RFQSOW DCR-002-26 Apr17-2026.pdf

PDF 1 MB Posted

Attached to
Ticket 377349 - FY26 - DCR Fleet EV Charging Stations Tolland State Forest Office
Solicitation number
BD-26-1042-ENVOP-FAC01-128328
Issued by
Massachusetts

About this file

This Statement of Work is issued by the Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs (EOEEA) for the purchase, installation, and commissioning of electric vehicle charging equipment at the Tolland State Forest Office in East Otis, Massachusetts. The project requires vendors to furnish and install two exterior Level 2 EV charging stations (ChargePoint CPF50-L23 or approved alternative) that are WEX compatible, a 100-ampere electrical subpanel, protective wall-mounted guards or bollards, exterior disconnect switches, and all associated conduit, wiring, circuit breakers, and hardware necessary for complete operational systems. All work must comply with the National Electrical Code and other applicable codes. The mandatory site visit is scheduled for Tuesday, April 21st, 2026, from 10:30 AM to 12:00 PM. Vendors must submit questions by April 29th, 2026, at 5:00 PM EST, with responses posted by May 6th, 2026. The proposal submission deadline is May 11th, 2026, at 3:00 PM EST, with an estimated contract start date of May 19th, 2026. All work must be completed by June 29th, 2026.

Vendors must submit proposals exclusively through COMMBUYS and include the required Response Cover Sheet (Attachment A), an itemized quotation with fixed-price fees and delivery schedule, and separate pricing for one-year and five-year networking and warranty options (including two-year, three-year, and four-year options). The solicitation is issued under the Massachusetts Small Business Purchasing Program (SBPP), with preference given to SBPP-registered participants meeting best value criteria; non-SBPP participants will only be evaluated if no qualified SBPP bidder meets evaluation standards. Vendors are responsible for all permitting, inspections, equipment commissioning, delivery of specification sheets, and as-built electrical drawings. No payments will be made until a Notice to Proceed is issued, and all expenses must be included in contract prices. This procurement is conducted under MGL Chapter 7, Section 22; Chapter 30, Sections 51 and 52; and 801 CMR 21.00, and falls under the statewide contract VEH122 for Advanced Vehicle Technology Equipment, Supplies, and Services.

View the file

Other files

File Type Posted
Tolland Prevailing Wages.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs

100 Cambridge Street, Suite 900 Boston, MA 02114

Maura T. Healey

GOVERNOR

Kimberley Driscoll

LIEUTENANT GOVERNOR

Rebecca L. Tepper

SECRETARY

Tel: (617) 626-1000 Fax: (617) 626-1081 http://www.mass.gov/eea

STATEMENT OF WORK (SOW) FOR

Project Number: DCR-002-26

Project Name: DCR Fleet EV Charging Stations Tolland State Forest

Office

Project Location: Tolland State Forest Office, 410 Tolland Rd, East Otis, MA 01029

Property ID: 17_38 Location ID: M_70845_879885 Approximate lot Size: 129.65 Acres

Source & Date: Massachusetts Interactive Property Map - April 8, 2026

Project Manager(s): Juan Guzman - Juan.Guzman@mass.gov Ryan Kingston - Ryan.C.Kingston@mass.gov

Awarding Entity: Executive Office of Energy and Environmental Affairs (100

Cambridge Street, Boston, MA)

Under OSD Statewide Contract:

VEH122: Advanced Vehicle Technology Equipment, Supplies and Services

Category 1: Electric Vehicle Supply Equipment (EVSE), Hardware, Software, and Ancillary Services https://massgis.maps.arcgis.com/apps/OnePane/basicviewer/index.html?appid=47689963e7bb4007961676ad9fc56ae9 mailto:Juan.Guzman@mass.gov mailto:Ryan.C.Kingston@mass.gov

This is a single document associated with a complete Bid that can be found on COMMBUYS (www.commbuys.com/). All Vendors are responsible for reviewing and adhering to all information, forms and requirements incorporated into the Statement of Work. Responses received after the deadline shall be disqualified. All Vendors should plan advance lead time for uploading proposals into COMMBUYS in a timely manner prior to the deadline. All Questions and Answers and Bid Responses must be submitted electronically through COMMBUYS.

