This is a Construction Safety and Phasing Plan (CSPP) document prepared by Century West Engineering for the Oregon Department of Aviation's Joseph State Airport AWOS Replacement Project (AIP No. 3-41-0092-017-2026). The project involves the demolition of the existing Automated Weather Observation System (AWOS) and installation of a new AWOS-3P/T system, including sensor installation on the existing beacon tower, ground level sensors, and associated electrical equipment at Joseph State Airport located approximately 1.5 miles southwest of Joseph, Oregon. Construction is anticipated to commence in Summer 2026 and must be completed within 45 continuous calendar days from the contractor's Notice to Proceed. A preconstruction conference will be held before work begins, and weekly coordination meetings will occur throughout the project duration. The contractor must submit a Safety Plan Compliance Document (SPCD) for engineer approval a minimum of 14 days prior to the Notice to Proceed, and a Notice to Airmen (NOTAM) must be issued no later than 72 hours before construction commences.
The CSPP establishes comprehensive safety protocols to maintain airport operational integrity during construction, including restrictions on contractor access routes, vehicle marking requirements with orange and white checkered flags and flashing yellow beacons, mandatory airport safety and radio communication training for all personnel, and requirement for two-way radio communication monitoring on frequency 122.80 MHz. Construction activities are restricted to designated staging areas and approved haul routes, with a portion of Taxiway A closed from north of the fuel island to south of Taxiway A2 for the duration of construction while Runway 15-33 remains completely operational. The contractor must implement low-level barricades with diagonal orange/white reflective striping and flashing red lights spaced no more than 10 feet apart, maintain Foreign Object Debris (FOD) and wildlife management protocols, provide 24-hour emergency contact availability, and ensure daily safety inspections. Penalties for non-compliance include work stoppages, safety meetings, and potential liquidated damages, with the contractor held responsible for all accidents resulting from personnel non-compliance with the safety plan.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DOCUMENTS
FOR
OREGON DEPARTMENT OF AVIATION
JOSEPH STATE AIRPORT (JSY)
AWOS REPLACEMENT PROJECT
ATTACHMENT E – AWOS REPLACEMENT PROJECT
CONSTRUCTION SAFETY AND PHASING PLAN
OWNER:
Oregon Department of Aviation
3040 25th St. SE Salem, OR 97302
ENGINEER:
Century West Engineering
5500 Meadows Rd., Suite 250
Lake Oswego, OR 97035
Phone: 503.419.2130
APRIL 2026
This Page Left Intentionally Blank
Joseph State Airport AWOS Replacement Project
Construction Safety and Phasing Plan AIP No. 3-41-0092-017-2026
April 2026
Prepared for:
3040 25th Street SE
Salem, OR 97302
Prepared by:
5500 Meadows Road, Suite 250
Lake Oswego, OR 97035
40097.144.01 | April 2026 | Page 1
Table of Contents
Construction Safety and Phasing Plan
I. PURPOSE AND OBJECTIVE
II. RESPONSIBILITIES OF THE CONSTRUCTION CONTRACTOR
III. INTRODUCTION OF STAFF
IV. SCHEDULE AND SCOPE OF WORK
A. Schedule
B. Scope
V. SAFETY PLAN
A. Construction Safety and Phasing
40097.144.01 | April 2026 | Page 2
Appendices
Appendix A Construction Project Daily Safety Inspection Checklist
Appendix B Specification Sections 01160 and 01300
Appendix C Construction Safety and Phasing Plan
Appendix D Safety Plan Compliance Document
Appendix E Safety Plan Compliance Checklist
Appendix F Safety Plan Compliance Document Example
40097.144.01 | April 2026 | Page 3
I. PURPOSE AND OBJECTIVE
Aviation safety is the primary consideration at airports, especially during construction. The
Construction Safety and Phasing Plan (CSPP) is a tool used to ensure safety compliance when coordinating construction activities with airport operations. This document identifies all aspects of the Joseph State Airport AWOS Reconstruction Project that pose a potential safety hazard to airport operations and outlines mitigation procedures for each hazard.
This plan has been prepared in accordance with FAA Advisory Circulars (AC) 150/5300-13B, “Airport Design” and 150/5370-2G, “Operational Safety on Airports During Construction.”
The following objectives must be met by the “Team” comprised of: the Airport Manager; Oregon
Department of Aviation; the Engineering Design Consultant; the Prime Contractor; and various subconsultants, subcontractors, airport users, and airport tenants in order to maximize safety and minimize time and economic loss. These objectives include:
• Maintaining the safety and integrity of operations on the airport.
• To the greatest extent practical, keeping the airport operational for all users.
• Minimizing delays for aircraft and construction operations.
• Maximizing airport operation and construction activity opportunities.
The “Team” must keep these objectives in mind when formulating work schedules and work activities affecting operations on the airport.
II. RESPONSIBILITIES OF THE CONSTRUCTION CONTRACTOR
The Contractor is responsible for supplementing and following the CSPP by way of the Safety
Plan Compliance Document (SPCD). See Appendix D for SPCD and Contractor requirements.
Contractor to attend required airport safety training by ODAV and pre-construction meeting for airport project specifics prior to construction.
Any modifications to the CSPP and SPCD will require review and approval from ODAV and
FAA.
Preliminary Timeline
Contractor submit revised CSPP and SPCD 1 Day
ODAV (including Engineer) review 7 Days
Contractor revise CSPP 1 Day
FAA review 14 Days
Contractor address FAA comments 2 Days
OE/AAA review (if needed) 30 Days
III. INTRODUCTION OF STAFF
Key staff associated with the safety and operational planning of the Project.
