The provided document is a set of architectural and engineering drawings for the Replace Air Cooled Chillers project at the Chalmers P. Wylie VA Ambulatory Care Center in Columbus, Ohio. The drawings include detailed plans for crane and laydown site positioning, a second-level life safety plan, and a phased mechanical system replacement strategy. The project involves replacing three existing air-cooled chillers (ACH-1, ACH-2, ACH-3) with new units, installing new piping and pumps, and reconfiguring the chilled water system, with work to be performed in four sequential phases to maintain continuous facility operations.

The phasing plan is designed to minimize disruption, with specific requirements including maintaining system operability throughout the project, potential short system downtimes during heating months, and provisions for maintaining critical space temperatures. The project is a 100% set-aside for Service-Disabled Veteran Owned Small Businesses (SDVOSB), with a project magnitude between $2,000,000 and $5,000,000. The work will be coordinated with VA Contracting Officers and involves comprehensive mechanical, electrical, and structural modifications to the facility's cooling infrastructure.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Drawing No. Sheet Name

General

GI000 COVER SHEET

GI001 CRANE & LAYDOWN SITE PLAN

GI101 SECOND LEVEL LIFE SAFETY PLAN

GC001 PHASING PLAN

Structural

SI001 STRUCTURAL GENERAL NOTES

SF101 OVERALL FRAMING PLAN

SF301 ENLARGED FRAMING PLANS

SF401 STRUCTURAL DETAILS

Architectural

AE104 ROOF - AREA-A - ROOF PLAN

AE111 SECOND LEVEL - AREA-A-RCP & ICRA PLAN

Fire Protection

F000 FIRE PROTECTION SYMBOLS AND ABBREVIATIONS

F200 SECOND LEVEL -AREA-A -FIRE PROTECTION

F201 THIRD LEVEL MECHANICAL ROOM-FIRE PROTECTION

Mechanical

EP200 FIRST FLOOR -ENLARGED -POWER

EP203 ROOF -OVERALL -POWER

EP203A ROOF -AREA-A -POWER

EP203B ROOF -AREA-B -POWER

EP203C ROOF -AREA-C -POWER

E500 ONE-LINE DIAGRAM

E700 ELECTRICAL SCHEDULES

M000 MECHANICAL SYMBOLS AND ABBREVIATIONS

MD102 SECOND LEVEL -OVERALL -MECHANICAL -DEMOLITION

MD102A SECOND LEVEL -AREA-A -MECHANICAL -DEMOLITION

MD102B SECOND LEVEL -AREA-B -MECHANICAL -DEMOLITION

MD102C SECOND LEVEL -AREA-C -MECHANICAL -DEMOLITION

MD103 ROOF -OVERALL -MECHANICAL -DEMOLITION

MD103A ROOF -AREA A -MECHANICAL DEMOLITION

MD103B ROOF -AREA B -MECHANICAL DEMOLITION

MH203B ROOF -AREA-B -MECHANICAL

MH203C ROOF -AREA-C -MECHANICAL

M300 ENLARGED MECHANICAL ROOM

M400 RISER DIAGRAMS

M401 RISER DIAGRAMS

M500 MECHANICAL DETAILS

M501 MECHANICAL DETAILS

M600 MECHANICAL SCHEDULES

Electrical

E000 ELECTRICAL SYMBOLS AND ABBREVIATIONS

ED100 FIRST FLOOR -ENLARGED -POWER -DEMOLITION

ED103 ROOF -OVERALL -ELECTRICAL -DEMOLITION

ED103A ROOF -AREA-A -ELECTRICAL -DEMOLITION

ED103B ROOF -AREA-B -ELECTRICAL -DEMOLITION

ED103C ROOF -AREA-C -ELECTRICAL -DEMOLITION

MD103C ROOF -AREA C -MECHANICAL DEMOLITION

MD300 ENLARGED MECHANICAL ROOM -DEMOLITION

MH202 SECOND LEVEL -OVERALL -MECHANICAL

MH202A SECOND LEVEL -AREA-A -MECHANICAL

MH202B SECOND LEVEL -AREA-B -MECHANICAL

MH202C SECOND LEVEL -AREA-C -MECHANICAL

MH203 ROOF -OVERALL -MECHANICAL

MH203A ROOF -AREA-A -MECHANICAL

ERIC G.

