S02 - Ogden Heat Exchanger - Final SOW.pdf

PDF 485 KB Posted

Attached to
Z1DA--Construction of Heat Exchangers, Ogden and Damen Building
Solicitation number
36C25226B0034
Issued by

About this file

Statement of Work Summary – JBVAMC Heat Exchanger Replacement

This is a Statement of Work for the replacement of four Steam to Hot Water Converters/Heat Exchangers at Jesse Brown VA Medical Center in Chicago, Illinois. The project objective is to replace aging and unreliable heat exchanger units in the Damen and Ogden buildings that are critical to maintaining temperature control and providing hot water for clinical operations and connected equipment. The contractor must complete all work within 90 days from the notice to proceed and is responsible for providing all personnel, equipment, supplies, facilities, transportation, tools, materials, and supervision.

The detailed scope of work includes: delivering materials during normal business hours; removing the four existing steam converters and accessories; installing four new BacNet-capable steam-hot water converters on existing concrete equipment pads; reconnecting all piping; replacing all steam traps and shut-off valves; reinsulating piping with mechanical insulation as necessary; testing the system for leaks; completing electrical work; providing a minimum one-year warranty; and performing daily cleanup. The contractor must comply with Jesse Brown VAMC site-specific requirements including badging, key policies, and rules of behavior. Normal delivery hours are 7:30 a.m. to 3:30 p.m. Monday through Friday, with modifications requiring written COR approval. Disruptive work activities must occur between 6:00 p.m. and 6:00 a.m., and crane lifts or activities blocking access must be performed on Sundays during low patient times. All work must comply with NFPA-99, OSHA, Joint Commission, VA, UL, NEC, state and local regulations, and all service technicians must be properly licensed, certified, or trained in accordance with applicable requirements. Safety assurance requirements include compliance with CFR regulations for hazardous materials, asbestos handling, confined space entry, and fall protection.

View the file

Other files

File Type Posted
36C25226B0034 0003.docx DOCX document
36C25226B0034 0002.docx DOCX document
36C25226B0034 0001.docx DOCX document
S06 - 36C25226B0034 Sign In Sheet.pdf PDF
S02 - Wage Rates.pdf PDF
36C25226B0034.docx DOCX document
S02 - 852.219-75.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW 3/31/25 Page 1 of 8

Statement of Work for JBVAMC Heat Exchanger Replacement

Place of Performance:

Jesse Brown VA Medical Center 820 S. Damen Ave Chicago IL 60612

Project Objective: The purpose of this project is to replace the (4) Steam to Hot Water Converters/Heat Exchangers within Damen and Ogden buildings.

Current Conditions: The existing Heat Exchangers are old and unreliable.

The Heat Exchangers are responsible for: maintaining and changing temperature in the Damen and Ogden buildings; and providing hot water to clinical needs and connected equipment.

The Heat Exchanger units are old, breaking continuously, and not reliable; and the dependent equipment cannot fulfill their duties due to the Exchangers being incapable to provide hot water and to maintain consistent temperatures, thus reducing efficiency and potentially damaging the equipment long-term. The staff rely equally on the Heat Exchangers to provide hot water, ensuring that the systems within Damen and Ogden that depend on hot water can continue to operate smoothly. JBVA Medical Center requests the immediate replacement of the Heat Exchanger units to continue providing the very critical services.

Part 1: Project Scope of Work Overview:

The contractor shall replace (4) existing Heat Exchangers. The removal & installation of the Heat Exchangers will include the disconnection and connection of electrical power.

The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, pay for their own parking while on site, tools, materials, and supervision required to perform the following:

Part 2: Detailed Project Scope of Work:

1. Deliver all materials to the site during normal working hours.

2. Remove existing (4) Steam Converters/Heat Exchangers and accessories from piping systems. SOW Attachment 1.

3. Install (4) Steam-Hot Water Converters/Heat Exchangers

a. BacNet capable

b. Installed on existing concrete equipment pads

4. Reconnect all piping to Converters

5. Replace all steam traps and shut off valves

6. Reinsulate piping with appropriate mechanical insulation, if necessary

7. Test system for leaks

8. Electrical

9. Minimum 1 year warranty

SOW 3/31/25 Page 2 of 8

10. Perform daily clean-up of work areas.

11. Project Coordination.

Part 3: Period of Performance. All work under this contract shall be fully completed within 90 days from notice to proceed.

Part 4: Applicable Performance Standards

A. Contractor shall ensure that the equipment functions in conformance with the latest published edition of NFPA-99, OSHA, Joint Commission, VA, UL, NEC, state and local regulations. The equipment covered under this contract shall be maintained in accordance with the manufacturer's standards/specifications. Preventive Maintenance inspection/repair procedures shall be in accordance with the manufacturer specifications.

