About this file

This document is an Invitation for Bid (IFB) issued by the Arkansas Department of Transformation and Shared Services (TSS) Office of State Procurement (OSP) for the Arkansas Department of Corrections (ADC) to obtain pricing and a contract for crop hauling services at ADC's East Arkansas Regional Unit - Farm Operation. The services are needed to haul crops such as corn, soybeans, and wheat from August through November, with peak season being August through October. The contract will be awarded to the lowest-bidding, responsible Prospective Contractor on an all or none basis. The initial term of the resulting contract will be for one (1) year, with the option to renew for up to six (6) additional one-year terms.

The bid responses must be submitted through ARBuy, the State's eProcurement system, by August 11, 2021, at 2:00 p.m. Central Time. Prospective Contractors must have an adequate number of vehicles, drivers, and other necessary equipment and supplies, and the drivers must possess a Commercial Driver License (CDL). Prospective Contractors must also maintain a minimum of $1,000,000.00 in liability coverage on their vehicles, equipment, and crops in transit.

View the file

Other files

File Type Posted
Contract and Grant Disclosure Form~16.pdf PDF
S000000030 IFB Bid Response Packet.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF ARKANSAS

DEPARTMENT OF TRANSFORMATION AND SHARED SERVICES

OFFICE OF STATE PROCUREMENT

501 Woodlane St., Ste. 220 Little Rock, Arkansas 72201-1023

INVITATION FOR BID

SOLICITATION DOCUMENT

SOLICITATION INFORMATION

Solicitation Number: S000000030 Solicitation Issued: July 14, 2021

Description: Crop Hauling Services-East Arkansas

Department: Arkansas Division of Correction

SUBMISSION DEADLINE AND DELIVERY OF RESPONSE DOCUMENTS

Bid Opening Date: August 11, 2021 Bid Opening Time: 2:00 p.m., Central Time

Bid responses for this Invitation for Bid must be submitted through ARBuy, the State’s eProcurement system.

It can be accessed at https://arbuy.arkansas.gov. Bids received after the submission deadline may be rejected as untimely. See section 1.2 for information regarding Live Bid Openings.

TSS OFFICE OF STATE PROCUREMENT CONTACT INFORMATION

TSS OSP Buyer: Jennifer Trancoso Buyer’s Direct Phone Number: 501-371-6070

Email Address: Jennifer.trancoso@arkansas.gov TSS OSP’s Main Number: 501-324-9316

TSS OSP

Website: https://www.transform.ar.gov/procurement/ https://arbuy.arkansas.gov/ mailto:Jennifer.trancoso@arkansas.gov

SECTION 1 – REQUIREMENTS

• Do not provide responses to items in this section unless specifically and expressly required.

1.1 INTRODUCTION

This Invitation for Bid (IFB) is issued by the TSS Office of State Procurement (TSS OSP) for the Arkansas Department of Corrections (ADC) to obtain pricing and a contract for crop hauling services at ADC’s East Arkansas Regional Unit - Farm Operation. Direct all questions, comments, or concerns you may have regarding this solicitation to the TSS Office of State Procurement, not the Arkansas Department of Corrections (ADC).

1.2 LIVE BID OPENING

See instructions below to view the bid opening online.

Zoom Meeting Link:

https://arkansas-gov.zoom.us/j/84366902186?pwd=Zm1yOCtCVlROQWxqZm1iYVBjVVlQQT09 Meeting ID: 843 6690 2186 Meeting Password: 679699 Dial-In Information: 833 548 0276 US Toll-free 833 548 0282 US Toll-free

1.3 CLARIFICATION OF SOLICITATION

A. Submit any questions requesting clarification of information contained in this Solicitation via the solicitation posting in ARBuy by midnight, Central Time on or before July 26, 2021.

1. For each question submitted, Prospective Contractor should reference the specific solicitation item number to which the question refers.

2. Prospective Contractors’ written questions will be consolidated and answered by the State as deemed appropriate. The State’s consolidated written response is anticipated to be posted to the solicitation posting in ARBuy by the close of business on July 30, 2021. If Prospective Contractor questions are unclear or non-substantive in nature, the State may request clarification of a question(s) or decline to answer.

B. The Prospective Contractor should notify the TSS OSP buyer of any term, condition, etc., that precludes the Prospective Contractor from submitting a compliant, Responsive Bid. Prospective Contractors should note that it is the responsibility of the Prospective Contractor to seek resolution of all such issues, including those relating to the terms and conditions of the contract, prior to the submission of a bid.

C. Prospective Contractors may contact the TSS OSP buyer with non-substantive questions at any time prior to the bid opening.

D. An oral statement by TSS OSP will not be part of any contract resulting from this solicitation and may not reasonably be relied on by any Prospective Contractor as an aid to interpretation unless it is reduced to writing and expressly adopted by TSS OSP.

1.4 DEFINITION OF TERMS

A. Unless otherwise defined herein, all terms defined in Arkansas Procurement Law have the same meaning herein.

B. “Prospective Contractor” means a responsible bidder who submits a Responsive Bid in response to this solicitation.

C. The terms “Invitation For Bid”, “IFB” and “Solicitation” are used synonymously in this document.

https://arkansas-gov.zoom.us/j/84366902186?pwd=Zm1yOCtCVlROQWxqZm1iYVBjVVlQQT09

D. “Responsive Bid” means a bid submitted in response to this solicitation that conforms in all material respects to this IFB.

E. “Shall” and “Must” mean the imperative and are used to identify requirements.

F. “Requirement” means something required.

G. “Specification” means any technical or purchase description or other description of the physical or functional characteristics, or of the nature, of a commodity or service. “Specification” may include a description of any requirement for inspecting, testing, or preparing a commodity or service for delivery.

H. “State” means the State of Arkansas. When the term “State” is used herein to reference any obligation of the State under a contract that results from this solicitation, that obligation is limited to the Department using such a contract.

I. “Business Day” means a day occurring Monday through Friday, excluding State Holidays. A current listing of State Holidays can be found on the Arkansas Secretary of State’s website at https://www.sos.arkansas.gov/news/state-holiday-calendar/.

J. “Contractor” means a person who sells or contracts to sell commodities and/or services.

K. “Department” means the Arkansas Division of Corrections.

L. “Gross Weight” means the weight of the truck when fully loaded with crops as determined by the ADC scales.

M. “Scale Ticket” means a ticket that shows information about the load at time of pick up, such as date, time, commodity, destination, Tare Weight, Gross Weight, and Net Weight.

N. “Buyer’s Ticket” means a ticket that shows information about the load at time of delivery, such as date, time, commodity, Tare Weight, Gross Weight, and Net Weight and Buyer Information.

O. “Tare Weight” means the combination weight of an empty truck and an empty trailer prior to loading crops as determined by the ADC scales.

P. “Net Weight” means the weight of the crops being hauled, excluding the weight of the truck.

1.5 BACKGROUND INFORMATION

A. East Arkansas Regional Unit is located approximately seventeen (17) miles southeast of Forrest City in Lee County, Arkansas.

B. Peak season for crop hauling services is August through October.

C. Historically, corn is harvested August through September, soybeans are harvested August through

November, and wheat is harvested in June.

D. All quantities of commodities to be hauled are estimates based on approximate annual crop yields and not guaranteed. Department needs may vary; ADC reserves the right to increase or decrease the quantities on an as needed basis.

E. Issuance of an award does not guarantee an order.

1.6 PROSPECTIVE CONTRACTOR QUALIFICATIONS

A. At the time of bid submission, the Prospective Contractor shall have an adequate number of vehicles, drivers, and other necessary equipment and supplies currently available to provide the services specified in this IFB.

B. Prospective Contractor’s drivers shall possess a Commercial Driver License (CDL).

C. Prospective Contractor shall have and maintain a minimum of $1,000,000.00 liability coverage on Contractor’s vehicles, equipment, and crops in transit throughout the term of a resulting contract, including all renewal periods.

1. Prior to award, the Prospective Contractor shall submit certificates of insurance as proof of required insurance and each year prior to each renewal.

1.7 SITE LOCATION OF CROPS

A. Crop hauling from the East Arkansas Regional Unit will be out of the fields and drivers may experience long wait times to get loaded. Drivers shall plan in a manner that does not delay pick-up and delivery of crops.

B. East Arkansas Regional Unit has no set hours of operations. Contractor shall be available to provide

East Arkansas Regional Unit with crop hauling services on time as requested, seven (7) days per week, 365-days per year, holidays as needed.

C. Crops are grown and hauled from:

Arkansas Division of Correction East Arkansas Regional Unit 326 Lee Road 603 #601 Brickeys, AR 72320

1.8 GENERAL REQUIREMENTS

A. Prior to entering ADC property, the Contractor shall provide a list of trucks and/or trailers, identified by license plate number, to the East Arkansas Regional Unit manager or designee.

1. Contractor shall notify ADC of changes in trucks, trailers, and/or license plate numbers as soon as reasonably possible, but not more than fourteen (14) calendar days after the change occurs.

B. Contractor shall allow ADC to search all vehicles entering ADC property at any time for illegal or smuggled freight. If illegal or smuggled freight is found, ADC will notify the appropriate authorities and the driver will be subject to charges being filed against them.

C. Contractor shall adhere to ADC guidelines and procedures.

1.9 TRUCK AND TRAILER REQUIREMENTS

A. Within three (3) hours of request from ADC, the Contractor shall provide four (4) dump trucks and/or hopper bottom trailers for hauling crops, as specified from ADC at the time of request.

1. If the Prospective Contractor cannot supply the trucks and/or trailers and drivers within the requested three (3) hour time frame, ADC will hire other trucks to haul the crops. The Contractor shall reimburse ADC for all cost incurred that exceeds the contracted price.

2. Trucks and/or trailers must have an 11-foot maximum clearance that will allow loading by grain carts.

B. When requested by the East Arkansas Regional Unit farm manger or designee and depending on the volume of crops to be hauled, the Contractor shall supply additional trucks and drivers within three

(3) hours of notification from the Department.

1.10 DRIVER REQUIREMENTS

A. Drivers shall present their CDL license to the ADC guard located in the guard shack before proceeding onto ADC property.

B. Since all ADC facilities are tobacco free, drivers shall lock all tobacco products inside the driver’s vehicle.

C. Drivers shall keep their cell phone(s) secured in their possession at all times.

D. Drivers shall remove key from the ignition, lock the vehicle, and keep keys in their possession when vehicles are left unattended.

1.11 LOADING, WEIGHING, AND HAULING REQUIREMENTS

A. Prior to the truck and/or trailer being loaded with crops, the driver shall have the empty truck and/or trailer weighed on the ADC scales to establish a Tare Weight.

B. After the Tare Weight is established, the ADC scale operator will enter the Tare Weight on a Scale

Ticket showing the weight of the empty truck. The driver shall proceed to the fields to load the trucks and/or trailer with crops.

C. After loading the crops into the truck and/or trailer, the driver shall proceed back to the ADC scales to obtain the Gross Weight. Note: ADC will allow drivers a onetime drive through to the weigh station for each load.

1. Drivers shall not add to or subtract from the current load once they reach the ADC scales.

D. After obtaining the Gross Weight, the ADC scale operator will complete the Scale and Buyer’s Tickets.

E. The ADC scale operator and driver must sign and date the Scale and Buyer’s Ticket. Copies of the

Scale and Buyer’s Ticket will be given to the driver.

F. The driver shall deliver the crops to the buyer at the destination specified on the Buyer’s Ticket.

1. The Scale and Buyer’s Ticket must be signed and dated by the buyer and the tickets given back to the driver.

G. After completion of crop delivery, the driver shall return the signed copy of the Scale Ticket and the

Buyer’s Ticket to the East Arkansas Unit Farm Office within five (5) Business Days for reimbursement.

H. Drivers shall adhere to the legal weight limits of each load and shall pay all penalties incurred for overloading.

1.12 DELIVERY

A. Contractor shall deliver crops to various locations throughout the State of Arkansas as required by the East Arkansas Regional Unit at the time services are provided.

B. Contractor shall not invoice any additional delivery fees to a third-party buyer when providing crop hauling services under any resultant contract.

1.13 PERFORMANCE STANDARDS

A. State law requires that contracts for services include Performance Standards for measuring the overall quality of services that a Contractor shall provide.

B. The State may be open to negotiations of Performance Standards prior to contract award, prior to the commencement of services, or at times throughout the contract duration. Performance Standards identifies expected deliverables, performance measures, or outcomes; and defines the acceptable standards.

C. Performance Standards shall not be amended unless they are agreed to in writing and signed by the parties.

D. Failure to meet the minimum Performance Standards as specified will result in the assessment of damages.

E. In the event a Performance Standard is not met, the Contractor will have the opportunity to defend or respond to the insufficiency. The State has the right to waive damages if it determines there were extenuating factors beyond the control of the Contractor that hindered the performance of services.

In these instances, the State has final determination of the performance acceptability.

F. Should any compensation be owed to the Department due to the assessment of damages, Contractor shall follow the direction of the Department regarding the required compensation process.

Criteria Standard Damages Response Time. Within three (3) hours of request from ADC with the required number of trucks and drivers.