40097.144.01 | April 2026 | Page 4
Jenna Pang Airport Engineer – FAA Seattle ADO (260)-231-4147
Anthony Beach Airport Manager – Oregon Department of Aviation (503)-378-2523
James Kirby, PE Senior Project Manager – Century West Engineering (503)-419-2130
Ryan Halvorson, PE Project Manager/EOR – Century West Engineering (503)-419-2130
IV. SCHEDULE AND SCOPE OF WORK
A. SCHEDULE
Dependent on funding availability, construction is anticipated to begin in Summer 2026.
B. SCOPE
The overall work includes the following:
1. Demolition of existing AWOS and removal of sensors on the existing beacon tower, ground level sensors, and the associated electrical equipment. The existing foundations are to remain in place.
2. Construction of new AWOS-3P/T, installation of sensors on the existing beacon tower, ground level sensors on existing foundation, and the associated electrical equipment on existing foundation.
V. SAFETY PLAN
A. CONSTUCTION SAFETY AND PHASING
The items listed below follow the guidance of Chapter 2, Section 2, “Plan Requirements” and Chapter 3, “Guidelines for Writing a CSPP” as provided in AC 150/5370-2G-Operational
Safety on Airports During Construction.
1) Coordination.
The Joseph State Airport AWOS Replacement project’s predesign, pre-bid, and preconstruction conferences will be used as opportunities to introduce the subject of airport operational safety during construction and to describe the elements of this
CSPP and resulting SPCD.
a. Contractor Progress Meetings. Operational safety will be a standing agenda item for discussion during weekly progress meetings throughout the duration of the project. The Engineer/Inspector will have final authority for safety decisions on-site and is responsible for stop-work order.
b. Scope or Schedule Changes. Changes in the scope or duration of the project will be represented by revisions to the CSPP.
40097.144.01 | April 2026 | Page 5
c. FAA-ATO Coordination. The contractor will work with the project representative during construction to assure that FAA Air Traffic Organization (ATO) will be coordinated with and schedule, airway facility (including NAVAIDs) shutdowns and restarts. The FAA ATO contact person will be the Western Service Center and can be reached at 1-206-2310-2420.
2) Phasing.
The Site Phasing and Safety Plan for the project details the scheduling of construction phases.
It is anticipated that the project will be completed in a single phase. The single phase includes project mobilization, demolition of the existing AWOS, and the installation of the new AWOS equipment, including the office terminal. The total contract time will be 45 calendar days.
3) Areas and Operations Affected by Construction Activity.
The attached Site Phasing and Safety Plan drawings for the project identify areas and operations affected by the construction. Major impacts include:
a. A portion of Taxiway A will be closed from north of the fuel island to south of
Taxiway A2 during the duration of the construction. The remainder of Taxiway A will remain open which will enable use of Runway 15-33 completely during all of construction. Back-taxi operations may be required.
4) NAVAID Protection.
The runway lights, lighted windcone, REILs, PAPIs, and Threshold lights will remain operational during construction. Extreme caution shall be used when working near new and existing light fixtures, underground electrical ducts, underground electrical cable and any other new or existing airport fixtures. Should damage occur to any of these items, they will be replaced at the Contractor’s expense.
5) Contractor Access.
a. Location of Stockpiled Construction Materials. Stockpiled materials and equipment storage will be restricted to the areas marked as ‘Contractor Staging
Area’ on the attached Site Phasing and Safety Plans. This area is located as far from aircraft operations as feasible. Contractor stockpiled materials and equipment storage are not permitted within Runway Safety Areas (RSA), Obstacle Free Zones (OFZ) or Object Free Areas (OFA) of operational runways.
Stockpiled materials and equipment adjacent to these areas are to be prominently marked and lighted during hours of restricted visibility or darkness
(see Section 16). Limit stockpiled materials to 12 feet in height and at least 125 feet from any runway centerline and 44.5 feet from any taxiway centerline.
Stockpiled materials shall not penetrate Part 77 surfaces shown on the Site
Phasing and Safety Plan in Appendix C. Materials are to be stabilized and stored at an approved location so as not to be a hazard to aircraft operations and to
40097.144.01 | April 2026 | Page 6 prevent attraction of wildlife and foreign object damage. Refer to Sections 6 and
7.
b. Vehicle and Pedestrian Operations. Vehicle and pedestrian access routes for airport construction projects must be controlled to prevent inadvertent or unauthorized entry of persons, vehicles, or animals onto the AOA. Construction and related vehicles shall be restricted to areas clearly indicated on the attached
Site Phasing and Safety Plan sheets and as directed by the Airport. The use of escort vehicles is addressed below.
i. Construction Site Parking. Vehicle parking areas for contractor employees will be restricted to ‘Contractor Staging Areas’ as depicted in the attached
Site Phasing and Safety Plan.
ii. Construction Equipment Parking. Contractor employees must park and service all construction vehicles in ‘Contractor Staging Areas’. Inactive equipment must not be parked on a closed taxiway or runway. Employees shall park construction vehicles in the designated areas when not in use by construction personnel (for example, overnight, on weekends, or during other periods when construction is not active).
iii. Access and Haul Roads. Construction contractor’s access to the construction sites and haul roads has been clearly marked on the Site
Phasing and Safety Plan. The construction contractor is not permitted to use any access or haul roads other than those approved. Access routes used by contractor vehicles must be clearly marked by contractor to prevent inadvertent entry to areas open to airport operations.