Vendors requiring assistance in the registration and use of COMMBUYS should contact the COMMBUYS Helpdesk at COMMBUYS@state.ma.us or the COMMBUYS Helpline at 1-888- MA-STATE. The Helpline is staffed from 8:00 AM to 5:00 PM Monday through Friday Eastern time, as applicable, except on federal, state and Suffolk County holidays.

Document Outline

I. Project Description II. Applicable Procurement Law

III. Scope of Work for Charging Stations IV. Compliance with Contract Requirements V. Compensation

VI. Best Value Selection and Negotiation VII. Small Business Purchasing Program (SBPP)

VIII. Bidder Communication IX. Estimated SOW Calendar X. Questions via the Bid (Q&A) on COMMBUYS

XI. Required Components for Response Submission XII. Attachments:

a. Attachment A – Response Cover Sheet

b. Attachment B – Installation Area View

c. Attachment C – EV Charging Electrical Sketch

d. Attachment D – Wall Mount Guard (1 of 2)

e. Attachment E – Mini Wall Mount Guard (2 of 2)

f. Attachment F – CPF50-L23 Architectural Drawings

g. Attachment G – Bollard Diagram

I. Project Description

The Commonwealth of Massachusetts, through EEA Facilities (EOEEA) is seeking to engage a qualified vendor (hereafter referred to as “Vendor”) to purchase, install, and commission Electrical Vehicle (EV) charging equipment at Tolland State Forest Office for Fleet use. The detailed scope of work is provided in Section III. Additional diagrams associated with the scope are attached under the “Attachments” section of this document.

NO PROPOSALS WILL BE ACCEPTED BY EMAIL, DELIVERY OR MAIL. ONLY

PROPOSALS RECEIVED VIA COMMBUYS WILL BE ACCEPTED.

http://www.commbuys.com/

II. Applicable Procurement Law This Solicitation is issued, and any contract will be awarded, under MGL c. 7, § 22; c.

30, § 51, § 52; and 801 CMR 21.00 (Goods and Services).

III. Scope of Work for Charging Stations

In accordance with the latest recognized National Electrical Code, (and all other applicable codes) the contractor shall be responsible for furnishing, installing, and commissioning all the equipment listed below:

Equipment:

• (2) – Exterior Level 2 EV Charging Stations, Wall-mounted units – ChargePoint CPF50-L23 (or approved alternative) Must be WEX compatible

• (1) – Electrical Subpanel – 100A

• Standard Wall Mount Guard – as per Attachment D will not fit.

Vendors should explore the Mini Wall Guard as shown in Attachment E, or explore an appropriate wall mounted solution.

o If no Wall Mounted solutions are possible (which is the ideal choice) then (2) bollards will be accepted as an alternate for the Wall Mount Guard – as per Attachment G

• Exterior Disconnect Switch (quantity as needed)

• Conduit, Wiring, Circuit Breakers, labeling, Junction Boxes, and all other associated hardware/equipment/ parts as needed for complete operational system

It is required that the contractor shall ensure that the completed operational systems have the required permitting and inspections. Other requirements include:

General Requirements:

• EV charging equipment to be wall-mounted at specifically designated locations, as indicated in project attachments

• All wiring to be run in conduit

• All wiring to be Copper

• Trenching will not be required

• Vendor must deliver spec sheet for all equipment – prior to completed work

• Vendor must deliver electrical one-line and/or as built drawings

• Vendor shall be responsible for inspection, permitting, and equipment commissioning

• Vendor must do a final walkthrough prior to the closing of this contract

• Vendors should include separate and clearly defined pricing for:

o 1-year networking and warranty options o 5-year networking and warranty options (include 2-year, 3-year, and 4-year)

The Vendor shall coordinate its work with the EEA team and shall not commence work until a Notice to Proceed has been issued. All work as defined in the RFP must be completed by no later than June 29th, 2026.

There are 7 diagrams attached to this document under the “Attachments” section.

They provide additional clarification and visuals for the desired outcomes of the installation.

IV. Compliance with Contract Requirements The vendor shall comply with all terms and conditions of their respective contract.

EEA Facilities reserves the right to negotiate and modify requirements with the awarded vendor.

V. Compensation No services may be performed, or fees incurred by the vendor under the contract unless a Scope of Services has been agreed to in writing and with a not-to-exceed amount and a written notice to proceed from EEA Facilities has been issued. No payments shall be made for goods or services not rendered. There will be no reimbursements for any costs incurred in the preparation of a bidder’s response to this RFP including but not limited to travel expenses, phone charges, tolls, fuel, parking or rental fees.