$100 credit on next invoice generated for each instance during the month whereby the Contractor fails to provide trucks and drivers within three (3) hours of request from ADC.

Contractor shall reimburse ADC for all associated cost incurred by ADC that exceeds the contract price to hire another company to haul crops.

Signed and dated Scale and Buyer’s Tickets returned.

Within five (5) Business Days of crop delivery.

10% reduction to the Contractor’s invoice for each instance where the Contractor’s driver does not meet the five (5) Business Days delivery Requirement.

SECTION 2 – GENERAL INSTRUCTIONS AND INFORMATION

• Do not provide responses to items in this section unless specifically and expressly required.

2.1 TYPE OF CONTRACT

A. As a result of this IFB, TSS OSP intends to award a contract to a single Contractor.

B. The anticipated starting date for any resulting contract is September 1, 2021, except that the actual contract start date may be adjusted unilaterally by the State for up to three (3) calendar months. By submitting a signed bid in response to the IFB, the Prospective Contractor represents and warrants that it will honor its bid as being held open as irrevocable for this period.

C. The initial term of a resulting contract will be for one (1) year. Upon mutual agreement by the

Contractor and Department, the contract may be renewed by TSS OSP for up to six (6) additional one-year terms or portions thereof, not to exceed a total aggregate contract term of seven (7) consecutive years.

2.2 CONTRACTOR SELECTION

A. Award will be made to the lowest-bidding, responsible Prospective Contractor on an all or none basis.

2.3 RESPONSE DOCUMENTS

A. All bid responses must be submitted through ARBuy, the State’s eProcurement system. The system can be accessed at https://arbuy.arkansas.gov.

B. Bid Response Packet

1. The following are bid submission requirements and must be submitted as part of a Prospective

Contractor’s bid response.

a. Signed Bid Signature Page. Signature may be ink or digital. (See Bid Response Packet.)

b. Completed Bid Response Packet, which must be in the English language.

c. Completed Pricing Response. Pricing must be proposed in U.S. dollars and cents.

d. Proposed Subcontractors Form. The utilization of any proposed subcontractor is subject to approval by the Department.

e. Exceptions Form.

2. The following items, which must be submitted prior to a contract award to the Prospective Contractor, may also be included with the Prospective Contractor’s bid response:

a. EO 98-04 Contract & Grant Disclosure Form.

b. Copy of Prospective Contractor’s Equal Opportunity Policy.

c. Voluntary Product Accessibility Template (VPAT), if applicable.

3. DO NOT include any other documents or ancillary information, such as a cover letter or promotional/marketing information.

https://arbuy.arkansas.gov/

2.4 ACCEPTANCE OF REQUIREMENTS

A. Unless a Prospective Contractor expressly and conspicuously identifies any exception or exceptions to any of the Requirements in the Requirements Section(s) of this IFB by listing them on the Exceptions Form (See Bid Response Packet), Prospective Contractor understands and agrees its submission of a bid to represent that its bid meets all such Requirements.

B. A Prospective Contractor’s bid may be rejected if the Prospective Contractor takes exception to any Requirements in the Requirements Section(s) of this IFB.

2.5 ADDITIONAL TERMS AND CONDITIONS

A. This IFB incorporates all of the Solicitation Terms and Conditions located on the TSS OSP website here (Agencies – Forms and Reporting – Solicitation Templates):

https://www.transform.ar.gov/procurement/agencies/forms-and-reporting/.

B. Any special terms and conditions included in this solicitation shall override the Solicitation Terms and Conditions.

C. Unless a Prospective Contractor expressly and conspicuously identifies any exception or exceptions to any of the terms in the Services Contract (SRV-1) Fillable Form by listing them on the Exceptions Form (See Bid Response Packet), Prospective Contractor agrees and shall adhere to all terms if selected as the successful Contractor. Items identified as non-negotiable may only be modified if the legal requirement is satisfied and approved by the State. The Services Contract (SRV-1) Fillable Form can be viewed on the TSS OSP website here (Agencies – Services – Forms):

https://www.transform.ar.gov/procurement/agencies/services/.

D. A Prospective Contractor’s bid may be rejected if a Prospective Contractor takes exception to any terms or conditions in the documents listed in 2.5.A and 2.5.C.

https://www.transform.ar.gov/procurement/agencies/forms-and-reporting/ https://www.transform.ar.gov/procurement/agencies/services/

SECTION 2 – GENERAL INSTRUCTIONS AND INFORMATION

File details come from the government source that posted it. Updated .