iv. Marking and Lighting of Vehicles. Contractor vehicles shall be marked with company identification (on both sides of the vehicle) and a flashing yellow beacon while operating within the airport boundary. Contractor vehicles will be required to have an Engineer approved orange and white checkered flag mounted on pickups, rollers, scrapers, dozers, trenchers, and all other Contractor vehicles and must be visible from 300 feet.
v. Vehicle Operations. Only vehicles used for construction purposes shall enter the air operations area. Contractor vehicle operations are allowed only in defined work areas, haul routes, and paved areas closed to aircraft traffic, unless otherwise approved by the Airport or Engineer in advance. The contractor is to familiarize all construction personnel with the safety provisions.
vi. Training Requirements for Vehicle Drivers. Contractor personnel shall attend Airport Safety and Radio Communication training; training records are kept on file. The training will introduce/refresh the Contractor on airport safety, operations, and communication. The Contractor will be required to pass a test at the end of the training.
40097.144.01 | April 2026 | Page 7
vii. Escorting. The Contractor and employees are not required to be escorted while on site if they have been trained per vi above.
viii. Situational Awareness. Vehicle drivers must confirm by personal observation that no aircraft is approaching their position (either in the air or on the ground) when given clearance to cross a runway, taxiway, or any other area open to airport operations.
ix. Two-way Radio Communication Procedures. When required by the
Airport the Contractor shall monitor the Common Traffic Advisory Frequency
(CTAF/UNIFOM) 122.80 MHz for Joseph Airport air traffic.
x. Maintenance of the Secured Area of the Airport. Not applicable. There are no secured areas on the airport.
6) Wildlife Management.
Construction contractors must carefully control and continuously remove waste or loose materials that might attract wildlife. Contractor personnel must be aware of and avoid construction activities that can create wildlife hazards on airports, such as the following:
a. Trash. Food scraps must be collected from construction personnel activity.
b. Standing Water. Standing water is not permitted on Airport grounds.
c. Tall Grass and Seeds. Grass seed is attractive to birds. Lower quality seed mixtures can contain seeds of plants (such as clover) that attract larger wildlife.
d. Poorly Maintained Fencing and Gates. See Section 5 above.
e. Encounters with Wildlife. If the contractor encounters large to medium sized mammals (such as deer) within Airport property fencing they are to notify the project representative during construction.
7) Foreign Object Debris (FOD) Management.
Waste and loose materials, commonly referred to as FOD, are capable of causing damage to aircraft landing gears, propellers, and jet engines. Construction contractors must not leave or place FOD on or near active aircraft movement areas. Materials capable of creating FOD must be continuously removed during the construction project.
The Contractor shall take care to manage FOD so as not to disturb operation of FAA owned facilities (including NAVAIDS) at the airport. Additionally, prior to reopening the runway or taxiways following a closure, all FOD must be removed from airfield pavement.
8) Hazardous Materials (HAZMAT) Management.
Encountering hazardous material (HAZMAT) during construction should be considered an emergency. Emergency procedures shall be followed in this instance. Contractor shall take care to prevent and contains leaks of hazardous material (fuel, hydraulic
40097.144.01 | April 2026 | Page 8 fluids, etc.). Contractors operating construction vehicles and equipment on the airport must be prepared to expeditiously contain and clean-up spills resulting from fuel or hydraulic fluid leaks.
9) Notification of Construction Activities.
a. List of Responsible Representatives:
In Case of Emergency
Joseph Police (General) ............................................................ (541) 432-3832
Joseph Fire District (Office) ...................................................... (541) 426-4978
Joseph State Airport Manager (Anthony Beach) ....................... (503) 378-2532
Century West Engineering ........................................................ (503) 419-2130
Federal Aviation Administration (Jenna Pang) .......................... (206) 231-4147
Poison Control Center ............................................................... (800) 222-1222
b. NOTAMs. Only the Airport Manager may initiate or cancel a Notice to Airmen
(NOTAM) on airport conditions and is the only entity that can close or open a runway or taxiway. The airport operator must coordinate the issuance, maintenance, and cancellation of NOTAMs about airport conditions resulting from construction activities with tenants and the local air traffic facility (control tower, approach control, or air traffic control center), and must provide information on closed or hazardous conditions on airport movement areas to the
FAA Flight Service Station (FSS) so it can issue a NOTAM.
Construction activity shall not commence prior to issuance of a NOTAM. The
Contractor shall provide written notice to the Engineer and Airport Manager at least 14 calendar days in advance of the planned commencement of construction activity. The Airport Manager will issue applicable NOTAMs no later than 72 hours prior to the start of closure activities. No further work in affected areas will be permitted after completion of work and removal of NOTAMs.
c. Emergency Notification Procedures. In the event of an emergency, Airport staff and the proper authorities will be notified immediately. In the event of an emergency, personnel and equipment shall move immediately to the staging area through appropriate routes. Prior to start of construction, the Contractor shall provide a list of contact information for personnel available 24 hours a day to be contacted in case of an emergency. As applicable, the list shall include phone numbers of the Engineer, Inspector, and Airport manager. The Contractor shall designate a qualified safety officer for the project as well as appoint a point of contact for any required operational safety concerns.
d. Coordination with ARFF. Coordinate ARFF activities with the Airport Manager.
Refer to Figure 1 for ARFF Access Route.
