CNF TASK ORDER 1.pdf

PDF 85 KB Posted

Attached to
Southern California Road Maintenance Project
Solicitation number
RFQ-S-05-SS-08-296
Issued by

About this file

Task Order 1 - Statement of Work

View the file

Other files

File Type Posted
Attachment_C1_San Bernardino Map.pdf PDF
sf_1449.pdf PDF
CNF MAP.pdf PDF
Fire Plan CNF.pdf PDF
Project Area Map.pdf PDF
837-1 Dip Drawing.pdf PDF
Attachment_F_Fire_Plan.pdf PDF
Attachment_D_Wage_Determinations.pdf PDF
Attachment_C_Maps.pdf PDF
Solicitation.pdf PDF
Attachment_A_Standard_Specifications.pdf PDF
Attachment_E_Experience_Questionnaire.pdf PDF
Attachment_B_Drawings_Typicals 1 .pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cleveland National Forest Task Order #1

PART I – SCHEDULE OF ITEMS

SECTION B- SUPPLIES OR SERVICES PRICE/COSTS

Road Maintenance

Palomar Ranger District

Pay Item Description EST

QTY UNIT UNIT

PRICE TOTAL

881(1) Mobilization 1 LS $______ $________

839(01)

Restore Drainage Function 37.8 MI $______

TOTAL $______ $_______

CNF TASK ORDER # 001

General Notes:

• This project involves performing road maintenance activities on High Point Rd., 5S05 (10.4 miles), Oak Grove Rd., 9S09 (7 miles), Halfway Rd., 9S06 (4 miles), and Palomar Divide Rd., 9S07 (16.4 miles). This is total of 37.8 miles of Forest Service, Maintenance Level II, and Level III roads. Contractor will provide all equipment, labor, and materials required to accomplish specified work.

• No Disposal or borrow sites are required. No side casting of material is permitted.

• Detailed “Work Schedule Plan” and “Traffic Plan” will be required prior to start of work.

• All equipment shall be cleaned and inspected prior to start of work.

Specified Work:

1. High Point Road, M.P. 0.00 to M.P. 10.4

• Restore Drainage Function

2. Oak Grove Road, M.P. 0.00 to M.P. 7.0

3. Halfway Road, M.P. 0.00 to M.P. 4.0

4. Palomar Divide Road, M.P. 0.00 to M.P. 16.4

5. Mobilization for all roads

Applicable Specifications and Drawings:

1. Specifications

• 881 Mobilization (04/05)

• 839(01) Restore Drainage Function

• BMP Notes

• CNF Fire Plan (Palomar District)

2. Drawings

• 837-1 Typical Rolling Dip

3. Maps

• California CNF Map

• CNF Map

BMP Notes

Soil erosion and storm water pollution control measures, where specified, shall be in accordance with section 204 and Caltrans “Best Management Practices”.

Caltrans Storm Water Quality Handbook, “Construction Site Best Management Practices Manual” (BMP’s) can be purchased from California Department of Transportation, publications distribution unit, (916) 445-3520.

When specified, the contractor shall submit a written “Storm Water Management Plan” at least 5 business days prior to beginning work.

The contractor shall not disturb the area beyond project limits. The contractor shall take all appropriate steps to insure that no discharge or pollutants enter any streambed as a result of the contractor’s work activities.