SHERMAN

E-82069

STATE OF OHIO

P

RR

O

F

ESS IONA L ENG

IN

E

E

REG I TERED

S

8910 Purdue Road, Suite 320 Indianapolis, IN 46268 Phone: 317.931.9800

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMP

321 4 5 6 7 8 9 10 www.specializedeng.com SES Project :

DESIGNER OF RECORDCONSULTANT

U.S. Department of Veterans Affairs

GUIDON DESIGN

1221 N Pennsylvania St, Indianapolis, IN 46202 Phone: 317.800.6388 www.guidondesign.com GD Project: 24-1012-01

ARCHITECT, STRUCTURAL ENGINEER

03/26/2025

A u to d e s k D o c s /2

.0

V

A C o lu m b u s

O H

A

E R e p la c e

A ir -C o o le d C h ill e rs

/7

-1

.B .G

.R

.r v t

/2

/2

:4

:2

A

M

GI000

COVER SHEET Replace Air Cooled Chillers

Chalmers P. Wylie VA Ambulatory

Care Center

420 N. James Rd, Columbus, OH 43219

01A

03/26/2025 JLN AEA

23203.001

100% CONSTRUCTION

DOCUMENTS

757-23-101

Replace Air Cooled Chillers Chalmers P. Wylie VA Ambulatory Care Center

420 N. James Rd, Columbus, OH 43219

Revisions: Date:

CONTRACTOR LAY-DOWN AREA

CRANE SETUP LOCATION

ERIC G.

SHERMAN

E-82069

STATE OF OHIO

P

RR

O

F

ESS IONA L ENG

IN

E

E

REG I TERED

S

333 E 2nd Street, Suite 16 Ogallala, NE 69153 Phone: 308.284.7323

8910 Purdue Road, Suite 320 Indianapolis, IN 46268 Phone: 317.931.9800

7100 East Belleview Ave.

Suite 107 Greenwood Village, CO 80111 Phone: 720.200.5955

1300 Baxter Street, Suite 230 Charlotte, NC 28204 Phone: 704.348.3097

10360 Ellison Circle Omaha, NE 68134 Phone:

402.991.5520

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMP

321 4 5 6 7 8 9 10 www.specializedeng.com SES Project :

DESIGNER OF RECORDCONSULTANT

U.S. Department of Veterans Affairs

NE Certificate Of Authorization Number: CA-1620

GUIDON DESIGN

1221 N Pennsylvania St, Indianapolis, IN 46202 Phone: 317.800.6388 www.guidondesign.com GD Project: 24-1012-01

ARCHITECT, STRUCTURAL ENGINEER

03/26/2025

A u to d e s k D o c s /2

.0

V

A C o lu m b u s

O H

A

E R e p la c e

A ir -C o o le d C h ill e rs

/7

-1

.B .G

.R

.r v t

/2

/2

:4

:2

A

M

GI001

CRANE & LAYDOWN SITE PLAN Replace Air Cooled Chillers

Chalmers P. Wylie VA Ambulatory

Care Center

420 N. James Rd, Columbus, OH 43219

01A

03/26/2025

23203.001

100% CONSTRUCTION

DOCUMENTS

757-23-101

NO SCALE

CRANE & LAYDOWN SITE PLAN

GENERAL NOTES:

1. THE CRANE SETUP LOCATION INDICATED IS WITHIN THE EMERGENCY ENTRANCE DROP OFF

AREA. PROVIDE A CRANE SCHEDULE TO THE VA AT START OF PROJECT TO ALLOW FOR VA

PLANNING.

