Rock_TA50_53_Quantity_and_Delivery_Directions.pdf
PDF 109 KB Posted
- Attached to
- 2" Road and 6-12" Rip Rap Federal contract opportunity
- Solicitation number
- RileyDPTMSTLD003
- Issued by
- Department of the Army
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FY18_RockContract3_TA50_53_map.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2” Road Rock
1050 ton of 2” Road Rock. Deliver Road Rock to Training Area 50 (See Attached map) at Fort Riley, Kansas
Request Delivery NLT 18 April 2018.
2” Road Rock
2200 ton of 2” Road Rock. Deliver Road Rock to Training Area 53 (See Attached map) at Fort Riley, Kansas
Request Delivery NLT 18 April 2018.
6-12” Rip Rap
650 ton of 6-12” Rip Rap delivered to Training Area 50 (See Attached map) Fort Riley, Kansas
Request Delivery NLT 18 April 2018
6-12” Rip Rap
550 ton of 6-12” Rip Rap delivered to Training Area 53 (See Attached map) Fort Riley, Kansas
Request Delivery NLT 18 April 2018
Due to training exercises, the delivery route will have to be traveling north on Old Hwy77 going past the Estes Gate heading north. Once on the installation make a left on the first tank trail. Head west approximately 2.5 miles –
Make a left turn at the tank trail intersection and head north approx. 1.2 miles to TA50 delivery location will be vicinity of T-intersection. See map for details and delivery location
The second delivery location head east on tank trail at TA50 delivery location approx. one half mile take left turn onto tank trail - Head north for approx.. 1 mile take left turn. Head west approximately one half mile - TA53 delivery location will be on the right. See map for details and delivery location.
Be aware that there is possibility of heavy track vehicle traffic on tank trails