RHBRT - Draft QMP Rev 1.0 (1), 10-30-2026.pdf
PDF 837 KB Posted
- Attached to
- Construction of the Richmond Highway BRT Project
- Solicitation number
- RFA-131103
- Issued by
- Fairfax County, Virginia
About this file
This document is a Quality Management Plan (QMP) Version 1.0 for the Richmond Highway Bus Rapid Transit (BRT) Project, prepared by the Fairfax County Department of Transportation (FCDOT) in coordination with the Virginia Department of Transportation (VDOT). The QMP establishes comprehensive quality management procedures and organizational responsibilities for the design, procurement, construction, installation, testing, and acceptance of the 6.7-mile dedicated transit guideway project in the median of Richmond Highway, plus a 0.7-mile mixed traffic segment on North Kings Highway. The project includes nine BRT stations, streetscape and intersection improvements, sidewalks, bicycle facilities, and modification of an existing maintenance facility. The project is divided into two sections: Section 1 extends 3.6 miles from Huntington Metro Station to Hybla Valley, and Section 2 extends 3.8 miles from Hybla Valley to Fort Belvoir. The QMP applies to all project staff, consultants, contractors, and suppliers and incorporates Federal Transit Administration (FTA) quality standards and industry best practices. No specific response dates, due dates, bidders' conferences, or award dates are provided in this QMP document, which serves as a foundational policy and procedural framework rather than a procurement solicitation.
The QMP establishes a quality management system governed by the FCDOT Director with oversight delegated to an Independent Quality Assurance Manager (IQAM) who reports directly to leadership. Primary project entities include the Project Management Consultant (led by STV Inc. and RK&K), an Independent Quality Assurance/Verification Sampling & Testing Contractor, construction contractors, and VDOT. The document references compliance with the FTA Quality Management System Guidelines (October 2019 Edition), VDOT Road and Bridge Specifications, and Fairfax County standards. Quality procedures address design control, document management, purchasing requirements, product identification and traceability, process control, inspection and testing, equipment calibration, nonconformance reporting, corrective actions, quality audits, and staff training. The plan requires all consultants and contractors to develop project-specific QA/QC plans conforming to FTA guidelines and this QMP. Funding sources, contract amounts, pricing terms, and specific procurement set-asides are not addressed in this QMP document, which focuses exclusively on quality management policies and procedural requirements throughout all project phases.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fairfax County Department of Transportation
Richmond Highway Bus Rapid Transit
QUALITY MANAGEMENT PLAN
for
Version 1.0
October 2026
RICHMOND HIGHWAY BRT PROGRAM
Quality Management Plan ii
Contents
1. MANAGEMENT RESPONSIBILITY
1.1 Purpose
1.2 Scope
1.3 Responsibilities
1.3.1 FCDOT Director
1.3.2 FCDOT Deputy Director
1.3.3 Independent Quality Assurance Manager (IQAM)
1.3.4 Project Management Consultant (PMC)
1.3.5 Independent Quality Assurance/Verification Sampling & Testing (IQAVS&T) Contractor
1.3.6 Construction Contractor
1.3.7 Virginia Department of Transportation (VDOT)
2. QUALITY MANAGEMENT SYSTEM
2.1 Purpose
2.2 Scope
2.3 Quality Improvement and QMP Updates
2.4 Standards and Reference Materials
3. DESIGN CONTROL AND REVIEW PROCESS
3.1 Purpose
3.2 Scope
3.3 Responsibility
3.4 Design Input Procedures
3.4.1 Design Criteria
3.4.2 Background Information and Other Design Input
3.4.3 Data Collection and Field investigation
3.5 Design Quality Review Procedures
3.5.1 Project Responsibilities
3.5.2 Project Stakeholder Reviews
3.6 Configuration Management Procedures
4. DOCUMENT CONTROL
4.1 Purpose
4.2 Scope
4.3 Procedure
4.4 Controlled Project Quality Documents
iii
5. PURCHASING
5.1 Purpose
5.2 Scope
5.3 Procedure
6. PRODUCT IDENTIFICATION AND TRACEABILITY
6.1 Purpose
6.2 Scope
6.3 Procedure
7. PROCESS CONTROL
7.1 Purpose
7.2 Scope
7.3 Procedure
8. INSPECTION AND TESTING
8.1 Purpose
8.2 Scope
8.3 Procedure
8.4 VDOT References
9. INSPECTION, MEASURING, AND TEST EQUIPMENT
9.1 Purpose
9.2 Scope
9.3 Procedure
10. INSPECTION AND TEST STATUS
10.1 Purpose
10.2 Scope
10.3 Procedure
11. NONCONFORMANCE
11.1 Purpose
11.2 Scope
11.3 Procedure
11.4 Definitions
11.5 Stop Work
12. CORRECTIVE ACTION
12.1 Purpose
12.2 Scope
12.3 Procedure
13. QUALITY RECORDS
iv
13.1 Purpose
13.2 Scope
13.3 Procedure
14. QUALITY AUDITS
14.1 Purpose
14.2 Scope
14.3 Schedule
14.4 Audit Procedure
14.5 Audit Records
15. TRAINING
15.1 Purpose
15.2 Scope
15.3 Procedure
15.4 Quality Training and Staff Development
LIST OF FIGURES
Figure 1: Project Quality Organization Chart (Outlining Contractual Quality Management)
APPENDICES
Appendix A – Definitions .................................................................................................................................. A v
REVISION INDEX
Rev. # Description Issue Date
0.0 New Document August 2022
0.1 Revised Document November 2022
0.2 Revised Document February 2023
0.3 Revised Document March 2023
0.4 Submitted for Approval June 2023
0.5 Engineering 90-day revisions September 2024
0.6 Updates based on PMOC coordination March 2025
0.7 Focus on Assurance Activities, Modify Quality
Structure. Sent to PMOC For review
August 2025
0.8 Update based on discussions with PMOC, submitted for FCDOT review
April 2026
0.9 Draft for PMOC review August 2026
1.0 Updated based on PMOC Comments October 2026
vi
QUALITY MANAGEMENT PLAN (QMP) REVIEW & APPROVALS PAGE
QMP Revision 1.0
QMP Revision Date [Pending PMOC Review]
FCDOT Director Gregg Steverson, PE, PTOE
QMP Originator
FCDOT Independent Quality Assurance Manager (IQAM)
Paul Elman, PE Date of Signature Sign Here
FCDOT Special Projects Division Chief
Yuqing Xiong Date of Signature Sign Here
FCDOT Director Gregg Steverson, PE, PTOE
Date of Signature Sign Here vii
ACRONYMS
The following acronyms are used within this document or in documents referenced within this Quality Management Plan.