2. CRANE MOBILIZATION DATES SHALL BE REVIEWED WITH THE VA 2 WEEKS PRIOR TO EACH

INSTANCE OF A CRANE ON SITE. THE COORDINATION OF THE CRANE SHALL INCLUDE START

AND FINISH DURATIONS.

3. PROVIDE GROUND PROTECTION FOR CRANE SETUP. ANY DAMAGED CONCRETE OR

LANDSCAPING SHALL BE REPLACED TO MATCH EXISTING.

4. PROVIDE TEMPORARY PROTECTIVE FENCING AROUND CRANE DURING SETUP AND TEAR

DOWN TO ALLOW ED ENTRANCE TO BE UTILIZED. PRIOR TO CRANE OPERATION, ED

ENTRANCE SHALL BE TEMPORARILY FENCED OFF AND LIFT AREA CLEARED. VA WILL BE

REQUIRED TO PLAN FOR ALTERNATE ED ENTRY FROM THE GENERAL POPULATION DURING

CRANE EVENTS.

5. WORK ASSOCIATED WITH CRANE SHALL BE PERFORMED IN STRICT COMPLIANCE WITH OSHA

AND OTHER GOVERNING REGULATIONS.

6. CONTRACTOR SHALL REVIEW VA AND OTHER REQUIREMENTS PRIOR TO STARTING CRANE

WORK. IT WILL BE A REQUIREMENT THAT ALL SITE AND BUILDING LOCATIONS WITHIN THE

CRANE PATH BE VACATED DURING EACH LIFT EVENT. BUILDING AREAS WITHIN PATH OF LIFT

SHALL BE VACATED FOR TWO LEVELS BELOW THE ROOF LINE.

7. THE CONTRACTOR AND VA SHALL REVIEW A PLAN FOR AMBULANCE ENTRY DURING A LIFT

EVENT. IN MOST VA LOCATIONS, SHOULD AN AMBULANCE NEED TO ARRIVE TO THE

EMERGENCY DEPARTMENT, VA PERSONNEL WILL ISSUE A STOP OF WORK ORDER FOR

CRANE ACTIVITIES TO ALLOW FOR THE AMBULANCE TO ENTER THE SITE. THE STOP WORK

ORDER FOR CRANE ACTIVITIES SHALL REMAIN IN EFFECT UNTIL AREA IS CLEAR.

8. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PROJECT CRANE ACTIVITIES.

9. CRANE LIFT(S) SHALL BE DONE AFTER HOURS.

N

A.

B.

THIS LIFE SAFETY PLAN WAS PRODUCED BY FP&C CONSULTANTS AND IS

PROVIDED HERE FOR REFERENCE ONLY, DATED 04-19-2022. IT WAS

PROVIDED BY THE VA AS THE CURRENT LIFE SAFETY PLAN FOR THE

BUILDING DURING THE DESIGN PHASE OF PROJECT 757-23-101.

SHOULD ANY PENETRATIONS BE MADE THROUGH RATED ASSEMBLIES,

CONTRACTOR SHALL SEAL AS REQUIRED, SEE SPECIFICATIONS.

GENERAL NOTES

8910 Purdue Road, Suite 320 Indianapolis, IN 46268 Phone: 317.931.9800

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMP

321 4 5 6 7 8 9 10 www.specializedeng.com SES Project :

DESIGNER OF RECORDCONSULTANT

U.S. Department of Veterans Affairs

AREA - A

AREA - B

AREA - C

KEY PLAN :-

GUIDON DESIGN

1221 N Pennsylvania St, Indianapolis, IN 46202 Phone: 317.800.6388 www.guidondesign.com GD Project : 24-1012-01

ARCHITECT, STRUCTURAL ENGINEER

Au to de sk

D oc s:

//2

.0

VA

C ol um bu s (O

H ) A

E R ep la ce A ir- C oo le d C hi lle rs /2

4.

