This document is a Quality Assurance Checklist for the USS LEWIS B. PULLER (ESB-3) Force Generation Risk Reduction (FGRR) solicitation. It outlines the required documentation that the contractor must submit for review, including a Quality Manual, Qualified Inspector List, Access Control Plan, Measuring and Test Equipment Calibration Records, Marine Chemist Certifications, Coatings Inspector Certifications, Welding/Brazing Certifications and Procedures, and NDT/NDI Inspector Certifications.
The document also provides guidance on the required Test and Inspection Plan (TIP), including information that must be included, such as inspection symbols, government notification points, and the relationship to key events in the availability. The TIP must be maintained and updated throughout the availability. This Quality Assurance Checklist is part of the larger solicitation for the USS LEWIS B. PULLER (ESB-3) FGRR, which includes a regular overhaul-drydock (ROH-DD), lay berth and Industrial Assistance (IA), and a mid-term availability (MTA) to be performed at the contractor's facility within the 6th Fleet Area of Responsibility.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment S-2: USS LWEIS B. PULLER FGRR (ROH-DD- MTA) Forward Deployed Regional Maintenance Center Quality Assurance
Checklist Solicitation
FDRMCINST 4355.4B
Ship Name: USS LEWIS B. PULLER
(ESB-3)
SSP#: BAHR-005-25
BAHR-001-26
POP: 05/28/2025 - 07/31/2025
08/01/2026 - 09/30/2026
Checked block indicates documentation submission is required
Documents requested for review are required by FDRMC Code 300 QA to determine contractor’s ability to comply with Work Package specification requirements
Please submit all requested documents in English
Quality Manual ☒ Submit for review, a copy of the Quality Manual that describes your QMS and/or those procedures you anticipate will be used during performance of this contract. If ISO 9001 certified also attach a copy of your certificate.
Qualified Inspector List ☒ Submit a list of qualified inspectors who witness and sign inspections and tests indicated by Work Item(s) symbol (I). The list shall indicate the type(s) of inspections and tests for which each inspector is qualified.
Access Control Plan (ACP) ☒
The Contractor shall complete and submit the Foreign Access Control Plan checklist/questionnaire, signed.
Measuring and Test Equipment Calibration
Records
Submit records of calibration for all measuring and test equipment anticipated for use during execution of the contract.
MARINE CHEMIST
CERTIFICATIONS ☐ Submit copies of Marine Chemist certifications.
Coatings Inspector(s)
(NACE/NBPI/CIP)
Certification(s)
☒ Submit copies of Coatings Inspectors Certifications.
Welding Certifications, Qualification and
Procedures
Submit legible copies of Welder Certifications, Weld Procedures, and Weld Procedure Qualification Test for review and acceptance, for use during execution of this contract.
Brazing Certifications, Qualification and
Procedures
Submit legible copies of Brazer Certifications and Brazing Procedures for review and acceptance, for use during execution of this contract.
NDT/NDI Inspector Certifications and
Qualification Procedures
Submit legible copies of NDT/NDI Inspector Certifications, Qualification Program, and NDT/NDI Method Written Practice for review and acceptance, for use during execution of this contract.
x
Test and Inspection Plan/Schedule (TIP) ☒
Submit draft of Test and Inspection Plan (TIP) that provides visual display of scheduled work items in the solicitation to indicate an understanding of the solicited work items. After contract award, the TIP must include all inspections required by references as well as the symbols (I), (V), (Q) at test/inspections points and (G) when government notification is identified in each Work Item. The Contractor may insert additional tests and inspections deemed necessary to validate product conformance to specifications. See Enclosure 1 for sample Test and Inspection Plan
Attachment S-2: USS HERSHEL ‘WOODY’ WILLIAMS FY23 ROH-DD Forward Deployed Regional Maintenance Center Quality Assurance Checklist Solicitation
(MSC Ships)
FDRMCINST 4355.4B
Enclosure 1
Date
KTR FDRMC
Time
Date
KTR FDRMC
Time
Date
KTR FDRMC
Time
Date
KTR FDRMC
Time
Date
KTR FDRMC
Time
1) The initial TIP for each Work Item must be revised and submitted to the SUPERSVISOR prior to the start of work and be updated as work proceeds.
2) Include provisions for documenting the date, time, and identification of the SUPERVISOR's representative notified and government representative attending each (G)-Point on the TIP.
3) Each test and inspection annotated on the specification must be identified by its respective Work Specification number and Work Specification paragraph number and must include inspection symbols (I) (Q) and (V).
4) Each test and inspection identified in the Work Specification by the (G)-Point symbol requires the SUPERVISOR's notification / witness and must be identified in the TIP.
5) Supporting data for tests and inspections requiring government notification (G), including accept/reject criteria, must be available at the location.
6) The TIP must be maintained at a contractor location accessible to the site of the work required by the Job Order and be updated within one day of the accomplishment or prior to the subsequent tests or inspection, whichever is less.
7) The TIP must annotate the relationship to a specific Key Event. The following Key Events must be considered at a minimum:
• Undocking.
• PCD.
• C5ILO.
• Dock Trials.
• Fast Cruise.
• Sea Trials.
• Availability Completion
Signature/Date Blank when FDRMC (G) inspection
Required
Calibration Date
Contractors Name Work Order/Job No:
TIP Rev/Date:
Milestone/Significant Event:
KTR:
FDRMC:
Location Inspection Type Inspection Description
Project/Vessel name & Number: Contract No:
TEST AND INSPECTION PLAN (TIP)
Work Spec Paragraph
Inspection Item Location Inspection Type Inspection Description Accept Criteria Test Equip S/N
Work Item: NAPL-##-### Scope/Description: Process Control Procedure (PCP):
Inspector Inspection Result
Accept Criteria
Calibration Date Signature/Date
KTR:
FDRMC:
Blank when FDRMC (G) inspection
Required
Test Equip S/N Inspector Inspection ResultWork Spec
Paragraph Inspection Item
KTR:
FDRMC:
Blank when FDRMC (G) inspection
Required
Work Spec Paragraph
Inspection Item Location Inspection Type Inspection Description Accept Criteria Test Equip S/N Inspector
Inspection Result
Calibration Date
Test Equip S/N
Signature/Date
An Excel Spreadsheet version of this Test and Inspection Plan may be used and is the preferred electronic media
Calibration Date
Work Spec Paragraph
Inspection Item Location Inspection Type Inspection Description Accept Criteria Test Equip S/N Inspector
Inspection Result Signature/Date
KTR:
FDRMC:
Blank when FDRMC (G) inspection
Required Copy and Insert additional work Items as required
Calibration Date Signature/Date
KTR:
FDRMC:
Blank when FDRMC (G) inspection
Required
Work Spec Paragraph
Inspection Item Location Inspection Type Inspection Description Accept Criteria Inspector
Inspection Result