B. Service Technician Requirements. All service technicians performing work under this

Contract shall be properly licensed, certified, or otherwise trained, in accordance with federal, state, and local requirements, to perform the work under this Contract. Any such licenses, certifications, or training shall be kept current throughout the period of performance of this Contract. The Contractor shall provide a copy of any such license or certificate the next Business Day, as defined below, upon request by the COR.

Part 5: Jesse Brown VAMC Additional Requirements

1. Comply with all Jesse Brown VAMC site specific requirements and SOPs including and not limited to: Key Policy, Badging Policy, Rules of Behavior, and Smoking Policy.

2. Normal delivery hours are 7:30 am to 3:30 pm Monday through Friday.

a. Normal work hours can be modified only by written approval of the COR.

b. No delivery by the Vendor on Federal Holidays and no delivery on the weekend when the Federal Holiday is on the respective Monday or Friday.

c. Work in stairs, interior / exterior public areas shall be between 6:00 pm through midnight concluding by 6:00 am on the following day.

d. Any work including and not limited to: noise, vibration, dust, odors, core drilling, hammer drilling, saw cutting, equipment moving in public corridors, soil compaction shall performed between 6:00 pm through midnight concluding by 6 am on the following day.

e. Crane lifts, any work that closes drive isles, closes building entries or closes public corridors shall be during low patient time and performed Sundays.

f. The Contractor shall check in (in person) with the Administrative Officer of the Day (AOD) which is located in Patient Admitting for any work between 6:00 pm through midnight to 6:00 am or any time on weekends. Provide the name and cell number of the on-site supervisor to the AOD. At the completion of the work, check out with the

AOD.

3. All building systems will be maintained in full operation at all times:

SOW 3/31/25 Page 3 of 8

a. Request system shutdowns in writing not less than 21 calendar days in advance.

b. Shutdown work shall be during low patient time and performed between Saturday 6 pm through midnight concluding by 6 pm on the following Sunday.

4. Utilities. The contractor can use existing building utilities during the execution of this work.

5. Safety Assurance

a. Compliance with Regulations. All work including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926. Work involving the disturbance or dismantling of asbestos or asbestos-containing materials; the demolition of structures containing asbestos; and/or disposal and removal of asbestos, shall also comply with the requirement of 40 CFR, Part 61, Subpart A. All work shall comply with applicable federal, state and municipal safety and health requirements.

Where there is a conflict between applicable regulations, the most stringent shall apply. The VA's Construction Safety Guidebook is available at the following web site:

http://vaww.ceosh.med.va.gov/01hp/pages/guidebooks.shtml

b. Accident Notification/Report. In the event of a job-related accident, the Contractor shall immediately notify the COR and shall prepare a Report of Accident (VA Form 2162 or equivalent) in quadruplicate and forward the original and two copies to the CO or COR for forwarding to Safety Officer for construction projects. The Contractor shall maintain an accident file for the life of the contract to include all accident reports. Any technical advice and assistance necessary in accident investigation and reporting may be requested from the respective Safety Office. Lost time injury is defined as "An injury resulting in a lost workday, not including the day of injury."

c. Contractor Responsibility. The Contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work.

d. Crawl spaces and attics are to be treated as confined space entry. Contractor must follow 29CFR 1910.146 and use VA furnished Form entitled Required Confined Space Entry Permit when making an entry. NOTE: A confined space does not include areas above suspended acoustical tile ceiling.

e. Where an employee can fall more than 6 feet, a fall protection system must be used; 29 CFR 1926.500 stipulates where this occurs and the different types of fall arrest systems.

f. When the Contractor is working in buildings that are occupied by Government personnel, the Contractor must provide Safety Data Sheets (SDS) to the COR before they begin any work involving chemicals.

g. All references to protection of the site and adjacent buildings when trenching.

h. Traffic Control Devices. The Contractor shall comply with the http://vaww.ceosh.med.va.gov/01hp/pages/guidebooks.shtml

SOW 3/31/25 Page 4 of 8 recommendations contained in Part 6 of the U. S. Department of Transportation, Federal Highway Administrations “Manual on Uniform Traffic Control Devices”, available at http://mutcd.fhwa.dot.gov/, to ensure proper warnings to motorists and adequate traffic control. The Contractor shall provide all warning lights, barricades and other traffic control devices and signs.

http://mutcd.fhwa.dot.gov/

SOW 3/31/25 Page 5 of 8

SOW Attachment 1

SOW 3/31/25 Page 6 of 8

SOW 3/31/25 Page 7 of 8

SOW 3/31/25 Page 8 of 8

Part 1: Project Scope of Work Overview:
Part 2: Detailed Project Scope of Work:
Part 3: Period of Performance. All work under this contract shall be fully completed within 90 days from notice to proceed.