.0

1_ A_ v2 4.

rv t

3/

/2

3:

:1

PM

GI101

SECOND LEVEL LIFE SAFETY

PLAN

Replace Air Cooled Chillers Chalmers P. Wylie VA Ambulatory Care Center

420 N. James Rd, Columbus, OH

01A

03/26/2025 JN TS

CONSTRUCTION

DOCUMENTS

757-23-101

23203.001

ACH-3

ACH-1

ACH-2

PHASE 1

PHASE 2

PHASE 3

PIPING INSTALLED IN PHASE 1,

OPERATIONAL IN PHASE 4

PUMPS INSTALLED IN

PHASE 1, OPERATIONAL

IN PHASE 4

ABCDEFGHJK

8910 Purdue Road, Suite 320 Indianapolis, IN 46268 Phone: 317.931.9800

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

STAMP

321 4 5 6 7 8 9 10 www.specializedeng.com SES Project :

DESIGNER OF RECORDCONSULTANT

U.S. Department of Veterans Affairs

AREA - A

AREA - B

AREA - C

KEY PLAN :-

GUIDON DESIGN

1221 N Pennsylvania St, Indianapolis, IN 46202 Phone: 317.800.6388 www.guidondesign.com GD Project : 24-1012-01

ARCHITECT, STRUCTURAL ENGINEER

03/26/2025

A u to d e s k D o c s /2

.0

V A

C o lu m b u s

O H

A

E R e p la c e

A ir -C o o le d C h ill e rs

/2

.0

V A

C o lu m b u s A

E R e p la c e

A C

C S

E S

.r v t

/2

/2

:3

:4

A

M

GC001

PHASING PLAN Replace Air Cooled Chillers

Chalmers P. Wylie VA Ambulatory

Care Center

420 N. James Rd, Columbus, OH 43219

01A

03/26/2025 DAB BJB

23203.001

CONSTRUCTION

DOCUMENTS

757-23-101

N

5 5 10 15 20 25 30 35 40 45

1/16" = 1'-0"

FEETSCALE

1/16" = 1'-0"

MECHANICAL PHASING PLAN

A PORTION OF THE WORK TO CONNECT NEW PIPING TO EXISTING ABOVE THE CEILING OF THE SECOND FLOOR WILL IMPACT THE LAB SPACE BELOW. COORDINATE REQUIREMENTS WITH THE COR. PROVIDE ALL GENERAL

CONSTRUCTION CUTTING AND PATCHING REQUIRED TO PERFORM THE WORK INDICATED.

DRAIN THE EXISTING ETHYLENE GLYCOL SOLUTION FROM THE PIPING SYSTEM AND FILL WITH THE PROPYLENE

GLYCOL SOLUTION INDICATED IN THE SCHEDULES.

INSTALL NEW STRUCTURAL STEEL FRAME FOR CHILLER ACH-3.

INSTALL NEW BREAKER THAT SERVES ACH-3. ROUTE CONDUIT AND FEEDERS ALONG THE SAME ROUTE AS THE EXISTING CONDUIT AND FEEDERS. INSTALL NEW BREAKER TO SERVE CHWP-5. INSTALL NEW FEEDERS AND

CONDUIT ALONG THE SAME ROUTE AS EXISTING.

ADD AIR COOLED CHILLER ACH-3, PIPING AND CONTROLS. PROVIDE PIPING TIE-INS TO THE EXISTING PIPING SYSTEM AS SHOWN ON THE PHASE 1 SEQUENCE - CHILLED WATER FLOW SCHEMATIC, SHEET M400. START-UP

CHILLER AND VERIFY IT IS RUNNING UNDER CONTROL.

INSTALL NEW PIPING ON THE ROOF AND TO THE MECHANICAL ROOM. INSTALL VALVES AND CAP PIPING AS SHOWN ON THE PHASE 1 - CHILLED WATER FLOW SCHEMATIC, SHEET M400. FILL THE SYSTEM WITH

PROPYLENE GLYCOL SOLUTION.