40097.144.01 | April 2026 | Page 9
Figure 1: ARFF Access Route
e. Coordination with Airport Hangar Tenants. Airport Manager to coordinate and notify airport hangar tenants a minimum of 2 days prior to closure of taxiway and access points via postings and/or emails.
f. Notification to the FAA.
i. Part 77. Any proposed construction or alterations of objects that affect navigable airspace, as defined in Part 77, will be coordinated with FAA.
ii. NAVAIDS. For emergency (short-notice) notification about impacts to both
Airport owned and FAA owned NAVAIDs, contact: 866-432-2622. FAA
ATO/Technical Operations shall be provided a 45-day minimum notice for the scheduled interruption of NAVAIDS.
10) Inspection Requirements.
a. Daily Inspections. Inspections shall be conducted at least daily, but more frequently if necessary to ensure conformance with the CSPP. For the
Contractors own use, a sample checklist has been attached to this safety plan in
Appendix A. The project representative during construction, serving as the project inspector, is responsible for monitoring work progress and will respond to construction and safety issues. The inspector will have communication capability with Airport staff. The Contractor is required to immediately remedy any deficiencies, whether caused by negligence, oversight, or project scope.
The Engineer is responsible for the supervision and enforcement of Safety Plan requirements, as well as addressing airfield issues with construction personnel, as appropriate.
40097.144.01 | April 2026 | Page 10
b. Inspections Prior to Reopening. As applicable, closed runway(s), taxiway(s) and tie-down apron(s) are subject to safety inspections prior to reopening the facilities for service. Requirements for reopening the runway at the end of each work shift include:
i. Runway Safety Area and Taxiway Safety Area conditions
a. Open trenches or excavations are not permitted within the RSA and TSA while the runway is open. Backfill trenches before the runway is opened.
If backfilling excavations before the runway must be opened is impracticable, cover the excavations appropriately. Covering for open trenches must be designed to allow the safe operation of the heaviest aircraft operating on the runway across the trench without damage to the aircraft.
b. The RSA and TSA must have no potentially hazardous ruts, humps, depressions, or other surface variations, and must be capable, under dry conditions, of supporting the occasional passage of aircraft without causing structural damage to the aircraft.
ii. Pavement conditions
a. Pavement edges and ends shall not exceed 3 inches vertically.
b. Construction debris (gravel, sand, mud, paving materials) and trash shall be removed from pavement prior to reopening runway.
iii. Return all equipment to staging areas.
iv. Remove barricades and runway closure markers.
11) Underground Utilities.
The following individuals, firms or corporations have authority to excavate or otherwise disturb non-FAA owned utility services or facilities located within the limits of the work:
Utility or other Facility Contact Person Phone Number
1. Utility One-Call One-Call Dispatcher 1-800-332-2344 (or 811)
2. FAA ATO Western Service Center 1-206-231-2420
No ground disturbance is allowed under this project. If accidental damage occurs, the
Contractor shall notify the Airport, the utility Company, and the Engineer.
12) Penalties.
Contractor will make construction personnel familiar with safety plan. All contractor and subcontractor personnel are required to comply with the safety plan. The Contractor will be held responsible for any accident that occurs as a result of construction personnel not following the provisions of this safety plan.
40097.144.01 | April 2026 | Page 11
Strict adherence to the provisions of this plan by all personnel assigned to or visiting the construction site is mandatory. In the event contractor activities are not in conformance with the provisions of this plan, the contractor shall immediately cease those operations involved in the violation of the provisions of this plan and conduct a safety meeting. The owner may direct the contractor, in writing, to immediately cease those operations involved in the violation of the provisions of this plan. The contractor shall not resume construction operations until an appropriate action is taken as determined by the Owner.
13) Special Conditions.
There are no special conditions that affect the operation of the airport or will require the activation of any special procedures.
14) Runway and Taxiway Visual Aids.
No impacts to runway and taxiway visual aids are anticipated for this project. Runway and taxiway visual aids shall remain in operation at all times.
Low level barricades will be utilized for define limits of construction. Low level barricades shall have nominal dimensions of 10”H x 96”L x 10”W, shall be specifically designed for airport use and shall be equipped with pins or connectors so that a “string” of barricades can be formed. They shall be weighted with water or sand as ballast. The low level barricades shall be in conformance with FAA AC 150/5370-2G, Operational Safety on
Airports During Construction. Low level barricades shall have diagonal striped, alternating, orange/white high reflective sheeting on both sides of the barricade, and two battery or solar powered flashing red lights. If solar powered lights are used, the contractor shall ensure that they are “on” during periods of low visibility, during daylight hours. Barricade type and placement shall be per the Construction Safety and Phasing plan, included in Appendix C. The low level barricades shall be spaced no more than 10 feet apart such that a breach is physically prevented barring a deliberate act. They shall be weighted down with water or sand as ballast.
15) Marking and Signs for Access Routes.
Pavement markings and signs for construction personnel will conform to AC 150/5340-
1M Standards for Airport markings and 150/5340-18H Standards for Airport Sign
Systems respectively and, to the extent practicable, with the Federal Highway
Administration Manual on Uniform Traffic Control Devices (MUTCD) and/or State highway specifications. Signs adjacent to areas used by aircraft must comply with the frangibility requirements of AC 150/5220-23, Frangible Connections.
16) Hazard Marking, Lighting and Signing.
a. Hazard marking and lighting prevents pilots from entering areas closed to aircraft and prevents construction personnel from entering areas open to aircraft.
Hazard marking and lighting must also be specified to identify open manholes, small areas under repair, stockpiled material, waste areas, and areas subject to jet blast.
40097.144.01 | April 2026 | Page 12
b. Hazard marking equipment.
i. Barricades will be used to identify and define the limits of construction and hazardous areas on airports. Low level barricades are proposed and will be used for the project. The low level barricades shall be in conformance with FAA AC 150/5370-2G, Airport Safety. Low level barricades shall have diagonal striped, alternating, orange/white high reflective sheeting on both sides of the barricade, and two battery or solar powered flashing red lights. If solar powered lights are used, the contractor shall ensure that they are “on” during periods of low visibility, during daylight hours. Barricade type and placement shall be per the
Construction Safety and Phasing Plan, included in Appendix C. The spacing of the barricades shall be no more than 10 feet apart, such that a breach is physically prevented barring a deliberate act.
ii. Lights must be red and must meet the luminance requirements of the
State Highway Department. Lights must be mounted on barricades and spaced at no more than 10 ft. Lights must be operated between sunset and sunrise and during periods of low visibility whenever the airport is open for operations. Mounted barricade lights may be operated by photocell or battery power, but the contractor must maintain the aforementioned luminance requirements while the airport is open for operations.
iii. No supplemental barricades with signs are needed for the proposed project.
iv. Air Operations Area – General. Barricades are not permitted in any active safety area or on the runway side of a runway hold line.
v. Air Operations Area – Runway/Taxiway Intersections. Use highly reflective barricades with lights to close taxiways leading to closed runways. Even for closures of relatively short duration, close all taxiway/runway intersections with barricades.
vi. Air Operations Area – Other. Not applicable to this project.
vii. Maintenance. In accordance with specification Section 01300 the contractor is required to have a person on call 24 hours a day for emergency maintenance of airport hazard lighting, barricades, and orange mesh safety fence. The contractor must file the contact person’s information with the airport operator.
17) Protection of Runway and Taxiway Safety Areas.
a. Runway Safety Area (RSA). A runway safety area is the defined surface surrounding the runway prepared or suitable for reducing the risk of damage to
40097.144.01 | April 2026 | Page 13 airplanes in the event of an undershoot, overshoot, or excursion from the runway
(see AC 150/5300-13B, latest edition and changes).
The Joseph State Airport RSA has the following dimensions:
Runway 15-33: 120’ in width and 5,680’ in length
Construction activities within the RSA are subject to the following conditions:
i. No activity (including construction) may occur within the RSA while the runway is open for aircraft operations.
ii. The RSA width will not be adjusted for the proposed project.
iii. Stockpiles are not permitted within the RSA while the runway is open.
iv. Excavations
a. Open trenches or excavations are not permitted within the RSA while the runway is open. No excavations or ground disturbances are allowed under this project.
v. Soil erosion must be controlled to maintain RSA standards, that is, the
RSA must be cleared and graded and have no potentially hazardous ruts, humps, depressions, or other surface variations, and capable, under dry conditions, of supporting snow removal equipment, aircraft rescue and firefighting equipment, and the occasional passage of aircraft without causing structural damage to the aircraft.
b. Runway Object Free Area (ROFA). Construction is not anticipated in the ROFA.
Equipment must be removed from the ROFA when not in use. The proposed project does not allow stockpiling within the ROFA.
The Joseph State Airport ROFA has the following dimensions:
Runway 15-33: 250’ in width and 5,680 in length
c. Taxiway Safety Area (TSA). A taxiway safety area is a defined surface alongside the taxiway prepared or suitable for reducing the risk of damage to an airplane unintentionally departing the taxiway.
The Joseph State Airport TSA has a width of 49’.
Construction activities within the TSA are subject to the following conditions:
i. No activity (including construction) may occur within the TSA while the taxiway is open for aircraft operations.
ii. The TSA width will not be adjusted for the proposed project.
iii. Excavations
40097.144.01 | April 2026 | Page 14
a. If required by Airport Operations, open trenches or excavations are not permitted within the TSA while the taxiway is open. No excavations or ground disturbances are allowed under this project.
b. If required by Airport Operations, construction contractors must prominently mark open trenches and excavations at the construction site with red or orange flags, as approved by the airport operator, and light them with red lights during hours of restricted visibility or darkness.
iv. Soil erosion must be controlled to maintain TSA standards, that is, the
TSA must be cleared and graded and have no potentially hazardous ruts, humps, depressions, or other surface variations, and capable, under dry conditions, of supporting snow removal equipment, aircraft rescue and firefighting equipment, and the occasionally passage of aircraft without causing structural damage to the aircraft.
d. Taxiway Object Free Area (TOFA). Unlike the Runway Object Free Area, aircraft wings regularly penetrate the taxiway object free area during normal operations. Thus, the restrictions are more stringent. No construction may occur within the taxiway object free area while the taxiway is open for aircraft operations.
The Joseph State Airport TOFA has a width of 89’.
e. Obstacle Free Zone (OFZ). Personnel, material, and/or equipment may not penetrate the OFZ while the runway is open for aircraft operations.
The Joseph State Airport OFZ has the following dimensions:
Runway 15-33: 250’ in width and 5,600’ in length
f. Runway Approach/Departure Areas and Clearways. All personnel, materials, and/or equipment must remain clear of the applicable threshold siting surfaces, as defined in Appendix 2, “Threshold Siting Requirements,” of AC 150/5300-13B, latest edition and changes.
18) Other Limitations on Construction.
a. Prohibitions.
i. No use of tall equipment (cranes, concrete pumps, and so on) unless a
7460-1 determination letter is issued for such equipment. A 7460-1 determination letter shall be submitted timely for the use of tall equipment.
ii. No use of open flame, welding, or torches unless fire safety precautions are provided and the airport operator has approved their use.
iii. No use of electrical blasting caps on or within 1,000 ft. (300 m) of the airport property.
