This document contains Repair Qualification Requirements (RQR) for multiple National Stock Numbers (NSNs) related to the AN/TPS-75 radar system. The RQR details the qualification requirements that prospective offerors must satisfy to become an approved repair source for items such as the Pulse Forming Network (PFN) Regulator, Trigger Amplifier, Exciter Radio Frequency, SF6 Tank Assembly, and Oil Tank Assembly.

The key requirements include: certifying facilities and equipment capabilities, verifying a complete data package, demonstrating the repair process, and conducting qualification testing at the offeror's expense. Prospective offerors must meet these requirements prior to the contract award date to be eligible for the subsequent repair contract. The document also outlines waiver criteria that may allow offerors to bypass certain qualification steps. The related federal contract opportunity is for the repair of these NSNs, with quantities ranging from 2 to 17 units per item, and is restricted to qualified sources only.

View the file

Other files

File Type Posted
TRANSPORTATION DATA.pdf PDF
SPIRES.pdf PDF
SOW.pdf PDF
IUID.pdf PDF
FA825024R0505.pdf PDF
RDL.pdf PDF
CAVAF.pdf PDF
PWS.pdf PDF
PACKAGING REQUIREMENTS.pdf PDF
ITEM DESCRIPTION.pdf PDF
CDRLS.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPAIR QUALIFICATION REQUIREMENTS

NSN: 5840-01-483-0555

P/N: 1366839 Noun: Pulse Forming Network (PFN) Regulator Application: AN/TPS-75

3 Jun 2024 Section C 1/3

SECTION C:

1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE

a. Prequalification Notice: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this Pulse Forming Network (PFN) Regulator.

b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to repair, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

c. Data Verification: The offeror must verify that they have a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession including, at a minimum Raytheon (CAGE 2F259) drawing 1366840, USAF Technical Order 31P3-2TPS75-2-2 and associated documents.

The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.

d. Repair Process Verification: The offeror must repair this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 415 SCMS/GUMBB. The offeror shall also identify its sources for materials and its standards for internally used processes.

e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 415 SCMS/GUMBB for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by TO 31P2-2TPS75-2-2 table 6-43 which requires in system testing to verify correct function of the PFN Regulator.

f. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 30 days. This is based on complexity of the PFN Regulator and other factors.

g. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to

P/N: 1366839

3 Jun 2024 Section C 2/3 provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.

h. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract.

Once all requirements are met, the offeror will be listed as an approved repair source for this item. Approval, however, does not guarantee subsequent contract award.

P/N: 1366839

3 Jun 2024 Section C 3/3

2. SOURCE QUALIFICATION WAIVER REQUIREMENTS

Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:

a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).

b. QWC2: The potential source is qualified on the right-hand article and requests to be qualified on the left-hand article. If the right-and left-hand articles are mirror images of each other, then approval can generally be given.

c. QWC3: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.

d. QWC4: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.

e. QWC5: A source qualified to provide a similar or like item can be qualified to provide the required item. However, for approval, the engineering authority must verify that there is no increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written proof, such as purchase orders, shipping documents, etc., to show that the similar item was provided to the original equipment manufacturer or DoD.

f. QWC6: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification is currently with the requester and that the requester has the same or equivalent facilities, tooling, equipment, personnel, and utilizes the original forging, castings, etc., in the repair process.

NSN: 5996-00-572-1617

P/N: 345D585G01 Noun: Trigger Amplifier

13 Feb 2024 Section C 1/3 contracting office, of intent to qualify as a source for this Trigger Amplifier.

they have, or have access to, the required facilities and equipment to repair, inspect, test using AN/TPS-75 transmitter or equivalent, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

including change notices, in the offeror’s possession at a minimum Westinghouse (CAGE 89661) drawing 345D585, USAF Technical Order 31P3-2TPS75-2-2 and associated documents. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications. The offeror is responsible for obtaining all pertinent data, as well as understanding the requirements necessary to produce a like-new asset.

offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 415 SCMS/GUEA. The offeror shall also identify its submit to 415 SCMS/GUUEA for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by the drawings which require in-system testing to verify correct function of the Trigger Amplifier.

f. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified are $6,000.

g. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 30 days. This is based on complexity of the Trigger Amplifier and other factors.

P/N: 345D585G01

13 Feb 2024 Section C 2/3

h. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards

i. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved repair source for this item. Approval, however, does not guarantee subsequent contract award.

Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written

P/N: 345D585G01

13 Feb 2024 Section C 3/3 is currently with the requester and that the requester has the same or equivalent facilities, NSN: 5840015386564

P/N: 310377 Noun: Exciter, Radio Frequency Application: AN/TPS-75 Radar

9 Oct 2019 Section C 1/3 contracting office, of intent to qualify as a source for this Exciter, Radio Frequency.

they have, or have access to, the required facilities and equipment to repair, inspect, test using an AN/TPS-75 transmitter or equivalent, package and store the item . The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

including change notices, in the offeror’s possession including, at a minimum Raytheon Company (CAGE 1PYQ1) drawing 310377, USAF Technical Order 31P3-2TPS75-4. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.

offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Technical Order 31P3-2TPS75-2-2 which requires in system testing to verify correct function of the Exciter, Radio Frequncy.

the Exciter, Radio Frequency and other factors.

meet them before the date specified for award of the contract. The award will not be delayed

P/N: 310377

9 Oct 2019 Section C 2/3 to provide the vendor with an opportunity to demonstrate its ability to meet the standards be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved repair source for this item. Approval, however, does not guarantee subsequent contract award.

P/N: 310377

9 Oct 2019 Section C 3/3

Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written is currently with the requester and that the requester has the same or equivalent facilities, NSN: 5840-01-481-7460

P/N: 1366840 Noun: SF6 Tank Assembly

3 Jun 2024 Section C 1/3 contracting office, of intent to qualify as a source for this SF6 Tank Assembly.

they have, or have access to, the required facilities and equipment to repair, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

including change notices, in the offeror’s possession including, at a minimum Raytheon (CAGE 2F259) drawing 1366840, USAF Technical Order 31P3-2TPS75-2-2 and associated documents.

The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.

offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by TO 31P2-2TPS75-2-2 table 6-43 which requires in system testing to verify correct function of the PFN Regulator.

the PFN Regulator and other factors.

meet them before the date specified for award of the contract. The award will not be delayed to

P/N: 1366840

3 Jun 2024 Section C 2/3 provide the vendor with an opportunity to demonstrate its ability to meet the standards be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract.

Once all requirements are met, the offeror will be listed as an approved repair source for this item. Approval, however, does not guarantee subsequent contract award.

P/N: 1366840

3 Jun 2024 Section C 3/3

Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written is currently with the requester and that the requester has the same or equivalent facilities, NSN: 5430-01-079-8076

P/N: 353D663G01 Noun: Oil Tank Assembly Application: AN/TPS-75

27 Jul 2021 Section C 1/2

SECTION C:

1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE

a. Prequalification Notice: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this Oil Tank Assembly.

b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to repair, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

c. Data Verification: The offeror must verify that they have a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession including, at a minimum Northrop Grumman (97942) Drawing 353D663 and USAF Technical Order 31P3-2TPS75-4. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.

d. Repair Process Verification: The offeror must repair this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 415 SCMS/GUEA. The offeror shall also identify its sources for materials and its standards for internally used processes.

e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 415 SCMS/GUEA for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Northrop Grumman (97942) Drawing 353D663.

f. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified are $5,000.

g. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 30 days. This is based on complexity of the Oil Tank Assembly and other factors.

h. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the meet them before the date specified for award of the contract. The award will not be delayed

NSN: 5430-01-079-8076

P/N: 353D663G01 Noun: Oil Tank Assembly Application: AN/TPS-75

27 Jul 2021 Section C 2/2 to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.

i. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved repair source for this item. Approval, however, does not guarantee subsequent contract award.

2. SOURCE QUALIFICATION WAIVER REQUIREMENTS

Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:

a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).

b. QWC2: The potential source is qualified on the right-hand article and requests to be qualified on the left-hand article. If the right-and left-hand articles are mirror images of each other, then approval can generally be given.

c. QWC3: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.

d. QWC4: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.

e. QWC5: A source qualified to provide a similar or like item can be qualified to provide the required item. However, for approval, the engineering authority must verify that there is no increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written proof, such as purchase orders, shipping documents, etc., to show that the similar item was provided to the original equipment manufacturer or DoD.

f. QWC6: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification is currently with the requester and that the requester has the same or equivalent facilities,

RQR_0555
RQR_1617
RQR_6564
RQR_7460
RQR_8076