USCG YARD BUILDING 5 ENGINE SHOP PAINT BOOTH
PERFORMANCE WORK STATEMENT (PWS)
Paint Booth Installation
1. GENERALSCOPE.: Supply and install This is a non-personal services contract for the installation and set-up of a large equipmenta paint booth and associated equipment in the Building 5 Engine Shop at the U.S. Coast Guard Yard, 2401 Hawkins Point Road, Curtis Bay, Baltimore, MD, 21226 for the purposes of painting and forced-air heated drying of marine diesel engines. Installation services will include start-up and balancing of the paint booth system. One-time training shall be provided to Government employees regarding operation and maintenance of the system..
Performance shall take place inside and around the vicinity of Building 5. The Government shall not exercise any supervision or control over Contractor employees performing the services herein. The Contractor’s employees shall be accountable solely to the Contractor, who is in turn responsible to the Government.
2. REQUIREMENTS.
3.
4. Description of Services/Introduction: The Contractor shall provide all personnellabor, equipment, tools, materials, disposals, and supervision to meet the below requirements. , and other items necessary to install, set up, and test the large equipment paint booth as defined in this PWS, except for those items specified as Government-Furnished Property and Services (GFP/GFS). The Contractor shall perform to the standards in this contract; ifWhere no standards are specified, the Contractor shall meet a commercially reasonable standard.
4.1. Background: It is anticipated that the U.S. Coast Guard Yard will require a large equipment paint booth installed in Building 5, for the purposes of painting and forced-air heated drying marine diesel engines.
4.2. Objectives: The Contractor shall be required to design, procure, install, and test a Large Cross-Draft Pressurized Paint Booth in Building 5 at the Coast Guard Yard, Baltimore, MD 21226. Coast Guard representatives will provide final acceptance upon witnessing that all PWS requirements are met.Paint Booth.
4.2.1. Enclosure Dimensions:. Tthe minimum clearance for workinternal dimensions inside the installed equipment paint booth sshall be 16’- 0” wide ×x 21’0” long × 1218’- 06” high x 24’ 0” long. The maximum external dimensions of the enclosure of the paint booth shall not exceed 18’-0” wide × 28’0” long × 17’-0” high. The Contractor is responsible for ensuring externally mounted fixtures do not interfere with existing building structure and equipment. the building’s structural limits. Comment by Dayneko, Sergey LTJG USCG YARD (USA): Engine Cart Dims: 8’ x 8’ 6” x 13’ (+4’ for minimum worker clearance on all sides) Comment by Dayneko, Sergey LTJG USCG YARD (USA): Engine Cart Dims: 8’ x 8’ 6” x 13’ (+4’ for minimum worker clearance on all sides) 4.2.2.
4.2.3. Door Dimensions. The door clearance shall be a minimum of 9’-0” wide × 10’-0” high and positioned at the free end of the enclosure. Comment by Dayneko, Sergey LTJG USCG YARD (USA): Engine Cart is 8’ x 8’6” (+1’ for clearance)
4.2.4. Air Flow/ and Ventilation.: Forced air shall be provided in thethe equipment paint booth shall enclosure with produce a cross-draft style of airflow with at an minimum approximate air velocity of 100 feet per minute.
4.2.4.1. The Contractor shall provide, as part of the bid proposal, requirements for Government-Furnished equipment, utilities, and foundations; including, but not limited to requirements for routing exhaust and makeup ventilation ducting, including the ventilation path, foundation material, foundation dimensions, and weight of the external structure, if included in the approved design.
4.2.4.1.1. If any holes are required to be cut in the side of Building 5 for routing ventilation, hole dimensions and locations shall also be provided in the bid proposal.
4.2.4.2.
4.2.5. Heating.: the equipment paint booth The internal ambient temperature shall be able to reach sustain a minimum of 80°F using natural gas heating utilities..
4.2.6. Power and Lighting.: the equipment paint booth interior shall produce sufficientInternal explosion-proof lighting lighting, no less than shall be provided at a minimum of 50 20 Foot Candles throughout the enclosure., to illuminate all work surfaces during routine painting and paint inspection operations. Comment by Dayneko, Sergey LTJG USCG YARD (USA): 20 FC is authorized w/ 50 FC inspection lights (hand held)
4.2.6.1. The Contractor shall provide an electrical feed panel to power the equipment paint booth’s electrical system. The power available in Building 5 is 480 V, 60 Hz.
