This document is a Statement of Work (SOW) for a Project Manager to support a $3.9 million Wildfire Prevention Grant Collection Agreement between the USDA-Forest Service, Angeles National Forest (ANF) and the Rivers and Mountains Conservancy (RMC). The Project Manager will be responsible for collaborating with project points of contact, maintaining stakeholder coordination, obtaining project status, and reporting on project progress and expenditures to meet RMC's quarterly reporting requirements. The period of performance is expected to begin on May 15, 2024 and continue through December 30, 2025. The Project Manager will focus on managing fuel reduction projects, invasive weed removal, and equipment purchases that support the Southern California Priority Landscape and the Wildfire Crisis Strategy. The SOW outlines two key tasks for the Project Manager: 1) Project Management, and 2) Project Reporting. The estimated hours for the Project Manager are up to 5 hours per week, with a total contract value to be determined based on the hourly rate.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Angeles National Forest

Statement of Work

Project Manager

Introduc on

The USDA-Forest Service, Region 5, Angeles National Forest (ANF) has a need for personnel with expertise in project management to provide support for the Wildfire Prevention Grant in the amount of $3.9 million dollars Collection Agreement with Rivers and Mountains Conservancy (RMC). The grant funding supports fuel reduction projects, invasive weed removal and purchase of equipment. This effort will support the Southern California Priority Landscape and make an investment of fuels projects for the Wildfire Crisis Strategy. Projects being implemented are with contractors and non-governmental partners. For timely reporting of expenditure of funds to RMC and coordination of our partners to work on projects, is in part dependent of a qualified professional project manager with experience in management of National Forest System lands.

Period of Performance: Work under this contract is expected to begin May 15th, 2024 and continue through December 30th, 2025.

Background

On May 16, 2022 the RMC Board awarded the Angeles National Forest a Wildfire Prevention Grant of

2.6 million dollars. Also, in the last month RMC awarded an additional 1.4 million dollars for additional fuels projects and for purchase of equipment. The funds have been put into a collection agreement which needs to be monitored and reporting to RMC needs to be done quarterly. POC’s for the projects are on the districts and the POC for the agreement is in the headquarters.

Project Description

The Contractor will be required to provide the services as described below in a collaborative, professional and responsive manner.

Task 1 – Project Management

Collaborate with project POC’s on the San Gabriel Mountains National Monument and the Los Angeles Gateway Ranger District to obtain information and ensure timelines are being met for completion of projects.

o Fuels Projects Tanbark Fuelbreak Maintenance Chilao Hazard Fuels Reduction Charlton Fuels Reduction Project Tanbark Admin Site and Fuelbreak Invasive Weed Treatment o Maintain stakeholder coordination and communication with the Tanbark Invasive Weed

Treatment Project.

Set mileposts for invasive weed projects and ensure timelines are met.

o Obtain status checks as needed for all Fuels Projects.

o Inform POC in headquarters of project timelines that need to be adjusted.

Maintain an RMC folder with project information as needed.

Task 2 – Project Reporting

A big part of this workload is centered around making sure we are meeting reporting requirements for Rivers and Mountains Conservancy (RMC). The project manager would need to facilitate and coordinate discussions with the POC’s to obtain the information needed for the reporting requirements.

o Determine progress against program objectives.

Evaluate project performance in regards to cost.

o Reports include Exhibit P – Progress Report and Exhibit Q – Expenditure Projection Report. Write a narrative (paragraph) describing the summary of activities for the previous reporting period.

Monitoring and Reporting will include expenditures of chippers, convection oven and water buffalo.

o Write a description of activities and accomplishments of each task shall be in sufficient detail to provide a basis for payment of invoices and shall be translated into percent of task work completed for the purpose of calculating invoice amounts. This would include activities undertaken and accomplishments of each task during the quarter, milestones achieved, and any problems encountered in the performance of the work under the Agreement.

o Ensure reports meet quarterly deadlines.

o Maintain folder of reports and narrative summary’s.

FINANCIAL PLAN

SUMMARY

Need this person to work up to 5 hours/week, but bill to only according to work performed.

Budget:

Project Coordinator

$Total Amount = Cost per/hour X 5 hours/week X 88 week periods

Work Schedule

Task 1 88 hours As calculated in $Total Amount above

Travel Lodging and Mileage, 1 trip/month as needed. Estimate of cost of $5,000.

88 hours Total