The services that may be provided are set forth in the SOW, and all expenses to deliver services shall be included in the contract prices. All invoices for payment under Contract shall include a detailed accounting of work authorized in a form and detail acceptable to EEA Facilities. Invoices must be submitted in a timely manner.

VI. Best Value Selection and Negotiation EEA Facilities may select the response which demonstrates the best value overall, including proposed alternatives, that will achieve the procurement and service goals of the EOEEA. Bidders may provide supplemental information. EEA Facilities and the selected bidder(s) may negotiate a change in any element of contract performance or cost identified in the original SOW or the selected Bidder’s or Contractor’s response which results in lower costs or a more cost effective or better value than was presented in the selected Bidder’s or Contractor’s original response.

During the selection process, EEA Facilities reserves the right to take any or all of the following actions if it deems them to be in the interests of the Commonwealth of Massachusetts:

• Reject any and all proposals;

• Waive any minor informalities in proposals received or request Respondents to correct them;

• Request additional information from Respondents and seek clarification from a

Respondent provided that EEA Facilities determines it is not prejudicial to the interests of the other Respondents to do so. Action by the selection team in this regard should not be construed to imply acceptance or rejection of a proposal.

VII. Small Business Purchasing Program (SBPP) Program Background. The Massachusetts Small Business Purchasing Program (SBPP) was established pursuant to Executive Order 599 to increase state contracting opportunities with small businesses having their principal place of business within the Commonwealth of Massachusetts.

Pursuant to the SBPP, it is the intention of the issuing department to award this Small Procurement to one or more SBPP participating business(es) as described below.

SBPP Award Preference. While all businesses, no matter the size or principal place of business, may submit responses to this solicitation, should an SBPP participant respond and meet the best value criteria as described in this solicitation, the SBPP participant shall be awarded the contract.

The Strategic Sourcing Services Team (SST) will not evaluate submissions from non-SBPP participants unless no SBPP Bidder meets the SSST’s best value evaluation criteria.

SBPP Participation Eligibility. To be eligible to participate in this procurement as an SBPP participant, an entity must meet the following criteria, and be marked as an SBPP registered business in COMMBUYS:

1. Have its principal place of business in the Commonwealth of Massachusetts;

2. Been in business for at least one year;

3. Employ a combined total of 50 or fewer full-time equivalent employees in all locations, or employees work less than a combined total of 26,000 hours per quarter; and

4. Have gross revenues, as reported on appropriate tax forms, of $15 million or less, based on a three-year average.

Non-profit firms also must be registered as a non-profit or charitable organization with the MA Attorney General’s Office and be up to date with all filings required by that office and be tax exempt under Section 501(c) of the Internal Revenue Code.

SBPP Compliance Requirements. It is the responsibility of the Bidder to ensure that their SBPP status is current at the time of submitting a response and throughout the life of any resulting contract. Misrepresentation of SBPP status will result in disqualification from consideration, and may result in debarment, contract termination, and other actions. To learn more about the SBPP, including how to apply, visit the SBPP Webpage.

Program Resources and Assistance. Bidders and Contractors seeking assistance regarding SBPP may visit the SBPP webpage, http://www.mass.gov/sbpp, or contact the SBPP Help Desk at sbpp@mass.gov.

VIII. Bidder Communication Bidders are prohibited from communicating directly with any employee regarding this SOW except as specified in this SOW with the EEA Facilities team. No other individual Commonwealth employee or representative is authorized to provide any information or respond to any question or inquiry concerning this SOW. Bidders may contact the contact person for this SOW in the event that the SOW is incomplete, or the bidder is having trouble obtaining any required attachments electronically through

COMMBUYS.

https://www.mass.gov/sbpp https://www.mass.gov/executive-orders/no-599-reaffirming-programs-to-ensure-diversity-equity-and-inclusion-for-diverse-and-small-massachusetts-businesses-in-state-procurement-and-contracting?_gl=1*wnz9qe*_ga*OTcxODE1Mjg3LjE2ODM2MzUyMjc.*_ga_MCLPEGW7WM*MTY5ODA3OTg1NC4yNi4wLjE2OTgwNzk4NTQuMC4wLjA.

