REPAIR, REMOVE, SUPPLY AND INSTALL HVAS
Solicitation number
70Z02421QPRW185
Issued by

Text of this file

5 | Page

Statement of Work for

Station NY Palazzo Hall/Building 8 &10 HVAC Repair FY21

70Z02421QPRW18500

Date april 06, 2021

Table of Contents

Introduction/Background2
Scope of Work2
Period of Performance3
Place of Performance3
Schedule3
Applicable documents3
Submittals3

Introduction/Background

The US Coast Guard Sector New York Engineering Department requires HVAC Repairs for the outlaying unit Station New York. Station New York is a Coast Guard base that secures the waterways around the Hudson Bay and surrounding areas. Palazzo Hall is a relatively new structure built within the last 5 years, while Building 8 & 10 are some of the oldest structures on its site. Both require HVAC repairs at this time.

Scope of Work

Palazzo Hall (Building 2)

The contractor shall supply and install any labor, material, tools, supervision, etc. to troubleshoot and repair all HVAC faults on the below unit to bring the unit back online and operating properly:
Unit Tag:OACU-1
MAKE:AAON
Model:V3-DRB-3-A-162C-000
Serial:201509-CJCD02217

At this time, the USCG has determined that both the compressor and controller is in need of replacement. The contractor is responsible for confirming this before making the repairs. With replacement of the two items listed above, the contractor shall abide by all EPA regulations in the recovery and introduction of all refrigerants.

The contractor shall not use old, or previously used refrigerant while refilling the system as well as replacing any existing filter driers installed. If the installation of the compressor and/or filter drier requires the use of torches, burning, soldering, etc., the contractor shall purge the lines with nitrogen at a minimum 1.5 psi throughout the full process.

Prior to re-introducing refrigerant to the system, the contractor shall pressure test all lines by manufacturer’s specifications and record the times and pressures to be given to the USCG upon completion.

All warranty cards or information shall be forwarded to the USCG for future use.

Buildings 8 & 10

The contractor shall supply all supervision, labor, material, tools, etc. to remove and install (2) condensers listed herein. The installation will include but is not limited to all HVAC, Electrical, Plumbing, Mechanical work needed to complete the full installation and operational capabilities of the condensers. The contractor shall abide by all current EPA and OSHA regulations regarding this install and while working on site. All refrigerants shall be documented stating the type, unit, and by lb/oz when recovering and/or pressurizing. Nitrogen testing, vacuum testing, or other means of testing shall be documented with pressures, dates, and times. At minimum, a nitrogen test per unit shall hold for (4) hours at a pressure 20% higher than the average operating pressure in 120F weather. The vacuum test must be brought down to 100micron before the introduction of refrigerants. The contractor must adhere to all installation instructions set forth by the manufacturer documents.
Both condensers listed below shall be spray coated with MicroGuard for Seasalt protection, or an equivalent chemical that protects the corrosion of the Condensers. The coating shall be done by the manufacturer prior to the procurement of the condenser and shall not be done by the contractor on or off site.

Existing Condensers

Unfortunately the below information is all the USCG can find on the units themselves. A site visit is preferred if the Contractor requires more information about the specific unit.

Building 8

Condenser
Model Number: 4TTA3036B3000AA
Serial Number: S/N 132656AL3F
Air Handler
Model Number: BMB12-3G-2W

Building 10

Condenser
Model Number: YD180C000A2AAA2A

The Air handler doesn’t have manufacturer’s stickers.

The contractor shall use the above information for referencing only and shall replace each with minimum 13 seer units.

The Contractor shall create and fill out a typical HVAC startup sheet after installation that shows temperatures, pressures, electrical data, etc. for the condensers and the air handlers. Differences between the data shall span over the course of 1 hour minimum.

Period of Performance

Period of performance is expected to be April 2021 contingent on weather and shortly after the award date. Estimated award date will be 2 – 3 weeks after solicitation date.

Place of Performance

The Engineering Office Building located at 311 Battery Road, Staten Island NY 10305 will be the main POC building for all needs. The contractor will be escorted from there to the work site <1 Mile away to Buildings 8 and 10, both under the address 10 Search Lane, Staten Island NY 10305-5055.

CONTRACTING OFFICER’S REPRESENTATIVE (COR)

Mr. Anthony Arico 718-354-4241 or Anthony.j.arico@uscg.mil

SITE VISIT

4/13/2021 at 10AM with make-up date of 4/15/2021 at 10AM. Meet at 311 Battery Rd., Staten Island, NY 10305-5055.

Schedule

Award Date (TBD)

Preconstruction Meeting and Walkthrough (scheduled within 5 days of award) Preconstruction Meeting will be done over a phone conference to all parties involved due to COVID restrictions. Meeting will be for introductions, scheduling and any questions, concerns, etc. required. Information will be taken to create IDs for those working onsite.

Commence work within one month’s time as estimated above and/or scheduled by pre-construction meeting.
Inspections and testing shall be done during installation of the Units
End of Contract and Approval

Applicable Documents N/A

Submittals

The contractor shall submit the manufacturer’s operational and installation instructions for submittal and approval prior to the installation and procurement. The information shall be given to the COR.

The contractor shall detail the piping installation procedure prior to installation. The USCG’s main concern will be if torching will be done on site. Though it is outside, the USCG will provide a watch-stander during this process. If compression fittings are to be used, the contractor shall supply the information of the material showing that it is American Made and the pressure ratings.
The contractor shall submit all testing records that include but not limited to the pressurization, vacuuming, and amount of refrigerant.
The startup sheet listed above shall be copied and sent to the Contracting Officer and Representative after installation. This information is imperative and the job will not be signed off without it.
The contractor shall supply to the USCG prior to installation all EPA certifications for any technician working on site.
The contractor shall supply to the USCG a pressure test report.
The contractor shall supply to the USCG all warranty information, cards, etc for any equipment installed.

Other files

File Type Posted
SF1413-13b.pdf PDF
RW185WR.txt TXT text file
RW185RFQPKG.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .