This document is a Statement of Work (SOW) for a federal contract opportunity to replace doors, repair or replace gutters, and fix or replace damaged siding at the USDA NRCS Big Flats Plant Materials Center in Corning, New York.

The SOW requires the contractor to furnish all materials, tools, equipment, and labor necessary to remove and install new doors, frames, and hardware at various locations in accordance with specific technical requirements. The contractor is also responsible for replacing or repairing gutters and downspouts, and repairing or replacing damaged siding on the shop/warehouse and equipment barn buildings. The anticipated period of performance is 15 calendar days. The solicitation is a 100% Small Business set-aside under NAICS code 238990 with an estimated magnitude between $25,000 and $100,000. The related federal contract opportunity is Solicitation Number 12FPC324Q0058 issued by the USDA Farm Production and Conservation - Acquisition and Procurement Division on behalf of the USDA-NRCS.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

LOCATION:

USDA NRCS Big Flats Plant Materials Center 3266 State Route 352 Corning, NY 14830

BACKGROUND

This Statement of Work (SOW) encompasses the purchase of (6) hollow metal doors, repair or replace gutters and fix or replace broken siding at the USDA NRCS Big Flats Plant Materials Center’s (BFPMC) greenhouse, seed barn, and shop buildings.

SCOPE OF WORK

This requires the Contractor to replace existing doors, frames and hardware in various locations;

furnish all materials, tools, equipment and labor necessary to remove the existing doors, frames and hardware (unless otherwise specified), prepare openings and install new doors, frames and hardware in accordance with the requirements, specifications and recommendations of this document and those of the manufacturer of the new doors, frames and hardware being installed.

Additionally, if new locks are installed, the locks will need to be configured to the current keys used.

Gutters and gutter guards will need to be furnished and replaced, unless repairs are feasible, at the shop/warehouse, greenhouse, and office. New gutters, where no gutters are currently, will need to be installed at the office, seed barn and equipment barn.

Siding at the shop/warehouse will need to be replaced/repaired in a 3 small areas with proper insulation and matching color (white).

PERSONNEL

A. Owner: Shawnna Clark, BFPMC Manager B. NRCS Contract Specialist (CS), Stephen Case C. NRCS Contract Officer Representative (COR), Shawnna Clark D. Contractor, TBD

DOOR SPECIFICATIONS

• Cold-rolled galvannealed steel; 18 gauge; 1-3/4” (44 .4 mm) thick (see below for all door dimensions)

• Foamed-in-place polyurethane core or similar for best energy efficiency; i.e., Insulated polystyrene core (R-Value 7.14, U-Value 0.14).

• Glazing- insulated flush design- G (1/2 glass);

• LEVEL 2 - HEAVY DUTY COMMERCIAL; HMMA 861 Commercial Hollow Metal

Door and Frame;

• Rust inhibitive prime coat ANSI/SDI A250.10

• Universal 4.5" x 4.5" Square Hinge Prep;

• Doors require a (3) hinge preparation , 7 Gauge hinge reinforcement ; non-removable security pins.

• Manufactured in the USA.

• Door closers will be of commercial grade installed at the top of door and be ADA compliant according to the Uniform Federal Accessibility Standards (sweep period of at least 3 seconds from door in 70-degree position to 3” from latch)

• Perimeter seals and gaskets will be installed to ensure a tight seal around the door.

• Caulking will be applied as needed around the frame.

• Threshold to be a maximum of 1/2” in height above the exterior concrete level to be

ADA compliant.

• Replace existing door handles and locks with keypad security, if applicable. If using existing locks, needs to be configured to current keys.

• All installation to be plumb and square and door must be free from rack and twist.

• Old or new doors cannot be left unsecured overnight. They must be able to be closed and locked.

ADDITIONAL SPECIFICATIONS FOR DOORS

Greenhouse and Seed Barn (just doors)

• (2) Single Door Panels that are Left-Handed reverse (36” x 80”)

• (2) Double Door Panels that are Left Hand Reverse (total width 72” x 80” height). Note:

both doors only have 1 door handle the other is latched to the frame and can be opened outward when needed.

• Install new thresholds, where needed.

• New door hardware must match the locations and fit properly in the existing frame.

• Confirm, before ordering, the measurements of the existing doors

• Door stops needed

Shop/Warehouse

• (2) Doors with frames; (both are 36” x 80”); current frames are wood.

• Left-handed, swing in

Frames o Standard hollow metal frames need to be factory primed for painting in the field.

New white paint will be needed for BOTH door and frame for all installations.

o Hollow metal frames cold-rolled, A-60 galvannealed in 16-gauge .

o Hollow metal frames welded.

o Locks with security keypad.

o Furnished with door stops.