BRT Bus Rapid Transit
BOA Basic Ordering Agreement
FCDOT Fairfax County Department of Transportation
FTA Federal Transit Administration
IQAM Independent Quality Assurance Manager
OP Operating Procedures
PMC Program Management Consultant
PMP Project Management Plan
PMOC Program Management Oversight Contractor
QA Quality Assurance
QC Quality Control
QCM Quality Control Manager
QMP Quality Management Plan
QCR Quality Control Reviewer
RP Responsible Professional
VDOT Virginia Department of Transportation viii
Project Quality Policy Statement
It is the mission of FCDOT that the Richmond Highway Bus Rapid Transit Project (Project) is planned and conducted to meet Federal Transit Administration (FTA) requirements and industry standards for quality under the purview of an effective quality program. FCDOT supports this mission with the development of the Quality Management Plan (QMP) that defines goals and objectives, specifies quality related activities and indicators, and assigns responsibilities for meeting and carrying out those objectives and activities. The
QMP provides the framework for assuring the quality of products and services through all phases of the program, including design, procurement, construction, installation, testing, and acceptance.
The QMP and associated quality procedures will apply to all project-related work such that it meets the required quality control and assurance standards established by FTA. Additionally, the QMP will:
• Address program objectives at various points in the project lifecycle related to activities associated with design, document control, procurement, construction, start-up, and operations as required
• Establish compliant quality policies, procedures, training, and documentation for all Project staff and to demonstrate compliance with QMP elements throughout the Project
Project Management will distribute copies of the QMP to all Project team members who must comply with the production, review process, and quality procedures described herein. Each Project team member must understand the project objectives, apply sound principles, and produce work that meets industry standards.
Project Description
The Project will operate in a dedicated (semi-exclusive) transit guideway in the median of Richmond
Highway for 6.7 miles and in mixed traffic for the 0.7-mile segment on North Kings Highway. The Project includes construction of new BRT-dedicated lanes in the median of the roadway, nine BRT stations, streetscape and intersection improvements, construction of sidewalks and bicycle facilities, and the modification of an existing maintenance facility for the BRT vehicles. The northern section of the Project
(referred to as Section 1) extends for 3.6 miles from the Huntington Metro station to Hybla Valley; the southern section (Section 2) extends 3.8 miles from Hybla Valley along Richmond Highway to Fort Belvoir.
1. MANAGEMENT RESPONSIBILITY
The quality management team is committed to providing a high level of quality for the Richmond Highway Bus Rapid Transit Project (Project). This section describes staff organization and responsibilities for quality activities in more detail.
1.1 Purpose
This section identifies the responsibility for developing, approving and implementing procedures for executing the Quality Management Plan (QMP) and satisfying project quality objectives. The QMP provides the framework for quality management of the Project, detailing specific objectives and procedures where appropriate. This QMP establishes requirements for the development, preparation, verification, and implementation of program and design documents, and for all activities that support the ultimate delivery of the Project. The QMP is prepared for Fairfax County Department of Transportation
(FCDOT) by the Independent Quality Assurance Manager (IQAM).
1.2 Scope
Several government agencies, consultants, and contractors comprise the Project staff, as described in the
Project’s Project Management Plan (PMP), and includes staff from:
• FCDOT
• Virgina Department of Transportation (VDOT)
• Project Management Consultant (PMC)
• Independent Assurance / Verification Sampling & Testing (IQAVS&T) Contractor
• Other consultants and contractors
The PMP defines the organizational approach, including the organizational structure and position descriptions. The project organization is structured to meet the project’s unique requirements. The PMP is maintained in the document control system. The QMP is a subplan of the PMP.
Each organization is responsible for achieving its own quality. However, FCDOT will maintain quality assurance (QA) oversight capability to ensure that the QMS and supporting plans/procedures are working and being implemented accordingly at the agency itself and within consultant, contractor, and supplier organizations. Section 1.3, Responsibilities defines the interrelation of each organization’s QA/QC Plan and this QMP in the execution of the Project’s quality program.
The Project quality program is structured and functions in such a manner that:
• QC is achieved and maintained by those who have been assigned responsibility for performing the work.
• People or organizations charged to verify quality are not directly responsible for performing the work.
• The organization responsible for QA/QC has the authority, access to work areas, and organizational freedom to the following: identify QC problems, verify the implementation of solutions, and verify that further processing, delivery, or installation is controlled until proper disposition of a deficiency, nonconformance, or unsatisfactory condition has occurred.
• Quality verification functions will report to a level of management that provides sufficient authority and leverage to verify appropriate action is taken to resolve conditions adverse to quality.
• FCDOT, the IQAM, and management of the organizations implementing the project QA/QC plans will assess the adequacy and effectiveness of the quality program annually.
• Audits performed by the IQAM will assess conformance to the plans.
• Management of quality control specific to the construction phase is detailed in the Project
Construction Quality Procedures (CQP).
1.3 Responsibilities
The responsibility for and commitment to quality begins with FCDOT Leadership, which includes the
FCDOT Director and FCDOT Deputy Director. The FCDOT Director has delegated the responsibility for establishing and implementing the QMP for the Project to the IQAM. All FCDOT project staff have an expectation of upholding quality standards as it pertains to their scope of work. Figure 1 shows an organization chart for project quality. The full project organization chart is included in the PMP.
1.3.1 FCDOT Director
The FCDOT Director is the public official responsible and accountable for implementing the project per federal and state requirements using sound management practices. Related to the project, the FCDOT
Director reports administratively to the BRT Executive Committee, which reports to the Fairfax County
Board of Supervisors. The FCDOT Director has delegated the responsibility for establishing and implementing the QMP for the Project to the IQAM. The FCDOT Director is responsible for approving the
QMP.
1.3.2 FCDOT Deputy Director
The FCDOT Deputy Director is assisting the FCDOT Director to oversee the Project. The FCDOT Deputy
Director may fulfill Project responsibilities of the FCDOT Director as delegated by the FCDOT Director, including oversight of the Project quality program and coordination with the IQAM.
1.3.3 Independent Quality Assurance Manager (IQAM)
The IQAM reports directly to the FCDOT Director and is responsible for the development and implementation of the QMP. This includes administration of the QMP, training staff in implementing the
QMP, monitoring compliance and evaluating the effectiveness of staff in implementing QMP, and conducting Quality Audits of consultants, suppliers, internal processes/procedures, contractors, and others providing professional services to the Project.
IQAM monitors the responsibilities of consultants, contractors, and suppliers pertaining to quality management and quality systems. The IQAM reviews the consultants’ and contractors’ QA/QC plans for conformance with the QMP and the FTA’s Quality Management System Guidelines (2019). All consultants and contractors for the Project have direct responsibility for QA/QC activities as they pertain to the scope requirements within each contract. The IQAM will conduct reviews of project-specific
QA/QC plans according to the RHBRT Project-Specific QA/QC Plan Review procedure.
The IQAM verifies that the program staff including FCDOT, PMC and all consultants and contractors involved in the Project conform to the requirements for quality assurance contained in this QMP. The
IQAM will be responsible for updates to the QMP as the project progresses through design into construction and operations. The IQAM will verify that all Project entities schedule trainings, coordinate audit activities Project-wide, and establish and maintain accurate quality records.
The IQAM will perform ongoing audits (both scheduled and unscheduled) of the Project process and procedures, detailed in Chapter 14.
The organizational chart in Figure 1 demonstrates that the IQAM reports directly to the FCDOT
Leadership.
1.3.4 Project Management Consultant (PMC)
The PMC, led by STV Inc. and RK&K, provides project management, design and specification, and construction management services to FCDOT in delivery of the Project. The PMC’s detailed scope of work is available in contract and/or plan of work documents.
The PMC will develop and maintain a project-specific quality assurance and quality control (QA/QC) plan that incorporates the requirements of this QMP and the FTA’s QMS guidelines. The PMC QA/QC plan must identify the quality manager who has the responsibility to initiate action to prevent quality problems, to identify and record quality problems, to initiate solutions through appropriate channels, and to verify implementation of solutions to quality problems. The quality manager must be functionally independent of those having direct responsibility for the work being performed.
The PMC is providing both design and construction services. Each phase has distinct and unique needs.
PMC will be providing quality control inspection and testing during construction.
The IQAM will provide oversight for the development and implementation of the PMC QA/QC plan(s), including plan approval and audits.
1.3.5 Independent Quality Assurance/Verification Sampling & Testing (IQAVS&T) Contractor
The IQAVS&T Contractor will perform independent inspections and material testing during construction, supporting quality assurance during construction. The Project has not yet procured the IQAVS&T
Contractor. The contract scope of work will be available upon notice to proceed.
The IQAVS&T Contractor will develop and maintain a project-specific quality assurance and quality control (QA/QC) plan that incorporates the requirements of this QMP and the FTA’s QMS guidelines. The
IQAVS&T Contractor QA/QC plan must identify the quality manager who has the responsibility to initiate action to prevent quality problems, to identify and record quality problems, to initiate solutions through appropriate channels, and to verify implementation of solutions to quality problems. The quality assurance manager must be functionally independent of those having direct responsibility for the work being performed.
The IQAM will provide oversight for the development and implementation of the IQAVS&T Contractor
QA/QC Plan, including plan approval and audits.
1.3.6 Construction Contractor
The Construction Contractor develops and maintains a project-specific quality assurance and quality control (QA/QC) plan that incorporates the requirements of this QMP and the FTA’s QMS guidelines. The
Construction Contractor’s plan must identify the quality manager who has the responsibility to initiate action to prevent quality problems, to identify and record quality problems, to initiate solutions through appropriate channels, and to verify implementation of solutions to quality problems. The quality assurance manager must be functionally independent of those having direct responsibility for the work being performed.