4.2.6.2. The Contractor shall provide at least one explosion-proof NEMA 5-15 120VAC outlet on each interior wall of the enclosure, excepting the side with the door.
4.2.7. Site Survey: prior to contract award, a site survey by prospective Contractors shall be required.
4.2.8. Engineering: all Contractor-provided drawings and plans are to be approved and stamped by a structural/civil engineer licensed by the state of Maryland.
4.2.9. Compressed Air: a manifold will shall be installed by the Contractor to provide compressed air for paint application and breathing air.
4.2.9.1. The working pressure of Building 5 is 125 psi. The manifold shall have a minimum of 4 connections.
4.2.10. (Optional) Fire Protection System (FPS): the paint booth may shall have an integrated fire suppression system FPS installed for emergencies. The FPS shall meet National Fire Protection Association requirements. This is as an optional work item to be exercised at the discretion of the Government.
4.2.11.
4.3. Bid Proposal: Scope of Work:
4.3.1. The Contractor’s Bid Proposal shall consist of two parts:
4.3.1.1. The Preliminary Bid Proposal shall include:
4.3.1.2. Mandatory Site Survey
4.3.1.3. Project Plan/Schedule
4.3.1.4. Conceptual Drawings, including equipment booth dimensions and physical location.
4.3.1.5. Utilities Requirements: Natural Gas, Electrical Power, Compressed Air, etc.
4.3.1.6. The Final Bid Proposal shall include:
4.3.1.7. Original Equipment Manufacturer’s parts requirementstechnical information and technical publications.
4.3.1.8. Startup/Balancing Services
4.3.1.9. Training
4.3.1.10. Maintenance Requirements and Training in usage and maintenance of installed equipment.
4.3.1.11. Spare Parts in sufficient quantities to perform manufacturer’s recommended maintenance, at least 1 year’s worth.
4.3.2. The Contractor shall provide all labor, material, equipment, supervision, and certifications prior to commencement of work.
4.3.3. The Contractor shall provide, as part of the preliminary bid proposal, requirements for Government-Furnished equipment, utilities, and foundation (size and weight)s; including, but not limited to:
4.3.3.1. Requirements for routing exhaust ventilation ducting outside the building, including the ventilation path, foundation material, foundation dimensions, and weight of the external structure, if included in the approved design.
4.3.3.1.1. In addition, if any holes need to be cut in the side of Building 5 for routing ventilation, hole dimensions and locations shall also be provided in the bid proposal.
4.3.3.2. Requirements for utility termination locations, including: electrical power (including voltage, current, and frequency), natural gas (including pressure), and compressed air (including pressure).
4.3.4. Upon completion of work, the Contractor shall provide start-up and balancing services and training to Government employees regarding operation, upkeep, and maintenance of the booth
4.3.5. The Contractor shall contact the KO or their designated representatives upon arrival on the job site and prior to departure each day.
4.3.6. Work shall be done in a safe and efficient manner and in accordance with all federal and state safety requirements.
4.3.7. Contractor Employees and/or Subcontractors assigned to contract performance shall be subject to dismissal from premises, at the request of the KO, for violation of any Coast Guard or Coast Guard Yard regulations, applicable laws, or pertinent contract provisions.
4.3.8. The Contractor must maintain a workforce sufficient to complete performance within the specified time frame agreed to by the KO and in accordance with the Coast Guard’s schedule.
4.3.9. The Contractor shall provide safety and health controls for:
4.3.9.1. Pprotection to the life and health of employees and other personnel;
4.3.9.2. Ffor prevention of damage to property, materials, supplies, and equipment;
4.3.9.3. Aagainst any hazardous conditions present in the performance of work.
4.3.10. The Contractor shall report to the KO or their designated representative any damage to property, materials, supplies and equipment incidental to work performed in accordance with provisions of the contract. If a hazardous situation arises during work, the Contractor shall immediately stop work and report the incident to the KO or their designated representative. In the event that the Contractor fails to promptly report any such situation and/or fails to immediately commence and promptly clean up completely, the Government reserves the rights delineated in the Federal Acquisitions Regulations (FAR) Clause 52.212-4 Contract Terms and Conditions.
4.3.11. Whenever the Contractor encounters any difficulty which is delaying, or threatens to delay, the timely performance of the contract, the Contractor shall immediately give verbal notice thereof to the KO or their designated representative confirmed in writing, including all relevant information with respect thereto. Such notice shall not in any way constitute an extension of the performance time or be construed as a waiver by the Government of any rights or remedies to which it is entitled by law or pursuant to the terms of this contract. Failure to give such notice, however, may be grounds for denial of any claim for additional costs because of such delay. Extensions may be granted on an individual basis only by the KO.
