S02 - SECTION 01 74 19 Construction Waste Management.pdf
PDF 111 KB Posted
- Solicitation number
- 36C26120B0016
About this file
This document contains a construction waste management specification and a related federal contract opportunity notice. The construction waste management specification outlines requirements for contractors to practice efficient waste management when working on a project to replace dental casework at the Veterans Affairs Palo Alto Health Care System in Palo Alto, California. Contractors must develop and implement a demolition debris management plan to reuse and recycle materials to the greatest extent feasible, and submit monthly reports quantifying all generated and diverted materials.
The related federal contract opportunity is a pre-solicitation notice for the dental casework replacement project. The solicitation will be a total Service-Disabled Veteran-Owned Small Business set-aside, with a projected award amount between $500,000 and $1,000,000. The duration of the project will be 180 calendar days from notice to proceed. A site visit is scheduled for the solicitation phase. Questions may be directed to the point of contact, with full solicitation documents expected to be available on June 19, 2020.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace Case Work in Dental 640-20-117
Palo Alto, Building 100, VA Palo Alto Health Care System Final Bid Document
10/12/2019
SECTION 01 74 19
CONSTRUCTION WASTE MANAGEMENT
1.1 DESCRIPTION
This specification covers the requirements for management of non-hazardous building construction and demolition waste.
1.2 RELATED WORK
A. Section 02 41 00, DEMOLITION.
B. Demolition and removal of roads, walks, curbs, and on-grade slabs outside buildings to be demolished: Section 31 20 00, EARTH MOVING
C. Safety Requirements: Section 00 72 00, GENERAL CONDITIONS, Article, ACCIDENT PREVENTION.
D. Disconnecting utility services prior to demolition: Section 01 00 00, GENERAL REQUIREMENTS.
E. Reserved items which are to remain the property of the Government:
Section 01 00 00, GENERAL REQUIREMENTS.
F. Asbestos Removal: Section 02 82 11, TRADITIONAL ASBESTOS ABATEMENT.
G. Lead Paint: Section 02 83 33.13, LEAD-BASED PAINT REMOVAL AND DISPOSAL.
1.3 GOVERNMENT POLICY
A. Contractor shall practice efficient waste management when sizing, cutting and installing building construction products.
B. Contractor shall use all reasonable means to divert construction and demolition waste from landfills and incinerators and facilitate their recycling.
C. Contractor shall be responsible for implementation of any special programs involving rebates or similar incentives related to recycling and any revenues or savings obtained from salvage or recycling shall accrue to the Contractor.
D. Contractor shall ensure that facilities used for recycling, reuse and disposal shall be permitted for the intended use to the extent required by federal, state and local regulations.
1.4 PLAN
A. Conduct a site assessment to estimate the types of materials that will be generated by demolition at the site. The Whole Building Design
Guide website (http://www.wbdg.org) has a Construction Waste Management
Database that contains information on companies that haul, collect, and process recyclable debris from construction projects http://www.wbdg.org/
Replace Case Work in Dental 640-20-117
Palo Alto, Building 100, VA Palo Alto Health Care System Final Bid Document
10/12/2019
B. Develop and implement procedures to reuse and recycle materials to the greatest extent feasible based upon the contract, the construction and demolition debris management plan, the estimated quantities of materials, and the availability of recycling facilities.
C. Prepare and submit to the Contracting Officer’s Representative a written demolition debris management plan. The Demolition Debris
Management Plan shall be submitted for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted Project Schedule. The plan shall include, but not be limited to, the following information:
1. Contractor and project identification information;
2. Procedures to be used for debris management;
3. A listing of the materials to be reused, recycled, or taken to the landfill.
4. The names and locations of reuse and recycling facilities or sites.
1.5 COLLECTION
A. Provide necessary containers, bins and storage areas to facilitate effective waste management.
B. Clearly identify so that recyclable materials are separated from trash and can be transported to respective recycling facility for processing.
1.6 DISPOSAL
A. Contractor shall be responsible for transporting and disposing of materials that cannot be delivered to a source-separated or mixed materials recycling facility to a transfer station or disposal facility that can accept the materials in accordance with state law.
B. Building or demolition materials with no practical use or that cannot be recycled shall be disposed of at a landfill or incinerator.
1.7 REPORT
A. With each application for progress payment, the contractor shall submit a summary of construction and demolition debris diversion and disposal, monthly and at the end of the contract quantifying all materials generated at the work site and disposed of or diverted from disposal through recycling.
B. Any request for periodic payment shall not be processed without this report being attached.
- - - E N D - - -