The IQAM will provide oversight for the development and implementation of the IQAVS&T Contractor
QA/QC Plan, including plan approval and audits.
1.3.7 Virginia Department of Transportation (VDOT)
VDOT will follow VDOT Road and Bridge Specifications Manual (most recent version available unless otherwise noted in the approved plan sheets) for quality procedures during construction for the scope of work to construct the widening of Richmond Highway in Section 2 and the BRT lanes in segments A, B, and C of Section 2. The Nonconformance and Corrective Action procedures developed for the Project (as defined in this QMP) will also apply to VDOT. These two elements are not specified in other VDOT specifications.
Figure 1: Project Quality Organization Chart (Outlining Contractual Quality Management) https://www.vdot.virginia.gov/doing-business/technical-guidance-and-support/technical-guidance-documents/road-and-bridge-specifications/
2. QUALITY MANAGEMENT SYSTEM
The Project’s quality management system (QMS) has been developed per requirements from the Project and FTA’s QA/QC guidelines. The QMS includes the following:
• The Project Management Plan (PMP);
• The Project Quality Management Plan (QMP);
• The Project Construction Quality Procedures (CQP);
• Quality requirements;
• Quality documentation;
• Inspection and testing procedures;
• Quality audit procedures (refer to Section 14);
• Quality records (refer to Section 13);
• Nonconformance and corrective action procedures;
• Consultant and Contractor QA/QC plans; and
• Training procedures (refer to Section 15).
2.1 Purpose
This section describes the QMS requirements for FCDOT transit projects and assigns responsibility for developing, approving, and implementing quality procedures for the Project.
2.2 Scope
These QMS requirements apply to all project staff, consultants, and contractors who perform activities that affect quality. Project staff, consultants, and contractors must use the appropriate project forms, where applicable, to document and monitor the quality of work.
The primary consultants, contractors, and other contracted entities must develop a project-specific
QA/QC plan, conforming to the FTA’s QMS guidelines, this Project QMP, and additional requirements as determined by their individual contracts. The QA/QC plan requirements will be specified in the individual contract. The prime contract holder will submit the QA/QC plan to the IQAM for review and acceptance.
Documented procedures must include the purpose and scope of each activity; identify the responsible actors; reference the applicable codes, standards or specifications; specify testing and inspection requirements; and identify the quality records that result from the described activity.
FCDOT may enter into cooperative agreements during the project lifetime with other government agencies to perform specific functions and activities for the Project. Generally, the oversight of these agencies will occur through regular meetings with agency staff and periodic site visits. Where these agencies produce specific products, FCDOT or one of its consultants will review the product. Agreements are developed between the FCDOT and partner agencies to identify scopes of work and each party’s responsibility for quality.
2.3 Quality Improvement and QMP Updates
Quality improvement involves identifying opportunities for improvement of the QMS for the services rendered by all entities for the Project.
The QMS should be evaluated for effectiveness, based on IQAM continuous feedback, internal or external audit results, comments received on deliverables, and other issues that may be identified during the annual review of the QMS.
The QMS will be updated to improve the system as necessary throughout the Project delivery to reflect any changes determined necessary.
Managers participate in quality improvement through discussions of quality issues during monthly discipline coordination meetings. Best practices are identified during those meetings, incorporated into the QMS, and distributed to the project team.
2.4 Standards and Reference Materials
This QMP has been prepared based on quality standards and reference materials, including the following:
• FTA Quality Management System Guidelines (October 2019 Edition)
• FTA Oversight Procedure 24 – Quality Assurance/ Quality Control Review
• Project Management Plan (PMP)
• Fairfax County Department of Transportation Engineering Proposal Document, January 2020
• Fairfax County Purchasing Resolution, July 2024
• Richmond Highway BRT Program Basis of Design Report, January 2022
• Virginia Department of Transportation Road and Bridge Standards
• Virginia Department of Transportation 2020 Road and Bridge Specifications
• Virginia Department of Transportation 2022 Supplement to the VDOT 2020 Road and Bridge
Specifications, December 31, 2021
• Virginia Department of Transportation Test Methods, August 2022
If, at any point during the Project lifecycle, additional specific standards or reference documentation is required, the Discipline Lead must identify the pertinent Standard, Specification, or Reference Document and submit it to Project Leadership for review and approval. Fairfax County and VDOT standards will be supplemented by additional standards that meet FTA quality requirements. The IQAM will verify FCDOT follows their established process for implementing these changes.