4.3.12. The Contractor shall at all times keep the work area and passageways around the work areas free from any accumulation of waste materials, rubbish, or oil and water, and upon completion of work, remove from the premises all material and equipment not the property of the Government. The Contractor is to leave the work area and premises in a clean, neat, and workmanlike manner that is satisfactory to the KO or their designated representative. If a clean-up of any spill or dirt is not immediately made, the Government may exercise the rights stated in the FAR 52.212-4 Contract Terms and Conditions.
4.3.13. The Contractor shall be given notice to proceed, not less than 48 hours, but as early as possible, prior to the requested starting time and date by the KO, allowing the KO sufficient time to plan a work schedule.
4.3.14. The Contractor shall properly remove and dispose of all materials in compliance with applicable federal, state, and local environmental laws and regulations. The Contractor assumes all responsibility and liability for the transport and proper disposal of materials and in particular the following requirements:
4.3.14.1. If a spill occurs, the contractor must report the spill to the USCG Yard Main Gate (410-636-3993) or land-line Yard extension X-3000 IMMEDIATELY and submit a letter describing the incident within 24 hours after the spill. During a spill, the contractor may receive direction from Yard Firehouse/Environmental.
4.3.14.2. The Contractor MUST follow the USCG Yard Facilities Response Plan, when operating on USCG Yard property.
4.3.14.3. Ordering data to be furnished to the Contractor upon placing the delivery
4.3.14.4. Order: Date and Time service is required for NLT (no later than) start and completion.
4.3.14.5. Yard Environmental Management System: the contractor will may be audited by a member(s) of the Yard Environmental Branch once a yearat CG Yard’s discretion. The audit will verify the qualifications of the Contractor to perform the work according to state and federal regulations, Yard Emergency Response Procedures, and contact information.
4.4. General Information
4.4.1. Quality Assurance: The Government shall evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
4.4.1.1. Quality Control: The Contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Quality Control Plan shall include, at a minimum, the following:
4.4.1.1.1. The quality control organizational structure.
4.4.1.1.2. A quality control inspection system covering all tasks included in the contract scope of work. It shall specify tasks or areas to be inspected, on either a scheduled or unscheduled basis, or the manner in which inspections are to be conducted.
4.4.1.1.3. A description of the methods of identifying deficiencies in the quality of services performed before the level of performance becomes unacceptable.
4.4.1.1.4. A description of the methods of documenting and enforcing quality control operations of Contractor, and any Subcontractor, work, including inspection and testing.
4.4.1.2. Quality Control Reports: The Contractor shall submit a copy of the daily Quality Control Reports to the COR at end of each working day. The Quality Control Reports shall contain, at a minimum, information on the following:
4.4.1.2.1. Progress Report
4.4.1.2.2. Conditions Found
4.4.1.2.3. Concerns
4.4.1.2.4. Safety Incidents
4.4.1.2.5. Items/Areas ready for inspection (per task list)
4.4.1.2.6. Cost Expenditure Reports
4.4.2. Recognized Holidays: The Contractor may be required to work on the following federal holidays:the Coast Guard Yard recognizes the following Federal Holidays:
| New Year’s Day | Labor Day | ||
| Martin Luther King Jr’s Birthday | Columbus Day | ||
| President’s Day | Veteran’s Day | ||
| Memorial Day | Thanksgiving Day | ||
| Independence Day | Christmas Day |
4.4.3. Hours of Operation: The United States Coast Guard Yard normal working hours are from 7:00 A.M. to 3:30 P.M., Monday to Friday, except Federal Holidays or when the Government facility is closed due to local or national emergencies, inclement weather, administrative closings, or similar Government-directed facility closings.
4.4.3.1. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed.
4.4.3.2. The Contractor may be required to work outside of the normal working hours, days, and possibly, on weekends or other periods of CG Yard closure (ex: Federally Recognized Holidays). Advance notice will be given, as much as practical.
4.4.3.3. On days of inclement weather the contractor will call the U.S. Coast Guard Yard inclement weather hotline at (410) 636-7910, option #1 for that day’s status. If the U.S. Coast Guard Yard is closed the contract employees will not report for that day. If there is a delayed opening the contract employees should report at that time specified in the announcement message.
4.4.4. Place of Performance: The work to be performed under this contract will be performed at the U.S. Coast Guard Yard, 2401 Hawkins Point Road, Building 5, Curtis Bay, Baltimore, MD 21226.
4.4.5. Type of Contract: The Government will award one (1) firm-fixed-price contract as a result of this solicitation.
4.4.6. Security Requirements: The U.S. Coast Guard Yard, Baltimore, MD is a controlled access area. The Contractor shall be responsible for providing company and issued photo identification to all employees directed to perform work on the U.S. Coast Guard Yard. All Contractor employees are required to identify themselves with company identification on their hard hats and/or uniforms. Any Contractor employee not following U.S. Coast Guard rules and regulations will be removed from performance on this contract and may be barred from reentering the U.S. Coast Guard Yard. This does not absolve the Contractor in meeting contract performance requirements.
4.4.6.1. Physical Security: The Contractor shall be responsible for safeguarding all Government equipment, information, and property provided for Contractor use.
4.4.6.2. Listing of Employees: The Contractor personnel shall maintain a current listing of employees. This list will include the employee’s name and date of birth. The list shall be provided to the Contracting Officer and the COR. An updated listing shall be provided when an employee’s status or information changes.
4.4.6.3. Reporting Requirements: Contractor personnel shall report to an appropriate authority (KO, KO’s Representative (COR), or Project Manager) any information or circumstances of which they are aware may pose a threat to the security of U.S. Coast Guard personnel, Contractor personnel, resources, and classified or unclassified defense information. The Contractor shall not substitute employee(s) without prior notification to the Contracting Officer and COR. Contractor employees shall receive a full safety briefing by their immediate supervisor upon initial on-base assignment of all known hazards in areas that work shall be performed.
4.4.7. Occupational Safety and Health Standards: The Contractor is required to follow 29 CFR 1915 (OSHA Shipyard Industry Standard), while performing work at the U.S. Coast Guard Yard. The Contractor must provide all required personnel safety equipment for their employees, such as, but not limited to; safety helmet, safety glasses and shoes, appropriate respirators (disposable paper respirators are unacceptable), safety harnesses, and hearing protection. All safety equipment must meet OSHA standards. Failure of Contractor employees to comply with the above requirements could result in a shutdown of operations.
4.4.7.1. The U.S. Coast Guard Yard has 24-hour first aid, spill response and fire protection available. If necessary, the Contractor may call 410-636-3993 from non-Yard phones and extension 3000 from Yard phones for emergency situations. The U.S. Coast Guard Yard will provide emergency first aid only. Injuries must be reported immediately and followed up with a written report to the COR.
4.4.8. COVID-19: The Contractor shall follow all federal, state, local, or US Coast Guard regulations regarding the ongoing COVID-19 pandemic.
4.4.9. Special Qualifications: The Contractor shall comply with all the U.S. Coast Guard Yard ISO 9001 Quality Management and ISO 14001 Environmental Management Systems certifications. The Contractor may be periodically audited to ensure conformity to these certifications and standards.
4.4.9.1. ISO Certifications: The Coast Guard Yard is an ISO 14001 certified industrial facility. Maintaining this environmental certification is of paramount importance to the Yard. The Contractor may be audited at CG Yard’s discretion tone or more times a year to ensure their compliance. The Contractor, therefore, will be held strictly accountable for violations of the ISO 14001 Standards and Environmental Law and/or Regulation. The Contractor will receive a Yard Environmental Corrective Action Request for any spills/releases of contaminated waters or oils. Any fines levied against the Government by the Maryland Department of the Environment, Environmental Protection Agency, or other regulatory body will be charged to the Contractor if the Contractor is found to be at fault.
4.4.10. Post Award Conference/Periodic Progress Meetings: The Contractor will agree to attend any post-award conferences convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart (FAR) 42.5. The KO, COR, and other Government personnel, as appropriate, may meet periodically with the contractor to review the Contractor's performance and schedule. At these meetings, the Contracting Officer will appraise the Contractor of how the Government views the contractor's performance and the contractor will apprise the Government of problems, if any, are being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
4.4.10.1. Kick-Off Meeting: The Kick-Off meeting shall be held at a time and place as designated by the KO/COR, prior to commencement of work.
4.4.10.1.1. Check-Off Sheets: Before any work commences, the Contractor shall meet with the KO/COR to perform a walk through to establish an interference check-off sheet as well as a specific services (tasks) check-off sheet. In addition, the Contractor shall provide a daily progress report to the COR. Both of these check-off sheets and the daily progress report shall be used by the COR during daily inspection of work daily and upon work completion.
