S02 - SECTION 09 65 13 RESILIENT BASE AND ACCESSORIES.pdf
PDF 107 KB Posted
- Solicitation number
- 36C26120B0016
About this file
This pre-solicitation notice is for a construction project to replace dental casework at the Veterans Affairs Palo Alto Health Care System located in Palo Alto, California. The project scope includes removing and replacing existing casework in dental treatment rooms, along with some associated plumbing, medical gas valves, electrical outlets, and safety measures. The construction duration is 180 calendar days with an estimated cost between $500,000 and $1,000,000. The full solicitation will be a total SDVOSB set-aside for registered and verified VIP/SAM concerns. The solicitation is expected to be released on or around June 19, 2020, with a mandatory site visit scheduled at the location. Questions may be directed to the point of contact provided.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace Case Work in Dental 640-20-117
Palo Alto, Building 100, VA Palo Alto Health Care System Final Bid Document
09 65 13 - 1
SECTION 09 65 13
RESILIENT BASE AND ACCESSORIES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Resilient base (RB) adhered to interior walls and partitions.
1.2 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. ASTM International (ASTM):
1. F1344-15 - Rubber Floor Tile.
2. F1859-14 - Rubber Sheet Floor Covering without Backing.
3. F1860-14 - Rubber Sheet Floor Covering with Backing.
4. F1861-08(2012)e1 - Resilient Wall Base.
5. D4259-88(2012) - Abrading Concrete.
C. International Concrete Repair Institute (ICRI):
1. 310.2R-13 - Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, and Polymer Overlays.
1.3 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Manufacturer's Literature and Data:
1. Description of each product.
2. Adhesives and primers indicating manufacturer's recommendation for each application.
3. Installation instructions.
C. Samples:
1. Resilient Base: 150 mm (6 inches) long, each type and color.
D. Sustainable Construction Submittals:
1. Recycled Content: Identify post-consumer and pre-consumer recycled content percentage by weight.
2. Low Pollutant-Emitting Materials:
a. Show volatile organic compound types and quantities.
E. Operation and Maintenance Data:
1. Care instructions for each exposed finish product.
1.4 DELIVERY
A. Deliver products in manufacturer's original sealed packaging.
09 65 13 - 2
B. Mark packaging, legibly. Indicate manufacturer's name or brand, type, color, production run number, and manufacture date.
C. Before installation, return or dispose of products within distorted, damaged, or opened packaging.
1.5 STORAGE AND HANDLING
A. Store products indoors in dry, weathertight facility.
B. Protect products from damage when handling and during construction operations.
1.6 FIELD CONDITIONS
A. Environment:
1. Product Temperature: Minimum 21 degrees C (70 degrees F) for minimum
48 hours before installation.
2. Work Area Ambient Temperature Range: 21 to 27 degrees C (70 to
80 degrees F) continuously, beginning 48 hours before installation.
3. Install products when building is permanently enclosed and when wet construction is completed, dried, and cured.
1.7 WARRANTY
A. Construction Warranty: FAR clause 52.246-21, "Warranty of
Construction."
PART 2 - PRODUCTS
2.1 PRODUCTS
Basis of Design: Section 09 06 00, Tarkett, color: 29 Moon Rock, 6”, topset with toe.
A. Provide each product from one manufacturer and from one production run.
B. Sustainable Construction Requirements:
1. Sheet Rubber Flooring Recycled Content: 90 percent total recycled content, minimum.
2. Low Pollutant-Emitting Materials: Comply with VOC limits specified in Section 01 81 13, SUSTAINABLE CONSTRUCTION REQUIREMENTS for the following products:
a. Flooring Adhesives and Sealants.
2.2 RESILIENT BASE
A. Resilient Base: 3 mm (1/8 inch) thick, 100 mm 6 inches high.
1. Type: Rubber use one type throughout to VA Palo Alto standard.
09 65 13 - 3
2. ASTM F1861, Type TP thermoplastic rubber or Type TV thermoplastic vinyl, Group 2 - layered.
B. Applications:
1. Style B - Cove.
2.3 PRIMER (FOR CONCRETE FLOORS)
A. Primer: Type recommended by adhesive manufacturer.
2.4 LEVELING COMPOUND (FOR CONCRETE FLOORS)
A. Leveling Compound: Provide products mixed with latex or polyvinyl acetate resins.
2.5 ADHESIVES
A. Adhesives: Low pollutant-emitting, water based type recommended by adhered product manufacturer for each application.
PART 3 - EXECUTION
3.1 PREPARATION
A. Examine and verify substrate suitability for product installation.
B. Protect existing construction and completed work from damage.
C. Remove existing base to permit new installation.
1. Dispose of removed materials.
D. Correct substrate deficiencies.
1. Fill cracks, pits, and depressions with leveling compound.
2. Remove protrusions; grind high spots.
3. Apply leveling compound to achieve 3 mm (1/8 inch) in 3 m (10 feet) maximum surface variation.
E. Clean substrates. Remove contaminants capable of affecting subsequently installed product's performance.
1. Mechanically clean concrete floor substrate according to ASTM D4259.
2. Surface Profile: ICRI Guideline No. 310.2R.
F. Allow substrate to dry and cure.
G. Perform flooring manufacturer’s recommended bond, substrate moisture content, and pH tests.
3.2 INSTALLATION GENERAL
A. Install products according to manufacturer's instructions.
1. When instructions deviate from specifications, submit proposed resolution for Contracting Officer consideration.
09 65 13 - 4
3.3 RESILIENT BASE INSTALLATION
A. Applications:
1. Install resilient base in rooms scheduled on Drawings.
2. Extend resilient base into closets, alcoves, and cabinet knee spaces, and around columns within scheduled room.
B. Lay out resilient base with minimum number of joints.
1. Length: 600 mm (24 inches) minimum, each piece.
2. Locate joints 150 mm (6 inches) minimum from corners and intersection of adjacent materials.
C. Installation:
1. Apply adhesive uniformly for full contact between resilient base and substrate.
2. Set resilient base with hairline butted joints aligned along top edge.
D. Field form corners and end stops.
1. V-groove back of outside corner.
2. V-groove face of inside corner and notch cove for miter joint.
E. Roll resilient base ensuring complete adhesion.
3.4 CLEANING
A. Remove excess adhesive before adhesive sets.
B. Clean exposed resilient base, surfaces. Remove contaminants and stains.
1. Clean with mild detergent. Leave surfaces free of detergent residue.
C. Polish exposed resilient base to gloss sheen.
3.5 PROTECTION
A. Protect products from construction traffic and operations.
B. Replace damaged products and re-clean.
1. Damaged Products include cut, gouged, scraped, torn, and unbonded products.
- - E N D - -
File details come from the government source that posted it. Updated .