This document contains a question and answer session as well as an addendum related to a Request for Proposal (RFP) issued by the Florida Department of Transportation (FDOT) District Five for Road Ranger Service Patrols (RRSP) along Interstate 4 (I-4) and Interstate 95 (I-95). The RFP seeks proposals from qualified contractors to provide motorist assistance and traffic incident management support within select segments along I-4, I-75, I-95, SR 528, and connecting roadways in several Florida counties. The RFP requires a minimum of 10 pickup trucks (7 primary and 3 spare) to provide 24-hour service on I-4 and 6am-10pm service on I-95 and SR 528, with a minimum of 2 units on I-4 from 6am-10pm and 1 unit overnight. Proposals are due by December 11, 2023, at 10:00 AM.
The RFP specifies a minimum monthly patrol hours requirement of 2800 hours, although the actual monthly hours may vary based on the contracted hourly rate and final approved schedule. The contractor must be properly licensed and registered to do business in the State of Florida. The contract will be subject to a 1% MFMP Transaction Fee and must comply with various nondiscrimination statutes and authorities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RRI4 Addendum 1.pdf | ||
| DOT-RFP-24-5005-RRI4 Complete.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Transportation
RON DESANTIS
GOVERNOR
605 Suwannee Street
Tallahassee, FL 32399-0450
JARED W. PERDUE, P.E.
SECRETARY
Improve Safety, Enhance Mobility, Inspire Innovation www.fdot.gov
ADVERTISEMENT NUMBER: DOT-RFP-24-5005-RRI4
DESCRIPTION: District Five Road Ranger Service Patrol (RRSP) for Interstate 4 (I-4) and Interstate
95 (I-95)
DATE: 12/7/2023
1.) Does the minimum number of trucks (referenced below) include trucks for I-4?
6.8 RRSP Vehicle Requirements
6.8.1 Pick-Up Trucks (page 33)
The CONTRACTOR will provide, at a minimum, ten (10) pick-up trucks (7 primary units and three 3 spare units) Note, this is a minimum. The CONTRACTOR is responsible for determining the necessary number of units to maintain confinuous services during prescribed coverage hours.
Answer: Yes, this is for all of the I-4 and I-95 coverage areas. As stated in the scope, this is the required minimum, as more may be necessary to cover the hours required.
2.) The Scope of Services does not include SR-528 however the Standard Operafing Guidelines (SOG) and Introducfion does. Is SR-528 included in the expected coverage?
SECTION 1 – INTRODUCTION (Page 4)
The Florida Department of Transportafion (FDOT) District Five, hereafter referred to as the
DEPARTMENT, requires services by a Road Ranger Service Patrol (RRSP) provider, hereafter referred to as the CONTRACTOR. The CONTRACTOR is responsible for providing motorist assistance and Traffic Incident Management (TIM) support within select segments along I-4, I-
75, I-95, SR 528, and any connecfing roadways, in the counfies of Brevard, Flagler, Lake, Marion, Orange, Osceola, Sumter, Seminole, and Volusia. Coverage includes all on and off ramps and requires addifional mileage into counfies of adjacent districts for turnaround points. Road Rangers can, at any fime, be dispatched up to 2.5-miles off the interstate.
SECTION 3 - GENERAL REQUIREMENTS (Page 11)
3.2 Hours of Operafion
RRSP vehicles operafing in District Five will provide services as outlined below, including
DEPARTMENT observed holidays for the term of the Contract.
a. I-4 East Zone (MM 98-MM 132, does not include turnarounds): 24-hrs;
minimum 2-units from 6am-10pm and 1-unit overnight
b. I-95 (MM 160-298, does not include turnarounds) and SR 528 (MM 31-46):
6am-10pm, minimum of 6-units, Monday – Friday and 4 units on Saturday and Sunday.
6.2 RRSP Service Areas (Page 28)
The RRSP service area for this contract spans approximately 182 interstate centerline miles covering the counfies of Flagler, Volusia, Brevard, Lake, and
Seminole. These include I-4, I-95, and any connecfing roadways. Addifional required coverage includes turnaround segments into the adjacent county or zone, all on- and off- ramps, and up to 2.5-miles on an arterial that is adjacent to the interstate. (Coverage must be provided for the enfire extent of District 5, requiring RRSP units to enter the next county/zone in order to turn around and the next available interchange.)
6.3 Hours of Operafion (Page 30)
CONTRACTOR shall ensure that RRSP vehicles are always fully operafional with full deployment of assigned zones.
a. I-4 East Zone (MM 98-MM 132, plus addifional miles to include turnarounds): 24-hrs; minimum 2-units from 6am-10pm and 1-unit from
10pm-6am.
b. I-95 (MM 160-298, plus addifional miles to include turnarounds, minimum of 5-units, Monday – Friday and 4 units on Saturday and Sunday.
Answer: See Addendum 1.
3.) The minimum monthly hours listed on ‘EXHIBIT "B" District Five Road Rangers Service Patrol (RRSP) for Interstate 4 (I-4) and Interstate 95 (I-95) METHOD OF COMPENSATION Secfion 2.0
Compensafion; Table 1: Normal Service’ is stated as 2800. The Scope of Services which details the number of trucks, routes, and daily schedule seemingly contradicts the minimum hours of 2800.
Can you please clarify the minimum monthly hours including the details above in the Scope of services?
Answer: The total patrol hours per month will vary based on the finalized contracted hourly rate and final approved schedule. The 2800 hours referenced in “Table 1” is the monthly minimum hours that are required.
4.) Due to the complexity and details required in the submission of the Technical Proposals, can FDOT extend the submission date by at least a week or more on DOT-RFP-24-5006-RR75 & DOT-RFP-24-
5005-RRI4?
Answer: While we understand the effort required from our industry partners to prepare and respond to the Request for Proposals, based on our current schedule, we are not able to accommodate an extension to the submission date at this fime.
FAILURE TO FILE A PROTEST WITHIN THE TIME PRESCRIBED IN SECTION 120.57(3),
F.S. SHALL CONSTITUTE A WAIVER OF PROCEEDINGS UNDER CHAPTER 120, F.S.