4.4.10.1.2. Performance Schedule: Within No later than 24 hours of prior to the kick-off meeting, the Contractor shall provide the Government with a schedule of work to be performed.
4.4.10.2. Daily Progress Report: The Contractor shall provide a daily progress report to the COR
4.4.10.3. Progress Meetings: The KO, COR, and other Government personnel, as appropriate, may meet periodically with the contractor to review the Contractor's performance and schedule. At these meetings, the Contracting Officer will appraise the Contractor of how the Government views the contractor's performance and the contractor will apprise the Government of problems, if any, are being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings will be held at a time and place designated by the KO/COR. Both check-off sheets listed in section 2.2.10.1.1 and daily progress reports listed in section 2.2.10.2 may be used at this meeting.
4.4.11. Contracting Officer’s Representative (COR): The COR will be identified by separate letter. The COR will monitor all technical aspects of the contract and assist in contract administration. The COR is authorized to perform only those functions designated in the letter, issued by the KO. A letter of designation, issued to the COR (a copy of which will be sent to the Contractor), states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in performance dates. The COR is not authorized to change any of the terms and/or conditions of the contract. All contract changes that impact price or cost, quality of work, and the performance schedule may only be approved or made by the KO.
4.4.12. Key Personnel: The Contractor shall provide a Supervisor/Alternate Supervisor who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the Contractor shall be designated in writing to the Contracting Officer. The Supervisor/Alternate Supervisor shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The Supervisor/Alternate Supervisor shall be available between 7:00 a.m. to 4:30 p.m., Monday to Friday except Federal Holidays or when the Government facility is closed for administrative reasons.
4.4.13. Coordination with COR: The Contractor shall coordinate all work requirements, stated herein, with the Contracting Officer and the COR. There may be occasions in which the U.S. Coast Guard Yard will request the Contractor to cease work or move to a different location due to U.S. Coast Guard Yard production requirements.
4.4.14. Interferences: Work sites may contain items such as scaffolding, hoses, debris, and other interferences from U.S. Coast Guard Yard work operations. The Government shall attempt to remove and/or minimize such interferences to the extent practical. In the event such interferences are not removed, however, the Contractor shall notify the COR immediately to mitigate the situation. The presence of interferences and the COR’s inability to totally mitigate the impact on performance will not relieve the Contractor of responsibility for performance of services required.
4.4.15. Damage to Government Property: The Contractor shall be held liable for any damage to Government Property caused by the Contractor. The Contractor shall provide protective coverings on all vulnerable equipment and surfaces. It shall be the responsibility of the Contractor to ensure that the coverings are adequate. Any concerns as to the adequacy of the coverings must be brought to the attention of the COR. The Contractor shall inspect the area before work commences and may request a technical inspection from the COR, however such an inspection does not relieve the Contractor from responsibility for damage.
PART 2
DEFINITIONS AND ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1. CONTRACT DEFINITIONS:
2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the Contracting Officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4. KEY PERSONNEL. Contractor personnel whose qualifications are evaluated in the source selection process and whose services the Government that can required as part of the performance of the contract in accordance with the Key Personnel provisions in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal. Substitution of all Key Personnel requires approval by the Contracting Officer.
2.1.5. QUALITY ASSURANCE. The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.6. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.7. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract and commercial quality requirements.
2.1.8. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
PART 3
GOVERNMENT FURNISHED ITEMS AND SERVICES
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
3.1. Services: Provide material handling services to load and unload Contractor machinery and set up of equipment. The U.S. Coast Guard Yard shall endeavor to provide timely assistance as requested by the Contractor. The Contractor shall provide 48 hours notice to the Government when there is a need for material handling services.
3.21. Utilities: Provide water, compressed air, natural gas, and electricity for the Contractor as defined herein. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating in such a manner that precludes the waste of utilities, for example: turning off the water faucets or valves after using the required amount to accomplish assigned work.
3.21.1. Water: Provide a source of water for Contractor machinery. The Contractor shall be responsible for ensuring that their water hookup connections are compatible with the Yard’s water sources.
3.21.2 Compressed Air: Provide a source of compressed air for Contractor machinery. The Contractor shall be responsible for ensuring that their compressed air hookup connections are compatible with the Yard’s compressed air sources. The Contractor shall be responsible to hook up the new equipment to the existing Yard infrastructure and determine compressed air line termination points. The Yard provides 125 psi of compressed air in Building 5.
