S02-ATTACHMENT 1 QASP.pdf

PDF 1 MB Posted

Attached to
RADIATION SAFETY ASSESSMENT Federal contract opportunity
Solicitation number
36C25623Q0843
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

View the file

Other files for this federal contract opportunity

Other files attached to RADIATION SAFETY ASSESSMENT, newest first.
File Type Posted
ATTACHMENT 6- GSA 1736 Page 1 (2).pdf PDF
S02- RFQ 36C25623Q0843.pdf PDF
S02-ATTACHMENT 3 -CONTRACTOR CERTIFICATION IMMIGRATION.pdf PDF
S02-ATTACHMENT 4 - EXPERIENCE REFERENCE CONTRACT WORKSHEET.pdf PDF
ATTACHMENT 5- GSA 1736 Page 1 (1).pdf PDF
S02-ATTACHMENT 2 - CONTRACTOR KEY PERSONNEL AND COI.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ 36C25623Q0843

Quality Assurance Surveillance Plan (QASP)

The contractor will be evaluated in accordance with the following:

1. PURPOSE

This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:

• What will be monitored?

• How monitoring will take place.

• Who will conduct the monitoring?

• How monitoring efforts and results will be documented.

This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance.

This QASP is a “living document” and the Government may review and revise it on a regular basis. However, the Government shall coordinate changes with the contractor through contract modification. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.

2. GOVERNMENT ROLES AND RESPONSIBILITIES

The following personnel shall oversee and coordinate surveillance activities.

a. Contracting Officer (CO): The CO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment under this contract. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.

Assigned CO: Billy Morris Organization or Agency: NCO16

b. Contracting Officer’s Representative (COR): The COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance. The COR shall keep a quality assurance file. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.

Assigned COR: _______________________ Organization or Agency:

3. CONTRACTOR REPRESENTATIVES

The following employee(s) of the contractor serve as the contractor’s program manager(s) for this contract:

Primary:

Alternate:

ATTACHMENT 1

4. PERFORMANCE STANDARDS

The contractor is responsible for performance of ALL terms and conditions of the contract. CORs will provide contract progress reports quarterly to the CO reflecting performance on this plan and all other aspects of the resultant contract. The performance standards outlined in this QASP shall be used to determine the level of contractor performance in the elements defined. Performance standards define desired services. The Government performs surveillance to determine the level of Contractor performance to these standards.

The Performance Requirements are listed below in Section 6. The Government shall use these standards to determine contractor performance and shall compare contractor performance to the standard and assign a rating. At the end of the performance period, these ratings will be used, in part, to establish the past performance of the contractor on the contract.

5. METHODS OF QA SURVEILLANCE

Various methods exist to monitor performance. The COR shall use the surveillance methods listed below in the administration of this QASP.

a. PERIODIC INSPECTION. Inspections scheduled and reported quarterly per COR delegation or as needed. OPPE will be reviewed (5) random patient charts per Fiscal Quarter throughout the performance period.

All inspections and reports will be conducted in compliance with VA Privacy and Information security standards.

b. VALIDATED USER/CUSTOMER COMPLAINTS. VAMC utilized the Patient Advocate Reporting System for complaints. The monitoring is direct and ongoing throughout the performance period.

6. SAMPLE QASP PERFORMANCE REPORT DATE: __________________

Measures PWS Referen ce

Performance Requirement

Standard Acceptable Quality Level

Surveillan ce

Method

Met AQL/DID NOT MEET

AQL-

CPAR RATING/ADD

COMMENTS

Quality Performance

1.5 All Contractor’s

shall perform in accordance with PWS standards

100% of care provided within PWS standards

92% Observation and Inspection

(OPPE)

(Bi-annually)

Qualifications of Key Personnel

1.7 Contractor’s

Medical Physicist shall meet the qualifications in accordance with

PWS

requirements.

All (100%) 100% Periodic Inspection or Random Sampling of qualificatio n documents

Scope of Practice/ 1.3 1.5

Contractor’s shall perform within their individual scopes of practice/ privileging g

All (100%) Contractor’s Medical Physicist within their scope of practice/ privilege s 100% of the time.

100% Contractor’s Medical Physicist perform within their scope of practice/privileges 100% of the time.

OPPE

Patient Access N/A N/A N/A N/A

Patient Safety 1.4.5 Life-threatening deficiencies or critical non-conformances shall be reported IAW PWS

All (100%) founds during testing shall be reported immediate to the COR. If the COR is not available, the contractor shall report to the near staff member in-charge, and to the Biomedical Department.

100% OPPE

Maintains licensing, registration, and certification

1.7 Updated

Licensing, registration and certification shall be provided as they are renewed.

Licensing and registration information kept current.

All (100%) licensing, registration(s) and certification(s) for Contractor’s shall be provided as they are renewed.

Licensing and registration information kept current.

100% licensing, registration(s) and certification(s) for Contractor’s shall be provided as they are renewed.

Licensing and registration information kept current. No acceptable deviation.

Periodic Inspection or Random Sampling

Mandatory Training N/A N/A N/A N/A

7. CPAR RATINGS ASSIGNED TO QASP ITEMS:

Metrics and methods are designed to determine rating for a given standard and acceptable quality level. The following ratings shall be used (Reference: CPARS User Manual https://www.cpars.gov/documents/CPARS- Guidance.pdf)

EXCEPTIONAL: Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Note: To justify an Exceptional rating, you should identify multiple significant events in each category and state how it was a benefit to the GOVERNMENT.

However, a singular event could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

VERY GOOD: Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

Note: To justify a Very Good rating, you should identify a significant event in each category and state how it was a benefit to the GOVERNMENT. Also, there should have been NO significant weaknesses identified.

SATISFACTORY: Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Note: To justify a Satisfactory rating, there should have been only minor problems, or major problems the contractor recovered from without impact to the contract.

Also, there should have been NO significant weaknesses identified.

MARGINAL: Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

Note: To justify Marginal performance, you should identify a significant event in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. A Marginal rating should be supported by referencing the management tool that notified the contractor of the contractual deficiency (e.g.

Management, Quality, Safety or Environmental Deficiency Report or letter).

UNSATISFACTO

RY: Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

https://www.cpars.gov/documents/CPARS-Guidance.pdf https://www.cpars.gov/documents/CPARS-Guidance.pdf

Note: To justify an Unsatisfactory rating, you should identify multiple significant events in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. However, a singular problem could be of such serious magnitude that it alone constitutes an unsatisfactory rating. An Unsatisfactory rating should be supported by referencing the management tools used to notify the contractor of the contractual deficiencies (e.g. Management, Quality, Safety or Environmental Deficiency Reports, or letters).

8. DOCUMENTING PERFORMANCE

a. The Government shall document positive and/or negative performance. Any report may become a part of the supporting documentation for any contractual action and preparing annual past performance using CONTRACTOR PERFORMANCE ASSESSMENT REPORT (CPAR).

b. If contractor performance does not meet the Acceptable Quality level, the CO shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case the CO shall document the discussion and place it in the contract file. When the COR and the CO determines formal written communication is required, the COR shall prepare a Contract Report (CR), and present it to CO. The CO will in turn review and will present to the contractor's program manager for corrective action.

The contractor shall acknowledge receipt of the CR in writing. The CR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CR will also state how long after receipt the contractor has to present this corrective action plan to the CO. The Government shall review the contractor's corrective action plan to determine acceptability. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance and the acceptability of the Contractor’s corrective action plan.

Any CRs may become a part of the supporting documentation for any contractual action deemed necessary by the CO. See Sample CR on the following page.

9. COR AND CONTRACTOR ACKNOWLEDGEMENT OF QASP

SIGNED:

COR NAME/TITLE DATE

SIGNED:

CONTRACTOR NAME/TITLE DATE

CONTRACT REPORT

1. CONTRACT NUMBER 2. REPORT NUMBER FOR THIS DISCREPANCY

3. TO: (Contracting Officer) 4. FROM: (Name of COR)

5. DATES

a. CR PREPARED b. RETURNED BY

CONTRACTOR:

c. ACTION COMPLETE

6. Issue Identified (Describe in detail. Include reference to PWS Directive; attach continuation sheet if necessary.)

7. SIGNATURE OF COR Date:

8. SIGNATURE OF CONTRACTING OFFICER Date:

9a. TO (Contracting Officer) 9a. FROM (Contractor)

10. CONTRACTOR RESPONSE AS TO CAUSE AND ACTIONS TO PREVENT RECURRENCE. (Cite applicable quality control program procedures or new procedures. Attach continuation sheet(s) if necessary.)

11. SIGNATURE OF CONTRACTOR REPRESENTATIVE Date:

12. GOVERNMENT EVALUATION.

13. GOVERNMENT ACTIONS

14. CLOSE OUT

NAME TITLE SIGNATURE DATE

CONTRACTOR

NOTIFIED

COR

CONTRACTING

OFFICER

Various methods exist to monitor performance. The COR shall use the surveillance methods listed below in the administration of this QASP.
a. PERIODIC INSPECTION. Inspections scheduled and reported quarterly per COR delegation or as needed. OPPE will be reviewed (5) random patient charts per Fiscal Quarter throughout the performance period. All inspections and reports will be conducted i...
b. VALIDATED USER/CUSTOMER COMPLAINTS. VAMC utilized the Patient Advocate Reporting System for complaints. The monitoring is direct and ongoing throughout the performance period.
b. VALIDATED USER/CUSTOMER COMPLAINTS. VAMC utilized the Patient Advocate Reporting System for complaints. The monitoring is direct and ongoing throughout the performance period.
a. The Government shall document positive and/or negative performance. Any report may become a part of the supporting documentation for any contractual action and preparing annual past performance using CONTRACTOR PERFORMANCE ASSESSMENT REPORT (CPAR).
b. If contractor performance does not meet the Acceptable Quality level, the CO shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case the CO shall document the discussion and p...