Hardware shall comply with BHMA A156 series requirements. All doors and frames should be factory primed and prepared for hardware installation.

Receiving Material

• Upon receipt, all material shall be inspected for damage caused in shipping. If damaged material is found, it should be noted on the freight bill before signing.

• The contractor must also notify the distributor immediately of any damage or missing materials and be rectified.

On Site Storage (if needed) Proper storage of hollow metal material at the site must be followed.

1. Store all materials in a dry area. All hollow metal material should be stored so that it does not come in contact with water or moisture.

2. Do not use non-vented plastic or canvas.

3. Place doors and frames vertically on wood blocking at least 4” off the ground.

5. Provide at least ¼” air space between each door/frame to permit air circulation.

CONTRACTOR RESPONSIBILITIES

Contractor is responsible for coordination and installation of products covered under this Section and will:

1. Verify and provide to the manufacturer, actual opening sizes and site conditions by field measurements before fabrication/purchasing.

2. Verify that substrate conditions, whether existing or installed, are as detailed and are acceptable for product installation in accordance with the manufacturer’s instructions.

3. Install hollow metal products using persons experienced and trained in the handling and installation of hollow metal products, having successfully accomplished installations of similar scope and size. They need to be able to read and understand architectural plans and specified hardware requirements.

4. Assure all steps are taken by the installer, glazer, or others to prevent water penetration, such as proper caulking and weather stripping.

5. Contractor must seal all joints that are exposed to the elements after the frame assembly is installed.

6. Doors shall be adjusted to maintain perimeter clearances. Shimming shall be performed by the installer, as needed, to assure the proper clearances are achieved.

7. Sand, touch up and clean prime painted surfaces prior to finish painting in accordance with the finish paint manufacturer’s instructions.

8. The temporary spreader bar shall be removed and a setting spreader, supplied by the installer, shall be used for installation of the frame.

9. Contractor is responsible for removing old doors/frames and all debris and leaving the area clean when done.

ADDITIONAL REQUIREMENTS

• Finish paint can be either factory or contractor supplied but must meet the performance requirements and acceptance criteria as stated in ANSI/ SDI A250.3, Test Procedure and Acceptance Criteria for Factory Applied Finish Coatings for Steel Doors and Frames.

• Manufacturing Tolerances for Standard Steel Doors and Frames shall apply to the standard steel doors and frames specified.

• Door edges will be manufactured in accordance with manufacturer’s standard for that model.

• The top and bottom of the door shall be closed with either flush or inverted channels or closures.

• Doors shall be installed and fastened to maintain alignment with frames to achieve maximum operational effectiveness and appearance.

• Glazed exterior doors and frames must be steel and meet the requirements of SDI Grade II; Commercial metal doors must adhere to Steel Door Institute standards, and are ADA compliant.

• Doors and frames shall be reinforced, drilled and tapped to receive mortised hinges, locks, latches, and flush bolts as required. Preparation shall be in accordance with ANSI/BHMA A156.115 Hardware Preparation in Steel Doors or Steel Frames and ANSI/SDI A250.6, Recommended Practice for Hardware Reinforcing on Standard Steel Doors and Frames where applicable.

• Installation of hardware items shall be in accordance with the hardware manufacturer’s recommendations and templates. ANSI/SDI A250.6, Recommended Practice for Hardware Reinforcing on Standard Steel Doors and Frames shall be consulted for other pertinent information.

• Frames shall be installed plumb, level, rigid and in true alignment as recommended in ANSI/SDI A250.11 Recommended Erection Instructions for Steel Frames.

• Energy Efficient Exterior Openings: Comply with minimum thermal ratings,based on ASTMC 1363.Openings to be fabricated and tested as fully operable, thermal insulating door and frame assemblies.

• Verify actual dimensions of openings by field measurements before fabrication.

SUBMITTALS

A. Product Data: For each type of product indicated, include construction details, material descriptions, components, hardware reinforcements, and finishes.

B. Templates: Door hardware supplier is to furnish templates, template reference number and/or physical hardware to the door and frame supplier in order to prepare the doors and frames to receive the finish hardware items.

C. Shop Drawings: Include the following:

1. Elevations of each door design.

2. Details of doors.

3. Frame details for each frame type, including dimensioned profiles and metal thicknesses.

4. Details of anchorages, joints, field splices, and connections.

5. Locations of reinforcement and preparations for hardware.

6. Details of each different wall opening condition.

7. Details of accessories.

D. Samples for Verification:

1. Samples are only required by request.

E. Informational Submittals:

1. LEED Documentation: Submit manufacturer's environmental documentation and applicable sustainability program credits.

ADJUSTING AND CLEANING

A. Final Adjustments: Check and readjust operating hardware items immediately before final inspection. Leave work in complete and proper operating condition. Remove and replace defective work.