3.21.3. Electricity: Provide up to 200 Amps and up to 480 Volts at 60 Hertz of electrical servicespower. The Contractor shall be responsible to hook up the new equipment/electrical panel to the existing Yard infrastructure.
3.21.4. Natural Gas: Provide a Natural Gas utility line for ventilation heaters in the equipment booth. The Contractor shall be responsible to hook up the new equipment to the existing Yard infrastructure and determine natural gas line termination points.
3.2.5. Exterior Foundations: if incorporated in the Contractor’s design, the Yard will provide concrete foundations outside Building 5 as directed by the Contractor for exhaust ventilation or other purposes. A minimum of 14 days’ notice must be provided by the Contractor if concrete foundations are requested by the same.
3.2.6. Ventilation Ducting: if incorporated in the Contractor’s design, the Yard will provide a penetration to the outside of Building 5 as directed by the Contractor for exhaust ventilation or other purposes. A minimum of 14 days’ notice must be provided by the Contractor if a hole to route ventilation ducting is requested by the same.
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS, SERVICES AND RESPONSIBILITIES:
4.1 General: The Contractor shall furnish all equipment and services required to perform work under this contract other than those explicitly addressed in Section 3 of this PWS. The Contractor shall report to the designated work site within 48 hours after notification by the KO. No other individual has the authority to direct the Contractor to begin work other than a warranted KO. Pending Coast Guard Yard production schedules, services may be required on an intermittent basis within the period and quantity specified.
4.2. Services: The Contractor – or a designated sub-Contractor – shall provide material handling services to load and unload Contractor machinery and set up of equipment.
4.23. Materials: The Contractor – or a designated sub-Contractor – shall provide all plans, equipment, hardware, supports, testing, and training as required for the performance of the contract, with the exception of Section 3 in this PWS.
4.34. Equipment: The Contractor – or a designated sub-Contractor – shall, throughout the performance of this contract, be in possession of fully functioning equipment and tools to complete assigned work. The equipment may be owned or leased by the Contractor/sub-Contractor and the demonstrated ability to own or lease the equipment must be indicated in the contract proposal.
4.3.1 The equipment may be owned or leased by the Contractor and the demonstrated ability to own or lease the equipment must be indicated in the contract proposal.
4.3 5 Hazardous Materials and Waste: If it comes to the Contractor’s attention that the materials requiring removal are suspected hazardous material and would produce hazardous waste (Code of Maryland Regulations, Title 26, Subtitle 13 and 40 CFR 260-267), the Contractor must cease work immediately and notify the COR. If the surface coating being removed contains lead, cadmium, chromium or Polychlorinated Biphenyl or PCB’s, the Contractor will notify the COR immediately. The Government will have the responsibility to dispose of any hazardous materials and waste. The Contractor will have the responsibility to provide its full cooperation with the removal and disposal process.
4.35.1 Disposal and Measurement: The Contractor will provide a ticket showing the quantity of waste removed to a certified commercial approved facility by the Contracting Officer. Contractor selected disposal sites must be an authorized Non-Hazardous waste disposal site.
4.35.2 Waste tickets and non-regulated waste manifests shall accompany invoices for each removal, so that payment may be processed for each service performed. Additionally, a copy of all weight tickets and invoices shall be submitted to the shop planner on the next business day after disposal with the contract number and task order number for services clearly marked on the weight ticket and invoices. Disposal of the waste shall meet all local, state, and federal standards and regulations, and is to be substantiated by the submittal of a non-regulated waste manifest to the Contracting Officer or the Contract Administrator and additional copy shall be furnished to the authorized caller.
PART 5
APPLICABLE PUBLICATIONS
5. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
5.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures included cited in this PWS, including:
· 29 CFR 1915 Occupational Safety and Health Standards for Shipyard Employment
· Coast Guard Yard Quality Manual, Management Operating Procedure 088
· ISO 14001 Environmental Management System Manual
· Yard National Pollution Discharge Elimination System (NPDES) Permit
· Yard Title V Operating Air Permit
· Yard Wastewater Discharge Permit
· Yard Oil Operations Permit
· All applicable Federal, State and Local Laws and Regulations
· Society for Protective Coatings Technology Guide No. 12
· The Contractor shall follow the USCG Yard Facilities Response Plan when operating on USCG Yard property.
Revision Date: 9/29/2021