This pre-solicitation notice and related technical specifications document describe a planned construction project to replace dental casework at the Veterans Affairs Palo Alto Health Care System medical facility. The project scope involves removing existing casework from dental treatment rooms and installing new casework, along with some associated plumbing, medical gas, electrical, and safety work. The construction duration is scheduled for 180 calendar days with an estimated cost between $500,000 and $1,000,000. The completed solicitation will be set aside specifically for registered and verified Service-Disabled Veteran-Owned Small Businesses. All questions regarding this pre-solicitation should be directed to the specified point of contact, with the full solicitation documents expected to be released on or around June 19, 2020.

View the file

Other files

File Type Posted
S02 - Wage Determination - CA20200018 07.10.2020 - 36C26120Q0818.pdf PDF
36C26120B0016 0002.docx DOCX document
S05 - RFI Log - PA Dental Casework - 640-20-117.pdf PDF
S02 - RFI 001 Exhibit B_revised 7-18-20.pdf PDF
S02 - Final SOW - PA Dental Case Work_FINALv2.pdf PDF
S02 - FAR 52.211-6 Brand Name or Equal Provision.pdf PDF
S02 - RFI 008 - attachment.pdf PDF
36C26120B0016 0001.docx DOCX document
S04 - Site Walk Sign in Sheet - PA - Replace Dental_FILLED OUT.pdf PDF
S02 - SECTION 01 74 19 Construction Waste Management.pdf PDF
S02 - SECTION 01 00 00 General Requirements.pdf PDF
S02 - SECTION 12 36 00 Countertops.pdf PDF
S02 - SECTION 09 91 00 Painting.pdf PDF
36C26120B0016_1.docx DOCX document
S02 - SECTION 12 32 00 MANUFACTURED WOOD CASEWORK.pdf PDF
S02 - Exhibit A.pdf PDF
S02 - SECTION 07 92 00 Joint Sealants.pdf PDF
S02 - SECTION 09 65 13 RESILIENT BASE AND ACCESSORIES.pdf PDF
S02 - SECTION 01 35 36 Safety Requirements.pdf PDF
S02 - SECTION 01 32 16.15 Project Schedule.pdf PDF
S02 - Exhibit B.pdf PDF
S02 - SECTION 09 06 00 Shedule Of Finishes Case Work.pdf PDF
S02 - SECTION 22 05 11 Common Results for Plumbing.pdf PDF
S02 - SOLICITATION RFI FORM.pdf PDF
S02 - SECTION 12 34 00 Manufactured Plastic Casework.pdf PDF
S02 - SECTION 06 20 00 Finish Carpentry.pdf PDF
S02 -SECTION 01 57 19 Temporary Environmental Controls.pdf PDF
S02 - SECTION 09 23 00 Gypsum Plaster.pdf PDF
S02 - PG 18-14 Room Finishes Door and Hardware Schedule.pdf PDF
S02 - SECTION 01 33 32 Shop Drawings Product Data and Samples.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace Case Work in Dental 640-20-117

Palo Alto, Building 100, VA Palo Alto Health Care System Final Bid Document

07 92 00 - 1

02 41 00

SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 DESCRIPTION:

This section specifies demolition and removal of portions of buildings, utilities, other structures and debris.

1.2 RELATED WORK:

A. Not Used.

1.3 PROTECTION:

A. Perform demolition in such manner as to eliminate hazards to persons and property; to minimize interference with use of adjacent areas, utilities and structures or interruption of use of such utilities; and to provide free passage to and from such adjacent areas of structures.

Comply with requirements of GENERAL CONDITIONS Article, ACCIDENT

PREVENTION.

B. Provide safeguards, including warning signs, barricades, temporary fences, warning lights, and other similar items that are required for protection of all personnel during demolition and removal operations.

Comply with requirements of Section 01 00 00, GENERAL REQUIREMENTS, Article PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES AND IMPROVEMENTS.

E. Prevent spread of flying particles and dust. Sprinkle rubbish and debris with water to keep dust to a minimum. Do not use water if it results in hazardous or objectionable condition such as, but not limited to; ice, flooding, or pollution. Vacuum and dust the work area daily.

F. NOT USED:

G. Before beginning any demolition work, the Contractor shall survey the site and examine the drawings and specifications to determine the extent of the work. The contractor shall take necessary precautions to avoid damages to existing items to remain in place, to be reused, or to remain the property of the Medical Center; any damaged items shall be repaired or replaced as approved by the Contracting Officers

Representative. The Contractor shall coordinate the work of this

07 92 00 - 2 section with all other work and shall construct and maintain shoring, bracing, and supports as required. The Contractor shall ensure that structural elements are not overloaded and shall be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under this contract. Do not overload structural elements.

Provide new supports and reinforcement for existing construction weakened by demolition or removal works. Repairs, reinforcement, or structural replacement must have Contracting Officers Representative’s approval.

H. The work shall comply with the requirements of Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS.

I. The work shall comply with the requirements of Section 01 00 00, GENERAL REQUIREMENTS, Article 1.7 INFECTION PREVENTION MEASURES.

1.4 UTILITY SERVICES:

A. NOT USED.

B. NOT USED

PART 2 - PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.1 DEMOLITION:

A. Completely demolish and remove equipment, electrical and associated materials.

B. Cut roof coverings, sheet metal and structural members as needed to provide an opening large enough to remove existing equipment and install new equipment.

C. Store removed roof section out of the way of lifting operations to ne reinstalled at the completion of the lifting operation(s).

3.2 CLEAN-UP:

On completion of work of each phase and after removal of all debris, leave site in clean condition satisfactory to Contracting Officers

Representative. Clean-up shall include off the Medical Center disposal of all items and materials not required to remain property of the

07 92 00 - 3

Government as well as all debris and rubbish resulting from demolition operations.