B. Remove stains and materials that will have and adverse affect on the doors and frames and restore slight blemishes in accordance with manufacturer’s instructions to match original finish.

C. Make sure all locks are functioning properly and any keys are provided with the proper configuration.

GUTTER, GUTTER GUARDS, DOWNSPOUTS and ASSOCIATED MATERIALS

REPAIR/REPLACEMENT

Requirements:

• Contractor will determine the size and type of gutters and downspouts that will give the greatest water flow, water capacity, and least amount of plugging. All final specifications will be approved by the Owner.

• Contractor’s responsibility to install gutters properly and if warranted upon inspection, placed behind the drip edge. Strip flashing must be used to bridge the gap between the drip edge and the back of the gutter if the gutter runs below the drip edge at the lower end of the gutter run.

• Gutter guards must be installed. Install only products that fit and install on top of the gutter and must be made of same material as gutter. No rolled metal or plastic screens.

• All gutters will be white, aluminum, seamless and properly sized for the type and size of roof. Install and use the proper gutter screws, gutter hangers, sealant, outlets and any other materials during the gutter replacement.

• Before installation and fabrication, all measurements of needed replacement gutters are to be confirmed as well as any additional materials needed, including any rotted soffit and fascia.

• Replace or repair any sections of downspouts that are needed and make sure are located properly to facilitate drainage and not interfere with walking, mowing, or driving areas.

• Use roof hanger mounting straps where needed. Ice will accumulate in winter months on the gutters so either a stronger hanger or more hangers to hold this extra weight for an extended period of time is needed.

• Proper slope must be adjusted, if any, during the installation process for adequate drainage.

• Make sure all seals and connecting points are free from leaks, are not loose, and no parts are missing before leaving the site.

Materials (must be rust proof):

1. Gutter Material: Aluminum, .032 Thickness

2. Downspout Material: Aluminum, .032 Thickness 3"x4" downspout and elbows

3. Finish gutters to match the roof fascia and rake trim.

Length of Gutters (approximate) and Gutter Guards Needed:

Before bidding and ordering, exact lengths and conditions need to be assessed and confirmed.

The lengths below are approximate and in linear feet.

• Shop/Warehouse- 150’ (replace)

• Office- 30’ (new and replace)

• Greenhouse- 100’ (replace)

• Seed Barn- 20’ (inspect)

• Equipment Barn (metal roof and will be new)- 220’

Total feet needed- 500’

Downspouts Repair, Replace or Install New:

Before bidding and ordering, exact lengths and buildings where needed, will need to be assessed and confirmed. The lengths below are approximate and feet.

• Shop/Warehouse- inspect current; repair and replace any damages to any part. 25’ from ground to shingle roof.

• Office- inspect current; repair and replace any damages to any part. Install new at entrance with proper drainage away from foundation. 15’ from ground to shingle roof.

• Greenhouse-inspect current; repair and replace any damages to any part. 10’ from ground to shingle roof.

• Seed Barn- inspect current; repair and replace any damages to any part. 25’ feet from ground to edge of metal roof.

• Equipment Barn- install new, associated materials, ensure proper drainage away from building. 25’ from ground to edge of metal roof.

SIDING REPAIRS (shop/warehouse, equipment barn)

Before bidding and ordering, exact damage and repair methods as well as lengths will need to be assessed and confirmed. The length and size of the holes and damaged sections are approximate.

There are 12 holes that are cracked, split and missing siding. No damages are more than 12” (w) x 12” (h). Holes have been caused by branches and equipment.

• Remove damaged sections of the siding pieces and nails or screws holding the sections into place, and replace with the same materials as currently installed.

• Contractor will make sure that the new replacement siding is cut and measured and secured properly to allow no moisture to penetrate. Replace any insulation where needed.

OR

• If new, replacement siding is not warranted, patches must be of same color and material to allow no moisture to enter.

• Caulk or any filler used must be cured properly and inspected before closeout.

DESPOSAL AND CLEANUP AFTER ALL WORK:

All old, damaged and removed gutters and siding plus any materials associated with their removal, will be removed and discarded, carefully, off-site.

Importantly, use a metal detector and thoroughly inspect around areas and buildings where work is being done to make sure all nails and screws are gone and other metal pieces.

File details come from the government source that posted it. Updated .