S-6-26_SCOPE_OF_WORK.pdf
PDF 184 KB Posted
- Solicitation number
- S-6-26
- Issued by
- Niobrara County, Wyoming
About this file
The document is a Scope of Work for Bid S-6-26 by the City of Cheyenne involving hazardous material abatement at the High Plains Arboretum, specifically targeting the Greenhouse, Lath House, and Head House. The project requires the removal of asbestos-containing materials and lead-based/lead-containing paint from historic structures, including demolition of existing components such as wood framing, glazing, steel frames, piping, electrical fixtures, and soil contamination. The abatement work is scheduled in two phases: Greenhouse Hazardous Material Abatement from 4/15/2026 to 5/15/2026, and Lath House Hazardous Material Abatement from 5/15/2026 to 6/15/2026. The Head House portion has been awarded separately and is included for coordination purposes.
The scope of work details specific removal requirements for each structure, including salvaging certain components for potential reuse by a general contractor. The project emphasizes careful deconstruction, with instructions to temporarily secure existing structures, remove paint and contaminated materials, and prepare surfaces for future renovation. The abatement contractor will work in close coordination with the general contractor completing work under a separate City of Cheyenne bid for the High Plains Arboretum renovation. While no specific budget or funding sources are mentioned in the document, the detailed scope suggests a comprehensive approach to preparing the historic structures for future restoration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Cheyenne / Bid S-6-26 / Scope of Work
HIGH PLAINS ARBORETUM –GREENHOUSE AND LATH HOUSE DEMOLITION
AND ABATEMENT
GENERAL SCOPE OF WORK
GREENHOUSE
1. GENERAL SCOPE OF WORK
a. In general, the scope of work for the Greenhouse involves the abatement of asbestos containing materials (ACM) and removal of lead-based and lead-containing paint on existing components of the existing historic greenhouses, lean-to greenhouses, connector spaces between the Head
House and the Greenhouses and between the East and West Greenhouses, and associated cold frames.
b. Note that there are existing n tunnels that run north-south through the connector between the Head House and the Greenhouses and East
Greenhouse and the West Greenhouse as well as east-west below the slab in portions of the East Greenhouse and the West Greenhouse.
2. DEMOLITION AND ABATEMENT
a. The following existing items shall be removed and disposed of as part of scope of the demolition and abatement contract:
i. chicken wire hail protection – the galvanized steel pipe frame shall remain
1. after removing glazing and wood components, temporarily secure the frame mounts to the steel frame of the greenhouse
ii. lead-based and lead-containing paint on the steel frame, other steel components, pipes, steel cap at top of concrete walls, rack & pinion sash operating hardware, etc.
iii. wood components of the greenhouses, including the wooden glazing bars, muntins, sashes, etc. (glazing compound on glazing bars, etc.
is asbestos containing and shall be removed with the glazing bars, etc.)
iv. wood ledger, framing and plywood sheathing at the flat portion of roof at the southwest greenhouse where it butts to the west greenhouse.
1. to facilitate removal of the wood ledger, etc. as noted above, remove and salvage the short horizontal aluminum framing members and fasteners at the top of the frames and salvage for reinstallation by others
2. provide temporary bracing and support for the southwest greenhouse framing as required
v. all remaining glass and glazing
1. remove and salvage the metal glazing retainer caps for reinstallation by others
vi. overhead steel steam piping in the connector spaces between the
Head House and the Greenhouses and between the East and West
Greenhouses
vii. existing soil in the concrete planting beds, wood planting benches and cold frame area, and in an area 6 feet outside the perimeter of the greenhouses, cold frames, etc. shall be removed to the depth necessary to remove the lead contamination.
viii. wood at planting beds, wood planting benches and cold frame area.
b. remnants of glazing compound at glazing bars and in grooves at glazing bars at the southwest lean-to greenhouse.
c. wood doors, frames and trim where shown
3. Notes:
a. The demolition and abatement contractor shall remove and salvage the following items and provide them to the general contractor for reuse:
i. glazing bar caps
ii. winged retainer clips on cold frame
b. Clip angles at the steel cap at the top of the concrete foundation walls used to attach wooden sashes and end wall framing shall remain. The General
Contractor responsible for installing the new wooden sashes and end wall framing shall provide new wood screws to secure those components to the vertical leg of the clip angle. Typical.
c. The existing gas-fired radiant heaters in the east and west greenhouses will be removed by the general contractor, prior to work of the demolition and abatement contract, and salvaged for reinstallation.
d. The existing gas-fired radiant heater in the connector between the east and west greenhouses will be removed by the general contractor, prior to work of the demolition and abatement contract.
e. All electrical conduits, light fixtures, etc. in the greenhouses and associated spaces shall be removed and disposed of by the demolition and abatement contractor.
f. Sheet metal planting trays in the greenhouse shall have the lead-based and lead-containing paint removed in preparation for repainting by others.
LATH HOUSE
1. GENERAL SCOPE OF WORK
a. In general, the scope of work involves the removal of lead-based and lead-containing paint on existing components of the existing historic Lath House.
2. DEMOLITION AND ABATEMENT
a. The following existing items shall be removed and disposed of as part of scope of the demolition and abatement contract:
i. Lead-based and lead-containing paint on the steel frame, etc.
ii. Wood components including the wood lath at the walls and roof as well as associated trim, etc.
i. Existing soil in the Lath House, shall be removed to the depth necessary to remove the lead contamination, 2 inches minimum.
ii. Existing soil in an area 6 feet outside the perimeter of the Lath
House, shall be removed to the depth necessary to remove the lead contamination.
HEAD HOUSE
This portion of the project has been AWARDED SEPARATELY, and is listed for general awareness and coordination purposes only.
1. GENERAL SCOPE OF WORK
a. In general, the scope of work for the Head House involves the abatement of asbestos containing materials (ACM) and removal of lead-based and lead-containing paint on existing components of the existing historic Head
Houses and associated spaces that are affected by the proposed renovation
2. DEMOLITION AND ABATEMENT
a. The following existing items shall be removed and disposed of as part of scope of the demolition and abatement contractor:
i. wood windows and trim
ii. wood doors, frames and trim where shown
iii. floor tile and mastic in the restroom
iv. overhead door, frame and trim
v. loose paint on exterior wood trim in preparation for repainting
SCHEDULE
The Abatement Contractor will be required to work in close coordination, from the General
Contractor completing the work under City of Cheyenne Bid #S-5-26 for the High Plains
Arboretum – Headhouse, Greenhouse, and Lath House Renovation. The abatement project shall be completed in accordance with the following schedule:
GREENHOUSE HAZARDOUS MATERIAL ABATEMENT
4/15/2026 to 5/15/2026
LATH HOUSE HAZARDOUS MATERIAL ABATEMENT
5/15/2026 to 6/15/2026