https://stvinc.sharepoint.com/sites/4018542/Shared%20Documents/Forms/AllItems.aspx?id=%2Fsites%2F4018542%2FShared%20Documents%2F01%20Program%20Management%2F1%2E10%20Task%20Orders%2FTask%2019%20%2D%20Entry%20into%20Engineering%20and%20Pre%2DFinal%20Design%2FFCDOT%20Eng%20Proposal%20Document%2FFCDOT%20Engineering%20Proposal%20Document%2D%20January%202020%20Update%2Epdf&parent=%2Fsites%2F4018542%2FShared%20Documents%2F01%20Program%20Management%2F1%2E10%20Task%20Orders%2FTask%2019%20%2D%20Entry%20into%20Engineering%20and%20Pre%2DFinal%20Design%2FFCDOT%20Eng%20Proposal%20Document https://www.fairfaxcounty.gov/procurement/sites/procurement/files/assets/documents/2024%20Purchasing%20Resolution.pdf https://stvinc.sharepoint.com/sites/4018542/Shared%20Documents/Forms/AllItems.aspx?id=%2Fsites%2F4018542%2FShared%20Documents%2F10%20Project%20Delivery%20%26%20Funding%2F10%2E2%20New%20Starts%20Submittals%2FBasis%20of%20Design%2F2022%2E01%2E14%5FBasis%20of%20Design%20Report%2Epdf&parent=%2Fsites%2F4018542%2FShared%20Documents%2F10%20Project%20Delivery%20%26%20Funding%2F10%2E2%20New%20Starts%20Submittals%2FBasis%20of%20Design http://vdot.virginia.gov/business/locdes/Standards_CompleteSections.asp https://www.virginiadot.org/business/resources/const/VDOT_2020_RB_Specs_acc071522.pdf https://www.virginiadot.org/business/resources/const/2022Supplement_to_the_2020SpecBook_acc071522.pdf https://www.virginiadot.org/business/resources/const/2022Supplement_to_the_2020SpecBook_acc071522.pdf https://www.virginiadot.org/business/resources/Materials/bu-mat-VTMs.pdf
3. DESIGN CONTROL AND REVIEW PROCESS
3.1 Purpose
This section establishes the standards used for the development, preparation, verification, and delivery of the design documents that make up the engineering and architecture deliverables for the Project.
3.2 Scope
This plan applies to all personnel developing, preparing, reviewing, and approving project submittals and deliverables. All design documents prepared by the PMC and its subconsultants will follow quality control procedures outlined in the PMC’s QA/QC plan.
The documents that the Project will produce with contracted services, include environmental documentation, construction documents (plans, specifications, cost estimates, schedules, the calculations and technical studies supporting the construction documents, and as-built drawings), technical specifications for the BRT vehicles and the fare collection system, design efforts supporting construction including answers to Request for Information, Nonconformance Report (NCR), and Change Orders (COs), the safety certification program, and design activities delegated to the contractors, fabricators, manufacturers, suppliers and vendors (including shop drawings, systems design, software development, management plans and systems integration testing plans).
It should be noted that utility companies and other similar companies are responsible for their QA/QC procedures unless explicitly stated otherwise in plan documents. However, all entities involved in the
Project must adopt quality assurance standards that meet the standards in this QMP.
The PMC will identify their quality assurance manager responsible for verifying and documenting that the elements of their project-specific QA/QC plan are functioning as intended and that the requirements are being performed in accordance with the plan.
The Project has developed a design criteria, detailed below, that includes standards and codes to ensure compatibility between design standards and quality standards. Project design documents will be checked for compliance with the design criteria by FCDOT discipline leads and stakeholder reviewers.
3.3 Responsibility
Senior FCDOT Management team assigns responsibility for implementing and maintaining the design control to FCDOT Division Chiefs and their management of the PMC and other entities providing design and construction services to the project.
The IQAM will periodically (as defined in Chapter 14 Quality Audits) perform independent audits of the
QC documents submitted to document control to verify the QC process for each deliverable adheres to the QMP.
3.4 Design Input Procedures
The design for the Project is guided by the FCDOT RFP Materials, and the Basis of Design Report and established federal, state, and local design standards and requirements as outlined in detail within the following sections.
3.4.1 Design Criteria
The Basis of Design Report provides a summary of the design criteria, considerations, and assumptions on which the design is developed. County, State, and Federal design specifications are referenced in the Basis of Design Report. The Fairfax County Engineering Proposal Document for the Project must also be followed in preparing the design documents. During the QC process, the design plans are reviewed against the design criteria.
Project stakeholders both internal and external to FCDOT are involved in the design process from the preliminary engineering through final design, construction, and operation phases. These partnering agencies/entities include the Fairfax County Transit Division (service provider of Connector), VDOT, and
WMATA. Their input is incorporated into the design criteria and process outlined in the Basis of Design
Report.
3.4.2 Background Information and Other Design Input
Discipline Leads collect background information and base data. This information and data include land surveys, geotechnical, natural, and cultural resources, historic fabric, hazardous materials, utility locations, verification of as-built information, building foundation location, and traffic data. Each data collection effort or field investigation activity is planned and documented per the design criteria. Other design inputs include:
• Design Methodology
• Design Assumptions
• Design Calculations
• Data Collection
Background data and methods used to collect the data will be controlled to protect the quality of the data used in the design process. The PMC Discipline Leads will be responsible for the determination of the quality requirements and standards that must be adhered to by the entities who perform data collection for the Project. The standards will consist of FCDOT, VDOT, and industry accepted requirements and be specified in the contract documents.
Changes that result from a change in design input such as design methodology or assumptions require more than revision of drawings and must be documented and communicated in the system per document control procedures provided in Section 4. The original reviewer or approver of methodology or assumptions must review and approve any changes. This responsibility is assigned to the project position or organization, not the specific person.
3.4.3 Data Collection and Field investigation
Data collection and field investigation plans are the responsibility of the discipline lead responsible for the data collection and/or field investigations. Data Collection and Field Investigation Plans will be completed per the Basis of Design Report and the Fairfax County Engineering Proposal Document. The Investigation and Testing Plan is included in Section 3.7 of the PMP.
3.5 Design Quality Review Procedures
3.5.1 Project Responsibilities
Contractors and subconsultants will be required to include procedures for control of data in their QA/QC plans and will be fully responsible for providing the data that conforms to the requirements established by the primary contract’s QA/QC plan. These procedures must be sufficient to provide confirmation and documentation that the incorporated data meets the Project’s QMP requirements.
