This document is a Repair Qualification Requirements (RQR) for the Trigger Amplifier with NSN 5996-00-572-1617 and P/N 345D585G01, which is used in the AN/TPS-75 system. The RQR outlines the qualification requirements that potential offerors must satisfy to become an approved repair source for this item. Key requirements include demonstrating the necessary facilities, testing and inspection capabilities, verification of the complete data package, and successful completion of the repair process verification and testing. The estimated cost for the qualification effort is $6,000, and the estimated completion time is 30 days. The RQR also provides details on potential source qualification waivers that may be granted under certain conditions. This RQR is related to a pre-solicitation for repair services on multiple NSNs, including the Trigger Amplifier, issued by the Department of the Air Force Materiel Command Air Force Sustainment Center.

View the file

Other files for this federal contract opportunity

Other files attached to Repair of Multiple NSNs, newest first.
File Type Posted
RQR_7460.pdf PDF
RQR_8076.pdf PDF
RQR_6564.pdf PDF
RQR_0555.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPAIR QUALIFICATION REQUIREMENTS

NSN: 5996-00-572-1617

P/N: 345D585G01 Noun: Trigger Amplifier Application: AN/TPS-75

13 Feb 2024 Section C 1/3

SECTION C:

1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE

a. Prequalification Notice: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this Trigger Amplifier.

b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to repair, inspect, test using AN/TPS-75 transmitter or equivalent, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

c. Data Verification: The offeror must verify that they have a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession at a minimum Westinghouse (CAGE 89661) drawing 345D585, USAF Technical Order 31P3-2TPS75-2-2 and associated documents. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications. The offeror is responsible for obtaining all pertinent data, as well as understanding the requirements necessary to produce a like-new asset.

d. Repair Process Verification: The offeror must repair this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 415 SCMS/GUEA. The offeror shall also identify its sources for materials and its standards for internally used processes.

e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 415 SCMS/GUUEA for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by the drawings which require in-system testing to verify correct function of the Trigger Amplifier.

f. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified are $6,000.

g. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 30 days. This is based on complexity of the Trigger Amplifier and other factors.

P/N: 345D585G01

13 Feb 2024 Section C 2/3

h. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.

i. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved repair source for this item. Approval, however, does not guarantee subsequent contract award.

2. SOURCE QUALIFICATION WAIVER REQUIREMENTS

Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:

a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).

b. QWC2: The potential source is qualified on the right-hand article and requests to be qualified on the left-hand article. If the right-and left-hand articles are mirror images of each other, then approval can generally be given.

c. QWC3: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.

d. QWC4: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.

e. QWC5: A source qualified to provide a similar or like item can be qualified to provide the required item. However, for approval, the engineering authority must verify that there is no increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written proof, such as purchase orders, shipping documents, etc., to show that the similar item was provided to the original equipment manufacturer or DoD.

f. QWC6: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification

P/N: 345D585G01

13 Feb 2024 Section C 3/3 is currently with the requester and that the requester has the same or equivalent facilities, tooling, equipment, personnel, and utilizes the original forging, castings, etc., in the repair process.