40097.144.01 | April 2026 | Page 15
iv. No use of flare pots within the AOA.
a. Restrictions. The Notes and Details shown on the attached Site Work Area and
Safety Plan offer additional details on restrictions on which areas cannot be worked in simultaneously, day/night work restrictions and other limitations.
Appendix A Construction Project Daily Safety Inspection Checklist
12/13/2017 AC 150/5370-2G
Appendix D
D-1
APPENDIX D. CONSTRUCTION PROJECT DAILY SAFETY INSPECTION CHECKLIST
The situations identified below are potentially hazardous conditions that may occur during airport construction projects. Safety area encroachments, unauthorized and improper ground vehicle operations, and unmarked or uncovered holes and trenches near aircraft operating surfaces pose the most prevalent threats to airport operational safety during airport construction projects. The list below is one tool that the airport operator or contractor may use to aid in identifying and correcting potentially hazardous conditions. It should be customized as appropriate for each project including information such as the date, time and name of the person conducting the inspection.
Table D-1. Potentially Hazardous Conditions
Item Action Required (Describe)
No Action
Required
(Check)
Excavation adjacent to runways, taxiways, and aprons improperly backfilled.
Mounds of earth, construction materials, temporary structures, and other obstacles near any open runway, taxiway, or taxi lane; in the related Object Free area and aircraft approach or departure areas/zones;
or obstructing any sign or marking.
Runway resurfacing projects resulting in lips exceeding 3 inch (7.6 cm) from pavement edges and ends.
Heavy equipment (stationary or mobile) operating or idle near AOA, in runway approaches and departures areas, or in
OFZ.
Equipment or material near NAVAIDs that may degrade or impair radiated signals and/or the monitoring of navigation and visual aids. Unauthorized or improper vehicle operations in localizer or glide slope critical areas, resulting in electronic interference and/or facility shutdown.
Tall and especially relatively low visibility units (that is, equipment with slim profiles)
— cranes, drills, and similar objects — located in critical areas, such as OFZ and
D-2
Item Action Required (Describe)
No Action
Required
(Check) approach zones.
Improperly positioned or malfunctioning lights or unlighted airport hazards, such as holes or excavations, on any apron, open taxiway, or open taxi lane or in a related safety, approach, or departure area.
Obstacles, loose pavement, trash, and other debris on or near AOA. Construction debris
(gravel, sand, mud, paving materials) on airport pavements may result in aircraft propeller, turbine engine, or tire damage.
Also, loose materials may blow about, potentially causing personal injury or equipment damage.
Inappropriate or poorly maintained fencing during construction intended to deter human and animal intrusions into the AOA.
Fencing and other markings that are inadequate to separate construction areas from open AOA create aviation hazards.
Improper or inadequate marking or lighting of runways (especially thresholds that have been displaced or runways that have been closed) and taxiways that could cause pilot confusion and provide a potential for a runway incursion. Inadequate or improper methods of marking, barricading, and lighting of temporarily closed portions of
AOA create aviation hazards.
Wildlife attractants — such as trash (food scraps not collected from construction personnel activity), grass seeds, tall grass, or standing water — on or near airports.
Obliterated or faded temporary markings on active operational areas.
Misleading or malfunctioning obstruction lights. Unlighted or unmarked obstructions in the approach to any open runway pose aviation hazards.
D-3
Item Action Required (Describe)
No Action
Required
(Check)
Failure to issue, update, or cancel
NOTAMs about airport or runway closures or other construction related airport conditions.
Failure to mark and identify utilities or power cables. Damage to utilities and power cables during construction activity can result in the loss of runway / taxiway lighting; loss of navigation, visual, or approach aids; disruption of weather reporting services; and/or loss of communications.
Restrictions on ARFF access from fire stations to the runway / taxiway system or airport buildings.
Lack of radio communications with construction vehicles in airport movement areas.
Objects, regardless of whether they are marked or flagged, or activities anywhere on or near an airport that could be distracting, confusing, or alarming to pilots during aircraft operations.
Water, snow, dirt, debris, or other contaminants that temporarily obscure or derogate the visibility of runway/taxiway marking, lighting, and pavement edges.
Any condition or factor that obscures or diminishes the visibility of areas under construction.
Spillage from vehicles (gasoline, diesel fuel, oil) on active pavement areas, such as runways, taxiways, aprons, and airport roadways.
Failure to maintain drainage system integrity during construction (for example, no temporary drainage provided when working on a drainage system).
D-4
Item Action Required (Describe)
No Action
Required
(Check)
Failure to provide for proper electrical lockout and tagging procedures. At larger airports with multiple maintenance shifts/workers, construction contractors should make provisions for coordinating work on circuits.
Failure to control dust. Consider limiting the amount of area from which the contractor is allowed to strip turf.
Exposed wiring that creates an electrocution or fire ignition hazard.
Identify and secure wiring, and place it in conduit or bury it.
Site burning, which can cause possible obscuration.
Construction work taking place outside of designated work areas and out of phase.
Appendix B Specification Sections 01160 and 01300
CENTURY WEST ENGINEERING 01160 General Requirements – 1 of 6 APRIL 2026 | #40097.144.01
01160 GENERAL REQUIREMENTS
1.00 GENERAL SCOPE
1.01 Location and Plans. The location of the work is at the Joseph State Airport (JSY), located approximately 1.5 miles southwest of downtown Joseph, Oregon. Joseph State
Airport is owned by the Oregon Department of Aviation (ODAV). For the purpose of this contract, the terms Airport and Owner are considered the same.
The contract plans for this project consist of 8 sheets titled “Oregon Department of
Aviation, Joseph State Airport AWOS Replacement”.
1.02 Airport Security. During the course of the contract, the Contractor shall be responsible for maintaining security against unauthorized access to the Airport. The
Contractor will be held responsible for any fines, damages, or civil penalties filed against
ODAV and Joseph State Airport for the Contractor's failure to maintain the regulations set forth herein.
The Contractor shall be fully responsible for compliance of all employees with the Airport security program and following regulations and orders of the Airport management. These regulations may affect identification requirements of employees and subcontractors, movement around the Airport, parking, entry, and other circumstances affecting the safety or protection of persons or property. The security requirements are subject to change at any time during the project without prior notice.
For the intent and purpose of these regulations, Air Operations Area (AOA) is construed to mean any area used or intended to be used for takeoff, landing, or surface maneuvering of aircraft, and all other areas restricted to public access on the field. Work boundaries within the AOA shall be established as shown on the drawings. Only Contractor's employees are permitted in the work sites.
The term “gate” used herein shall mean any controlled, securable opening in the security fence. The Contractor must enter and exit the AOA only through the gates designated by the Engineer. Deliveries to work sites will be controlled by the Contractor or, if applicable, a security gate guard (employed by the Contractor), who will record name and license of driver, vehicle license, and times in and out. The Contractor shall keep the gates locked and secured at all times when not in use. The Contractor shall account for Airport-issued keys and access cards in a manner approved by the Airport.
Within the Air AOA, all equipment, vehicle, and personnel travel shall be restricted to designated work sites.
Only vehicles used for construction purposes that are clearly marked with company logos shall enter the AOA. Contractor personnel shall park their personal vehicles within a designated staging area.
FAA-approved orange and white checkered flags shall be provided by the Contractor on all vehicles and equipment within the Airfield.
During night operations, each vehicle entering the AOA shall be equipped with a yellow flashing light mounted on the roof of the cab. Headlights, taillights, and flashers shall be used for all activities during these hours.
CENTURY WEST ENGINEERING 01160 General Requirements – 2 of 6 APRIL 2026 | #40097.144.01
In the event of an emergency, personnel and equipment shall move immediately to the staging area.
1.03 Layout of the Work. The Contractor will do all the construction surveying on the project. The Engineer will provide vertical and horizontal reference control points in the proximity of the work. The Contractor should refer to Section 01406, “Construction
Staking”, for specific requirements.
1.04 Completion Time. All items of contract work shall be substantially complete within the time period specified in the “Proposal” and the “Contract” or “Agreement”.
1.05 Environmental Codes and Regulations. The Contractor shall comply with provisions of Federal, State and local statutes, ordinances and regulations dealing with the prevention of environmental pollution and the preservation of natural resources that affect the project.
If the Contractor must undertake additional work due to the enactment of new or the amendment of existing statutes, ordinances and regulations dealing with the prevention of the successful bid, the Airport will issue a supplemental agreement setting forth the additional work that must be undertaken. The supplemental agreement shall not invalidate the contract and there shall be, in addition to a reasonable extension of contract time, if necessary, a reasonable adjustment in the contract price to compensate the successful bidder for all costs and expenses incurred, including overhead and profits, as a result of the additional work.
1.06 Special Permits. The Contractor shall pay for and obtain any and all permits required for construction of the work.
1.07 Inspection and Testing. All tests called for in the specifications or deemed necessary by the Engineer will be performed by the Engineer, except when indicated otherwise in the specifications. The Engineer will perform quality assurance testing when, in the opinion of the Contractor, the work area to be tested is prepared and will meet the required specifications. Contractor shall schedule testing at least 48 hours in advance of when he is ready for the test. Hot mix asphalt testing shall be scheduled a minimum of 14 days in advance of beginning paving. In the event test results do not meet the specifications, any cost for re-testing as may be required by the Engineer shall be at the
Contractor's expense, charged at the rate established in the Engineer's standard fee schedule.
1.08 Contractor's Staging Area. An area (or areas) will be set aside on the Airport property for the Contractor's use as a staging area for personnel, equipment, and materials. The Contractor shall obtain all necessary building permits and operating licenses from local governmental agencies. The Engineer will define the actual location in the field. The Contractor may install a security fence. The area shall be restored to its original condition at the conclusion of the work, at no cost to the Owner.
1.09 Disposal of Waste Material. Excess materials of all kinds, including, but not limited to waste earthen material, unsuitable material, strippings, and vegetation/organic material from clearing and grubbing or excavation shall be disposed of off-site at the Contractor's expense.
Concrete and other debris shall be disposed of offsite.
CENTURY WEST ENGINEERING 01160 General Requirements – 3 of 6 APRIL 2026 | #40097.144.01
Disposal of waste materials shall be in accordance with governing agency safety, health, and other requirements.
1.10 Site Investigation and Representation. The Contractor acknowledges familiarity as to the nature and location of the work, the general and local conditions, particularly those bearing upon availability of transportation, disposal, handling and storage of materials, availability of labor, water, electric power, roads, and uncertainties of weather, or similar physical conditions at the site, the conformation and conditions of the ground, the character of equipment and facilities needed preliminary to and during the prosecution of the work and all other matters which can in any way affect the work or the cost thereof under this contract.
The Contractor further acknowledges understanding of the character, quality, and quantity of surface and subsurface materials to be encountered from inspecting the site.