INSTALL NEW CHWP-3, CHWP-4 AND CHWP-5, NEW AS-4, NEW GLYCOL FEEDER AND NEW PIPING IN THE MECHANICAL ROOM AS SHOWN ON THE INTERMEDIATE SEQUENCE CHILLED WATER FLOW SCHEMATIC, SHEET M400.

INSTALL NEW FEEDERS AND CONDUIT FOR CHWP-3, CHWP-4 AND CHWP-5. INSTALL BREAKER FOR CHWP-5.

INSTALL POWER AND CONTROLS FOR NEW PUMPS. NEW PUMPING AND PIPING SYSTEM WILL NOT YET BE

OPERATIONAL. SYSTEM SHALL CONTINUE TO RUN OFF OF THE ORIGINAL PUMPS.

PHASING OF CHILLED WATER REPLACEMENT

PHASE 1:

REMOVE EXISTING AIR COOLED CHILLER ACH-2, PIPING AND CONTROLS.

DISCONNECT EXISTING POWER CONNECTION TO ACH-2. REMOVE EXISTING BREAKER AND REPLACE WITH

NEW. UTILIZE EXISTING CONDUIT. PROVIDE NEW FEEDERS PER SCHEDULE.

PROVIDE NEW AIR COOLED CHILLER ACH-2, PIPING AND CONTROLS. PROVIDE PIPING TIE-INS TO THE EXISTING PIPING SYSTEM. START-UP CHILLER AND VERIFY IT IS RUNNING UNDER CONTROL. PROVIDE VALVED CONNECTION TO THE NEW 8" GCWS PIPING SHOWN ON THE PHASE 2 SEQUENCING - CHILED WATER FLOW

SCHEMATIC, SHEET M400..

NEW PIPING AND PUMPS SYSTEM WILL NOT YET BE OPERATIONAL. SYTEM WILL CONTINUE TO RUN OFF OF THE

ORIGINAL PUMPS.

PROVIDE ALL GENERAL CONSTRUCTION CUTTING AND PATCHING REQUIRED TO PERFORM THE WORK

INDICATED.

PHASE 2:

REMOVE AIR COOLED CHILLER ACH-1, PIPING AND CONTROLS.

DISCONNECT EXISTING POWER CONNECTION TO ACH-1. REMOVE EXISTING BREAKER AND REPLACE WITH

NEW. UTILIZE EXISTING CONDUIT. PROVIDE NEW FEEDERS PER SCHEDULE.

PROVIDE NEW AIR COOLED CHILLER ACH-1, PIPING AND CONTROLS. PROVIDE PIPING TIE-INS TO THE EXISTING PIPING SYSTEM. START-UP CHILLER AND VERIFY IT IS RUNNING UNDER CONTROL. PROVIDE VALVED CONNECTION TO THE NEW 8" GCWS PIPING SHOWN ON PHASE 3 SEQUENCING - CHILLED WATER FLOW

SCHEMATIC, SHEET M401.

NEW PIPING AND PUMPS SYSTEM WILL NOT YET BE OPERATIONAL. SYTEM WILL CONTINUE TO RUN OFF OF THE

ORIGINAL PUMPS.

PROVIDE ALL GENERAL CONSTRUCTION CUTTING AND PATCHING REQUIRED TO PERFORM THE WORK

INDICATED.

PHASE 3:

DEMOLISH CONNECTIONS TO THE ORIGINAL PIPING SYSTEM AND CAP WHERE SHOWN ON THE PHASE 4

SEQUENCE - CHILLED WATER FLOW SCHEMATIC, SHEET M401.

DISCONNECT EXISTING CHWP-3 AND CHWP-4. PROVIDE NEW BREAKERS AND CONNECT PREVIOUSLY

INSTALLED NEW FEEDERS AND CONDUIT.

START NEW PUMPS, CONVERT CONTROLS TO NEW SEQUENCING, AND SET THE SYSTEM INTO OPERATION.

DRAIN GLYCOL FROM ABANDONED ORIGINAL PIPING IN THE CEILING SPACE OF THE SECOND FLOOR.

