About this file

This document contains a bid sheet and related federal contract opportunity for replacing condenser water piping at the Brooklyn VA Medical Center. The bid sheet outlines three items: Base Bid Item I for replacing condenser water piping from the chiller plant to cooling towers for $2,913,396; Bid Item II using Aquatherm piping for the entire system for $2,663,396; and Bid Item III including Bid Item I costs and lead paint abatement for $2,463,396. The federal contract opportunity provides additional details on the project scope, which involves replacing condenser water piping and associated valves and equipment. The solicitation requests bids for the base work and two alternates using Aquatherm piping for the entire system and including lead paint abatement. The completion period is 260 days with off-hours work potentially required.

View the file

Other files

File Type Posted
36C24221B0014.docx DOCX document
S02 DRAWINGS.pdf PDF
Addendum.pdf PDF
S02 SPECS.pdf PDF
S02 ADDITIONAL INSERTS.pdf PDF
S02 ALL POSTERS.pdf PDF
C10 VA ID PACKAGE UPDATED 01-16-2019.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Title: Replace Condenser Water Piping Building 4 Project No: 630A4-13-403

STATEMENT OF BID ITEM(S)

A. BASE BID ITEM I: Work includes general construction, replacement of condenser water piping from chiller plant to cooling towers on the roof on the east side of Building 4. Replacement of valves controlling flow in these lines, electrical heat tracing of piping, and installation of centrifugal separator/cleaner package.

Construction Estimate: $2,913,396 Completion Time: 260 calendar days

B. BID ITEM II: BASE BID ITEM I use of Aquatherm Piping (Polypropylene (PP-R)) on entire system in lieu of steel. To include flange connections, piping, elbows as needed.

Construction Estimate: $2,663,396 Completion Time: 260 calendar days

C. BID ITEM III: BASE BID ITEM II base bid item I and costs associated with scraping and repainting lead paint structural steel.

Construction Estimate: $2,463,396 Completion Time: 230 calendar days

File details come from the government source that posted it. Updated .