Cleveland National Forest Task Order #1
PART I – SCHEDULE OF ITEMS
SECTION B- SUPPLIES OR SERVICES PRICE/COSTS
Road Maintenance
Palomar Ranger District
Pay Item Description EST
QTY UNIT UNIT
PRICE TOTAL
881(1) Mobilization 1 LS $______ $________
839(01)
Restore Drainage Function 37.8 MI $______
TOTAL $______ $_______
CNF TASK ORDER # 001
General Notes:
• This project involves performing road maintenance activities on High Point Rd., 5S05 (10.4 miles), Oak Grove Rd., 9S09 (7 miles), Halfway Rd., 9S06 (4 miles), and Palomar Divide Rd., 9S07 (16.4 miles). This is total of 37.8 miles of Forest Service, Maintenance Level II, and Level III roads. Contractor will provide all equipment, labor, and materials required to accomplish specified work.
• No Disposal or borrow sites are required. No side casting of material is permitted.
• Detailed “Work Schedule Plan” and “Traffic Plan” will be required prior to start of work.
• All equipment shall be cleaned and inspected prior to start of work.
Specified Work:
1. High Point Road, M.P. 0.00 to M.P. 10.4
• Restore Drainage Function
2. Oak Grove Road, M.P. 0.00 to M.P. 7.0
3. Halfway Road, M.P. 0.00 to M.P. 4.0
4. Palomar Divide Road, M.P. 0.00 to M.P. 16.4
5. Mobilization for all roads
Applicable Specifications and Drawings:
1. Specifications
• 881 Mobilization (04/05)
• 839(01) Restore Drainage Function
• BMP Notes
• CNF Fire Plan (Palomar District)
2. Drawings
• 837-1 Typical Rolling Dip
3. Maps
• California CNF Map
• CNF Map
BMP Notes
Soil erosion and storm water pollution control measures, where specified, shall be in accordance with section 204 and Caltrans “Best Management Practices”.
Caltrans Storm Water Quality Handbook, “Construction Site Best Management Practices Manual” (BMP’s) can be purchased from California Department of Transportation, publications distribution unit, (916) 445-3520.
When specified, the contractor shall submit a written “Storm Water Management Plan” at least 5 business days prior to beginning work.
The contractor shall not disturb the area beyond project limits. The contractor shall take all appropriate steps to insure that no discharge or pollutants enter any streambed as a result of the contractor’s work activities.