PROVIDE ALL GENERAL CONSTRUCTION CUTTING AND PATCHING REQUIRED TO PERFORM THE WORK

INDICATED.

PHASE 4:

1. THIS PHASING PLAN IS PROVIDED TO THE CONSTRUCTION CONTRACTOR TO UTILIZE AS A BASIS FOR SCHEDULE DEVELOPMENT AND PROJECT SEQUENCING ONLY. THE CONSTUCTION CONTRACTOR SHALL BE RESPONSIBLE FOR DEVELOPING A PROJECT FINAL SCHEDULE THAT TAKES INTO ACCOUNT THE

SEQUENCING REQUIREMENTS AND ALLOWS THE PROJECT SCOPE OF WORK TO BE COMPLETED PER

THE CONSTRUCTION DOCUMENTS AND VA REQUIREMENTS.

2. THE INTENT OF THE PHASING PLAN IS TO SEQUENCE THE WORK IN A MANNER THAT WILL ALLOW THE CHILLED WATER SYSTEM TO BE OPERATIONAL THROUGHOUT THE DURATION OF THE PROJECT. WITH PRIOR APPROVAL FROM AND COORDINATION WITH THE COR, THE SYSTEM CAN BE DOWN FOR PRE-

SCHEDULED WEEK LONG DURATIONS DURING THE HEATING MONTHS OF DECEMBER, JANUARY AND

FEBRUARY WHEN THE CONNECTED UNIT IS OPERATING UNDER AIR SIDE ECONOMIZER CONTROL.

DURING ALL OTHER MONTHS, THE SYSTEM SHALL BE OPERATIONAL WITH A MINIMUM OF TWO

CHILLERS CAPABLE OF BEING OPERATED, UNDER THE EXISTING SYSTEM SEQUENCE OF OPERATION, UNTIL SUCH TIME THAT ALL NEW EQUIPMENT IS RUNNING UNDER THE NEW SEQUENCE OF CONTROL.

ANY DOWN TIME REQUIRED IN THOSE MONTHS SHALL BE COORDINATED WITH AND APPROVED BY THE COR AND THE CONTRACTOR SHALL ASSUME THAT THESE TIMES WILL BE DURING NIGHTS, WEEKENDS

AND HOLIDAYS.

3. OUTAGES DURING NIGHTS, WEEKENDS, AND HOLIDAYS SHALL BE COMPLETED A MINIMUM OF 2 HOURS

PRIOR TO BUSINESS START TIME.

4. RTU-10 SHALL CONTINUE TO OPERATE UNDER NORMAL OPERATION DURING CHILLED WATER

OUTAGES. AIRFLOWS, HEATING, FILTRATION AND PRESSURIZATION SHALL BE MAINTAINED IN THE

OCCUPIED SPACES.

5. RTU-13 SHALL CONTINUE TO OPERATE UNDER NORMAL OPERATION DURING PERIODS WHEN THE COIL IS BEING RE-PIPED. ASSURE THAT THE WORK IS BEING PERFORMED WHEN THE OUTSIDE AIR IS COOL

ENOUGH TO PROVIDE SPACE COOLING WITHOUT CHILLED WATER.

6. IF THERE ARE SPACES SERVED BY RTU-10 WHERE TEMPERATURE AND HUMDITY ARE CRITICAL AND CANNOT BE MAINTAINED WHEN THE CHILLED WATER IS NOT ACTIVE, WITHOUT CHILLED WATER, THE

CONTRACTOR SHALL PROVIDE TEMPORARY MEANS OF COOLING FOR THESE CONDITIONS. THIS

REQUIREMENT APPLIES TO THE SCHEDULED SHUTDOWN PERIODS (NIGHTS, WEEKENDS, HOLIDAYS, HEATING MONTHS).

GI000 - COVER SHEET
GI001 - CRANE & LAYDOWN SITE PLAN
GI101 - SECOND LEVEL LIFE SAFETY PLAN
GC001 - PHASING PLAN