Contractors and subconsultants are also required to perform quality assurance of all design documents submitted to FCDOT for review, according to the primary contract’s QA/QC plan.
After each design phase, the IQAM will conduct an audit of that phase’s QC activities. The quality audit will evaluate if the design contractor followed QC procedures. The IQAM will have access to how public outreach and stakeholder coordination informed the design. The QMP will focus on the following design milestones:
• 30% design documents
• 60% design documents
• 80% design documents
• 100% final design plans
3.5.2 Project Stakeholder Reviews
Design documents submitted to FCDOT, and other approving authorities or agencies will be subjected to a project stakeholder review based on the type of deliverable. IQAM will verify that comments provided through stakeholders are tracked, responded to appropriately and are addressed in subsequent submittals.
Reviewers of design documents shall consider constructability, usability, operability, safety, and maintainability. This review will be conducted in the form of one or multiple interdisciplinary workshop(s) in coordination with FCDOT and partnering agencies to include the comment review and disposition resolution process. The constructability review will be led by the PMC and include the design team and construction contractor groups. Details pertinent to the constructability review will be updated with appropriate information during the Engineering phase of the project. Operations and maintenance reviews will include the ultimate operator, the FCDOT Transit Services Division Operations and Maintenance Division. FCDOT will use a project-specific constructability review checklist developed by the PMC (included in the Constructability Review Report).
Agency and departmental stakeholders included in Project Stakeholder review include:
• VDOT
• WMATA
• Fort Belvoir
• FCDOT -Transit Services Division Operations and Maintenance Division
• Fairfax County Department of Public Works and Environmental Services (DPWES), Maintenance and Stormwater Management Division (MSMD)
3.6 Configuration Management Procedures
To ensure project integrity, all physical and technical elements will be consistently defined and documented throughout the project lifecycle. Once a baseline is established, configuration management will govern the systematic evaluation, coordination, and formal approval or rejection of any proposed changes. Configuration control procedures are detailed in Section 3.5 of the PMP.
The following protocols will be maintained:
• All project drawings will be assigned a unique identification number.
• Specifications will adhere to a standardized format to ensure consistency.
• Comprehensive drawing lists will track revision history, including status updates and effective dates.
• Permanent records of all contract documents and a complete historical log of project changes will be maintained.
• The current approval status of the evolving design will be clearly identified and accessible to all relevant project personnel.
4. DOCUMENT CONTROL
4.1 Purpose
This section establishes the procedures and requirements for the systematic control of project documents developed during design and construction.
4.2 Scope
These requirements apply to staff or consultant/contractor prepared design and construction documents issued as Project documents. Document control applies to the systematic and controlled approval, release, revision, reproduction, distribution, maintenance, retention and disposition of project documents. Documents can include but are not limited to plans, contracts, specifications, quality records, procedures, etc.
Document controls are enacted so that project documents can be located and made available upon request.
4.3 Procedure
Procedures have been developed in the Document Control and Record Retention Plan for the following:
• Document Naming Conventions;
• Version Control;
• Incoming Documents;
• Outgoing Documents;
• Hard Copy Documents;
• Confidential Documents;
• Emails; and
• Other Project Documents.
The purpose of the Document Control and Record Retention Plan is to establish a process whereby project related documents are reviewed, approved, distributed, and archived in a consistent and controlled manner. Controlled documents are defined as ones that have been prepared, reviewed, and approved by authorized personnel.
Records shall be established and maintained throughout the Project to provide evidence of conformity to the requirements of the contract, and to the effectiveness of the overall quality management system.
Records shall be legible, readily identifiable, and available. A documented procedure defines the controls needed for document storage and retention time.
Project staff will be responsible for document and records control within their work scopes. Their documents are subject to audit by the IQAM and/or an independent auditor. Audits (including the development of the audit check lists) will be based on the policies and procedures defined in the
Document Control and Record Retention Plan. The audit procedure will follow the process detailed in
Chapter 14.
4.4 Controlled Project Quality Documents
Controlled project quality documents and records include, but are not limited to, the following:
• Quality Processes and Plans:
o Quality Management Plan o Audit Schedules o Audit Plans
• PMC and Other Consultant/Contractor Quality Records:
o Project Deliverables/Basis of Design o Comment Resolution Sheet o Comment Response Summary o Daily Work Records o Detail Check Records o Nonconformance Report o Technical Review Records o Summary Reports and Evaluations o Corrective or Preventative Action Plan
The IQAM will generate the following as part of independent quality assurance reviews and which will be stored as quality records as part of project document control:
• IQAM Quality Records:
o Audit Reports o Audit Report Log o Deficiency Log o Training Records o Minutes of Quality Management Review Meetings o Monthly Quality Reports o Nonconformance Log
All controlled documents will follow the same processes and procedures for storing, controlling, distributing, reviewing, retaining, and maintaining documents, records, drawings, and data, as described in the Document Control and Record Retention Plan. The IQAM will verify through quality assurance and/or audit that entities are complying with the Document Control and Record Retention Plan.
5. PURCHASING
5.1 Purpose
This section outlines the requirements of the QMS to be incorporated into procurement documents.
5.2 Scope
The requirements of this section apply to all major procurement, installation, and construction activities for the project. Project staff, project partners, consultants, and contractors are responsible for providing QA/QC in accordance with approved QA/QC plans and contracts, as applicable. Where additional clarification or guidance is necessary to determine the intent or requirement of any particular procedure, reference shall be directed to the FTA Circular 4220.1G and the FTA Best Practices Procurement and Lessons Learned Manual.