The Contractor warrants that as a result of the examination and investigation of all the aforesaid data that he can perform the work in a good and workmanlike manner and to the satisfaction of the Airport. The Airport assumes no responsibility for any representations made by any of its officers or agents during or prior to the execution of this contract, unless (1) such representations are expressly stated in the contract, and (2) the contract expressly provides that the responsibility therefore is assumed by the Airport.
Representations for which liability is not expressly assumed by the Airport in the contract shall be deemed only for the information of the Contractor.
1.11 Information on Site Conditions. All information obtained by the Airport regarding site conditions, subsurface information, ground water elevations, existing construction of site facilities as applicable, and similar data will be available for inspection upon request.
Such information is offered as supplementary information only. The Airport does not assume any responsibility for the completeness or interpretation of such supplementary information.
1.12 Subsurface and Site Information. Information derived from inspection of test results, of topographic maps, or from plans showing location of utilities and structures will not in any way relieve the Contractor from any risk, or from properly examining the site and making such additional investigations as he may elect, or from properly fulfilling all the terms of the contract documents.
The submission of a proposal shall be conclusive evidence that the Bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the contract documents.
1.13 Underground Utilities. Known utilities and structures expected to be adjacent to or encountered in the work are shown on the plans. It is expected that there may be some discrepancies and omissions in the locations and quantities of utilities and structures shown. Those shown are for the convenience of the Contractor only, and no responsibility is assumed by the Airport for their accuracy or completeness.
1.14 Fire Prevention and Protection. The Contractor shall perform all work in a fire-safe manner. The Contractor shall comply with applicable local and State fire prevention regulations.
CENTURY WEST ENGINEERING 01160 General Requirements – 4 of 6 APRIL 2026 | #40097.144.01
1.15 Temporary Water. No potable water supply is immediately available at the designated Contractor's staging area. The Contractor shall make arrangements for obtaining water and pay all costs for same.
1.16 Temporary Electric Power. No electric power is immediately available at the designated Contractor's staging. The Contractor shall make arrangements for electric power for use during the construction period until final acceptance by the Airport, and pay all costs for same.
1.17 Sanitary Facilities. The Contractor shall provide and maintain sanitary facilities for employees and subcontractor's employees that will comply with the regulations of the local and State departments of health and as directed by the Engineer.
2.00 GENERAL CONSTRUCTION RESPONSIBILITIES AND PROCEDURES
2.01 Site Restoration and Cleanup. Upon completion of the project, all areas used by the Contractor in connection with the work shall be properly cleared of all temporary structures, rubbish, and waste materials and properly graded to drain and blend in with the abutting property.
2.02 Haul Routes and Maintenance. The Contractor shall abide by prevailing legal load limit regulations when hauling over airfield pavements and public roads. The Contractor shall perform all necessary maintenance of haul routes during construction and shall perform all work as necessary to restore the routes used by all equipment to their original condition at the conclusion of construction. New construction haul roads shall be obliterated and original vegetation re-established. Existing roadways, runways, and taxiways shall be patched or overlaid at the Contractor’s expense, as necessary to restore them.
Unsurfaced haul roads shall be sprinkled with water as necessary to prevent dust diffusion during the course of the work.
All maintenance and restoration work shall be completed to the Engineer's satisfaction before final payment is awarded. No direct payment will be made for this work.
2.03 Responsibility for Damage to Existing Structures. Where any existing structures or facilities which are intended to remain are damaged by the Contractor during demolition or construction, the Contractor shall promptly repair or replace the damaged portion or facility at no additional cost to the Airport.
2.04 Storage of Materials. Materials shall be so stored as to insure the preservation of their quality and fitness of the work. When considered necessary, they shall be placed on wooden platforms or other hard, clean surfaces, and not on the ground, and/or they shall be placed under cover. Stored materials shall be located so as to facilitate prompt inspection. Private property shall not be used for storage purposes without the written permission of the Airport or lessee.
2.05 Cleanup. The Contractor shall at all times during the work keep the premises clean and orderly, and shall promptly remove all waste materials and rubbish. All directions from the Engineer and other authorized public officials having jurisdiction over health and safety shall be obeyed. Areas to be opened up to aircraft operations shall be swept thoroughly clean with power broom equipment. Any debris resisting sweeping shall be removed by hand labor or other suitable means.
CENTURY WEST ENGINEERING 01160 General Requirements – 5 of 6 APRIL 2026 | #40097.144.01
Upon completion of the work, all materials, equipment, and appurtenances not required, as a part of, or appurtenant to, the completed structure or facility shall be completely removed from the Airport property.
2.06 Blasting. Blasting is not allowed.
3.00 WORK PROGRESS SCHEDULE
3.01 Scope. The work specified in this subsection includes planning, scheduling, and reporting that is required to be performed by the Contractor.
3.02 Preconstruction Conference. A preconstruction conference will be held at the
Airport before Notice to Proceed is issued. The conference shall be attended at a minimum by the Contractor’s project manager and superintendent, and representatives of all subcontracting firms that will provide five percent (5%) or more of the total value of the project. A copy of the Contractor’s anticipated construction schedule shall be submitted to the Engineer at least 5 days prior to the preconstruction conference. The Contractor shall be prepared to discuss details of how construction will progress, how they expect to conduct their operations, and discuss operational and safety requirements associated with the work.
3.03 Coordination Meetings. Coordination meetings will be held on a weekly basis or more often if necessary, to communicate work efforts between the Engineer, the Airport and the Contractor. The Resident Engineer will schedule the meetings with attendance required by at least one person from each organization.
3.04 Method. An overall project critical path schedule…
This is the start of the file's text. The full file is on GovTribe.