https://www.commbuys.com/bso/ http://www.mass.gov/sbpp http://www.mass.gov/sbpp mailto:sbpp@mass.gov

IX. Estimated SOW Calendar

Milestone Date Availability of SOW on COMMBUYS April 17th, 2026 (Mandatory) Tolland State Forest Office Site Visit

Vendors can visit Tuesday, April 21st, 2026

Site personnel will be available only from:

10:30AM-12:00PM

Submission of Vendor Question(s) through COMMBUYS (DUE)

April 29th, 2026 by 5PM

EST

Responses to Vendor Questions posted in COMMBUYS (Estimated)

May 6th, 2026

Proposal Submission Deadline May 11th, 2026 by 3PM Estimated Contract Start Date May 19th, 2026 Final Date for all Deliverables/ Specifications under the Scope of Work Deadline

June 29th, 2026

X. Questions via the Bid (Q&A) on COMMBUYS The Bid Q&A provides the opportunity for Vendors to ask written questions and receive written answers from EEA Facilities regarding this SOW. All Vendor questions must be submitted through the Bid Q&A found on COMMBUYS. Questions may be asked at any time prior to the Deadline for Submission of Questions stated in the Estimated Procurement Calendar. EEA Facilities reserves the right not to respond to questions submitted after this date. It is the Vendor’s responsibility to verify receipt of questions.

Please note that any questions submitted to EEA Facilities using any other medium (including those that are sent by mail, fax, email or voicemail, etc.) will not be answered. To reduce the number of redundant or duplicate questions Vendors are asked to review all questions previously submitted to determine whether the question has already been posted.

Vendors are responsible for entering content suitable for public viewing, since all questions are accessible to the public. Vendors must not include any information that could be considered personal, security sensitive, inflammatory, incorrect, collusory, or otherwise objectionable, including information about the Vendor’s company or other companies. EEA Facilities reserves the right to edit or delete any submitted questions that raise any of these issues or that are not in the best interest of the Commonwealth or this SOW.

All answers are final when posted. Any subsequent revisions to previously provided answers will be dated.

It is the responsibility of the prospective/ awarded Vendor to maintain an active registration in COMMBUYS and to keep current the email address of the Vendor’s contact person and prospective contract manager. If awarded a contract, the Vendor is required to monitor that email inbox for communications from EEA Facilities, including requests for clarification. EEA Facilities assumes no responsibility if a prospective/ awarded Vendor’s designated email address is not current, or if technical problems, including those with the prospective/ awarded Vendor’s computer, network or internet service provider (ISP) cause email communications sent to/ from the prospective/ awarded Vendor and EEA Facilities to be lost or rejected by any means including email or spam filtering.

XI. Required Components for Response Submission The following components specific to this SOW must be included in the order outlined below with your response. Failure to include all the requested information and completed required forms may result in rejection of your firm’s submission. Proposals received after the deadline will be rejected. The required SOW components are as follows:

1) Attachment A – Response Cover Sheet

2) Proposal based on Scope of Work (including Schedule)

3) Compensation Structure/ Pricing and Expenses

Proposal based on Scope of Work: This refers to an itemized bid quotation that outlines a not to exceed fixed-price fees, the expected timeline (schedule) for deliverables, and details any associated expenses outlined in the project scope. This quotation must account for any quote requirements mandated through the designated Massachusetts Statewide Contract.

Bidders are encouraged to provide supplemental information regarding anything pertaining to the scope. Bidders will not be penalized for not submitting supplemental information. EEA Facilities will consider all aspects of a bidder’s proposal in its determination.

XII. Attachments

ATTACHMENT A – Response Cover Sheet DCR Fleet EV Charging Stations Tolland State Forest Office

Issued on:

April 17th, 2026

VENDOR SUBMITTING RESPONSE

Firm Submitting Proposal

Name of Authorized Signatory Title

Email Phone Number

Address of Firm

Signature Date

ATTACHMENT B – Installation Area View

ATTACHMENT C – EV Charging Electrical Sketch

ATTACHMENT D – Wall Mount Guard (1 of 2)

ATTACHMENT E – Mini Wall Mount Guard (2 of 2)

ATTACHMENT F – CPF50-L23 Architectural Drawings

ATTACHMENT G – Bollard Diagram