5.3 Procedure
The FCDOT Director or designee will have the responsibility to identify the need for and initiate all procurements of professional/technical services and construction contracts for the project. Procurement policies and procedures are detailed in the Fairfax County Purchasing Resolution (2026, or most recent version available); including, but not limited to, procurement authorization, ordering office supplies and equipment, equipment inventory, consultant contracts, processing payments, and contract bidding and award. The Fairfax County Purchasing Resolution details general purchasing provisions, including competitive solicitation process, contract award process, disclosure of information, bonds, and prequalification process. Senior project staff at FCDOT will review and approve purchasing documents, recorded with the FCDOT Solicitation Quality Compliance Check List.
Authorized Purchasing Agents shall ensure that consultants, contractors, and suppliers are capable of providing the desired product or service, in a timely, cost‐effective and consistent manner as specified in the contract. FCDOT shall evaluate and select consultants/contractors/suppliers based on their ability to supply products or services in accordance with the contract requirements, including the bidder’s QA organization.
All Project contract and purchasing requirements will clearly specify the expectations of the purchaser, including relevant standards, drawings, specifications, process requirements, inspection instructions and approval criteria for materials, processes, and product.
The procurement documents will include any requirements for the purchaser, supplier, or a different organization to perform verification activities at the production site, special handling or receiving of material or equipment, in‐process inspections, product acceptance, storage, etc.
FTA’s QMS Elements are extended to FCDOT’s project partners, contractors, subcontractors, consultants, and other vendors. The PMC, construction contractor, and IQAVS&T contractor must submit a QA/QC plan, that includes a quality organization, to the IQAM for approval. The QA/QC plan requirements for consultants, contractors, and suppliers will be included in the contract scope of work.
Additional quality standards will be included in the contract special provisions. FCDOT procurement staff will use the RHBRT QA/QC Contract Requirements Checklist to verify that quality requirements are included in the contract, as appropriate for the scope of work. The prime consultant and contractor are responsible for the quality of work under their contract, including the work of their subcontractors.
Contractors are responsible for the review and acceptance of their subcontractor’s quality program.
https://www.transit.dot.gov/sites/fta.dot.gov/files/2025-01/Third-Party-Contracting-Guidance-%28Circular-4220.1G%29.pdf https://www.transit.dot.gov/sites/fta.dot.gov/files/docs/funding/procurement/8286/fta-best-practices-procurement-and-lessons-learned-manual-2016.pdf https://www.transit.dot.gov/sites/fta.dot.gov/files/docs/funding/procurement/8286/fta-best-practices-procurement-and-lessons-learned-manual-2016.pdf https://www.fairfaxcounty.gov/procurement/resolution
Basic Ordering Agreement (BOA) Contracts are reviewed and approved by FCDOT in accordance with the advertised Request for Qualifications document and latest version of the Fairfax County Purchasing
Resolution document and Engineering Proposal Document. BOA Contracts will include the required documentation and terms set forth by FCDOT. Original BOA Contracts are also reviewed and approved by the VDOT Assurance and Compliance Office to ensure compliance with State/Federal Requirements.
VDOT Local Assistance Office issues Notice to Proceed to award the Original BOAs.
These procedures, along with the referenced Fairfax County Purchasing Resolution, provide guidance to ensure the goods and services are procured as economically as feasible, in a manner that complies with all Federal, state, and local laws and policies.
The Project shall require the right‐of‐access to the contractor or subcontractor facilities as specified in the contract documents to inspect, review, audit or otherwise verify the specified purchasing requirements are being fulfilled.
The Fairfax County discipline leads identified in the project organizational chart are responsible for the periodic review of service provider deliverables within their discipline for timeliness and accuracy, including evidence of effective implementation of the quality requirements. The review will be documented using the RHBRT Deliverable Quality Review Form. The completed form will be submitted to IQAM and the Document Control Team.
Fairfax county may perform additional audits of contracts (including amendments) in excess of $200,000 related to compliance with contract documents for a period of three years after final payment (as detailed in the Fairfax County Purchasing Resolution).
The Fairfax County Department of Public Works and Environmental Services will train staff involved in procurement on the FTA and project-specific requirements for procurement.
The IQAM will perform independent audits to verify compliance with this procedure according to the schedule in the Audit procedure.
6. PRODUCT IDENTIFICATION AND TRACEABILITY
6.1 Purpose
This section describes the procedure for the control of materials, parts, and components used to construct the project.
6.2 Scope
These requirements apply to all materials, parts, components, equipment, and products produced for incorporation into the Project. Contract documents will describe the requirements for tracing materials to the location where they are incorporated into the work, based on industry standards about the criticality of the material to the Project.
6.3 Procedure
Contractors and their subcontractors, vendors and suppliers will establish QC procedures to ensure control, identification, and traceability of items. All raw materials received must be traceable to a specific batch number, shipment number, packaging slip, or invoice and be accompanied by applicable test reports, Buy America/Build America documentation, and other necessary material certifications.
These identifications shall be referenced on QC test and inspection documents to provide an auditable trail from fabrication or testing to installation on the project. Unidentified items lacking required traceability or nonconforming items must be segregated or otherwise controlled to prevent their use on the Project.
Final assemblies must be clearly marked with project numbers, model numbers, serial numbers, or bar codes so that all pertinent information regarding that assembly may be retrieved.
