusive property of the U.S. Government and shall be submitted to the CO at the conclusion of the task order.
The CO will be the sole authorized official to release, verbally or in writing, any data, draft deliverables, final deliverables, or any other written or printed materials pertaining to this task order. No information shall be released by the contractor. Any request for information relating to this task order, presented to the contractor, shall be submitted to the CO for response.
Press releases, marketing material, or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.
9. Training, Security and NARA Requirements
9.1. Contractor Training check if required: All contractors on-site shall complete required training. Each contractor is required to print, review, and sign the attached TMS 20939 document. Contract owner/supervisor must send signed TMS 20939 documents to the contract COR, Doug Sprinkle, (605) 745-7259.
9.2. 6500.6 Appendix C Security and NARA PRIVACY-HIPAA CLAUSE: All contractors on-site shall read and comply with attached 6500.6 Appendix C Security and NARA PRIVACY-HIPAA CLAUSE documents.
9.3. Any contractor that is required to be on site must take TMS Training 20939 and those certificates must be sent to the COR prior any work starting.
End of Statement of Work