This document is a construction schedule for the San Diego VA Medical Center SCI/CLC project under contract number W912PL21C0004 with the U.S. Army Corps of Engineers. It outlines key milestones and deadlines for the project, including mobilization in April 2021, construction start in May 2021, structural steel work beginning in May 2022, garage completion in September 2023, and overall construction completion scheduled for March 2024. Later milestones include contractor evaluation and final payment in mid-2024, beneficial occupancy by November 2024, and project fiscal completion by March 2025. The related federal contract opportunity RFQ 36C77622Q0237 from the Department of Veterans Affairs Technology Acquisition Center Austin is for San Diego SCI IOT&A but provides no further detail on required products or services.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Group Phase Milestone Event Original Date Scheduled Date Scheduled Time Actual Date Status
System Construction Contract Award 02/12/2021 02/11/2021 Completed System Construction NTP Acknowledged 03/08/2021 03/08/2021 Completed Contract Construction Preconstruction Conference 03/11/2021 03/11/2021 Completed Contract Construction Mobilization 04/15/2021 04/19/2021 Completed System Construction Construction Start Date 05/17/2021 05/17/2021 Completed Contract Construction Government Office Set up 07/28/2021 07/29/2021 Completed District Construction Post Award AAR 10/29/2021 11/04/2021 Completed Contract Construction 12 KVA Reroute Complete 11/22/2021 11/22/2021 Completed Contract Construction Start Structural Steel 05/16/2022 Scheduled Contract Construction Dry In Complete CLC/SCI 06/09/2023 Scheduled Contract Construction Garage Complete 09/22/2023 Scheduled System Construction Red Zone Meeting 01/22/2024 Scheduled System Construction Construction Completion 03/07/2024 Scheduled System Construction Contract Required Completion 03/08/2024 03/14/2024 N/A N/A System Post Construction Contractor Evaluation Date 05/06/2024 Scheduled System Post Construction Transfer Document Date 05/06/2024 Scheduled District Post Construction Post Construction AAR 05/06/2024 Scheduled District Design Real Property Cards to User 05/21/2024 Scheduled System Post Construction Contractor Final Payment 07/05/2024 Scheduled System Post Construction Beneficial Occupancy Date 11/03/2024 11/03/2024 Scheduled System Post Construction Contract Physical Completion 11/10/2024 Scheduled System Post Construction Project Fiscal Completion 03/03/2025 Scheduled System Post Construction AE Evaluation Date N/A VA Construction Latest CSRA Complete Not Scheduled VA Construction CD1 100% FastTrack Submittal Not Scheduled VA Construction SD2 35% Design Complete Not Scheduled VA Construction CD1 100% Design Complete Not Scheduled VA Construction CD2 RTC Design Complete Not Scheduled VA Construction DVA Commissioning Start Date Not Scheduled
4/20/2022 San Diego DVA Resident
Office W912PL21C0004 San Diego VA Medical Center SCI/CLC
All Events
L1005217US Army Corps of Engineers
CONTROLLED UNCLASSIFIED INFORMATION
Page: 1
CONTROLLED UNCLASSIFIED INFORMATION
File details come from the government source that posted it. Updated .