Physical identification and control will be used to the extent possible. Where physical identification is impractical, physical separation, including removing from the job site, or other appropriate means will be used to ensure that only correct and acceptable items are used and to prevent the use of deficient or defective items. Acceptable methods for preserving lot identification include physically preserving observable lot identifications, recording the lot identification on an inspection form, or collecting
(photographing) the physical lot identifier as a record. The physical lot identifier can be a delivery ticket and/or a shipping label. Product identification and traceability requirements will be added to the
Construction Contractor contract.
The Project design team (FCDOT Staff and the PMC) is responsible for determining the quality requirements and standards for the materials included in the contract. To prevent the use of incorrect or defective items, the PMC will be responsible for reviewing and accepting the contractor’s determination of specific requirements for identifying and controlling production elements.
The contractor’s responsible lead along with any associated suppliers are responsible for providing the necessary documentation to support the identification, origin and quality disposition of supplied material and construction components. This includes completing any material receiving inspection reports to verify that materials were inspected upon delivery and prior to installation. The contractor’s quality manager has the overall responsibility for tracking the status of all receiving inspections performed, reviewing the records, and maintaining a tracking log. The PMC Construction Manager will provide oversight to verify if the procedure is being followed as outlined.
All products/materials/supplies shall be from VDOT-approved materials lists unless otherwise approved by FCDOT and VDOT. Materials needing special approval may include but not be limited to materials involved in the construction of Project stations, vehicles, and the Operations and Maintenance Facility.
The PMC will develop the specifications for required materials not included in the VDOT-approved material list. The PMC will verify materials upon delivery. The Project will follow the Materials
Acceptance and Materials Notebook Program, Chapter 7 of VDOT’s Materials Manual of Instruction. The
Materials Notebook serves as the tool to document that all materials used on the project are approved materials meeting specifications.
Project documents for traceability, identification, and material control will be developed during Final Design. Identification and traceability records will be maintained as quality records.
Quality assurance will primarily be provided via the audit of these records. Processes may also be monitored to ascertain the adequacy of this effort.
7. PROCESS CONTROL
7.1 Purpose
This section establishes the requirements for the control of special processes, as identified herein. The process and procedures for other, common construction processes are defined in the inspection and testing section.
7.2 Scope
These requirements apply to all special processes that subsequent inspections cannot verify quality. These include but are not limited to welding, heat treatment, cleaning, concrete and asphalt placement, plating, waterproofing, non-destructive examinations, and testing including initial in-plant fabrication/testing at VDOT approved fabricator plants (for items like signal poles, pre-cast pipe, inlets, other pre-cast concrete elements).
7.3 Procedure
Contractors, suppliers, and fabricators shall identify and plan the production, installation, and servicing processes that directly affect quality. The FCDOT Construction Manager, or designee, shall ensure that these processes are carried out under controlled, continuously monitored, conditions. The IQAVS&T contract will have the primary responsibility for monitoring and verifying special processes.
The construction contractor’s QC plan will address the following:
• Identification of special processes.
• Special process production procedures and instructions per applicable codes, standards, specifications, and drawings.
• A work plan for special process productions or installation that provides for an appropriate work sequence, suitable working environment, appropriate equipment, and acceptance criteria.
• Appropriate certifications for special process production procedures.
• Appropriate qualifications for personnel performing or inspecting special processes.
• Equipment warranty requirements and operations and maintenance procedures will be required as a deliverable in each system’s procurement contract.
Contractors, suppliers, and fabricators are responsible for performing special processes per their contract documents and QC plan. Documented work instructions can help with process sequencing where there is complex or multi-disciplined work. Process controls ensure that work is performed in the proper sequence.
In addition, the contract documents will identify required hold points or special inspection requirements
(see Section 5 for quality in contracting procedures).
The IQAM will approve QC plans for special processes and verify conformance to the plan through a pre-determined audit schedule.
8. INSPECTION AND TESTING
8.1 Purpose
This section describes the procedures for planning, implementing, and documenting inspections and test activities necessary to verify conformance to contract requirements for the Project. Procedures will be developed and maintained per the VDOT’s Inspection Manual and Construction Manual. Inspection and testing procedures must be planned and executed as necessary to verify quality.
8.2 Scope
The procedure will apply to any activity involving inspections and tests required to verify quality in the inspection of items that materials are correct and compliant prior to use or installation including in-plant fabrication inspection and testing at VDOT-approved fabricator plants.
8.3 Procedure
Inspection and testing procedures during the design phase are detailed in PMP Section 7.3. FCDOT has developed Construction Quality Procedures and Forms (CQP) that detail quality control procedures and forms used by inspectors and construction managers during the construction phase. Inspection and testing procedures are required for initial inspections, receiving products, quality check point inspections and control of deficiencies.
FCDOT will retain overall project oversight responsibilities during the design and construction of the Project. The FCDOT Construction Manager and designees will monitor inspection and testing to verify the activities affecting quality are inspected and documented in accordance with contract requirements.
Construction contractors and suppliers will be responsible for the QC activities necessary for monitoring, inspection, and testing in accordance with contract requirements and verifying that the results meet the established requirements. The construction contractor shall test material, workmanship and site conditions when required by the contract.
FCDOT will procure an Independent Assurance and Verification Sampling and Testing (IQAVS&T) services contract to provide inspection and testing QC. Testing services may be performed when required, or deemed necessary by the IQAVS&T Contractor, on such materials as asphalt, soils, concrete, structural steel, etc.
Project construction staff will use a Control of Deficiencies procedure to document the existence, location, and communication of the status of the issue and to verify that deficient work is brought back into compliance and not…