7900975_PM_ON_WASTE_WATER_TREATMENT_SYSTEM_2019.docx
DOCX document 179 KB Posted
- Attached to
- PREVENTIVE MAINTANENCE SERVICE CONTRACT FOR WASTE WATER COLLECTION AND TREATMENT SYSTEMS
- Solicitation number
- RFQ7900975
- Issued by
-
Department of State US Embassy Abuja
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 7900975__COVER_LETTER.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ #PR7900975 - BME for NEC Waste Water Treatment System
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NO.
PR7900975
6. SOLICITATION ISSUE DATE
12/017/2018
7. FOR SOLICITATION
INFORMATION CALL
a. NAME
b. TELEPHONE NO. (No collect calls) +234 9-461-4000
8. OFFER DUE DATE/LOCAL TIME
12/31/2018, 4:00pm
| 9. ISSUED BY |
| CODE |
| 10. THIS ACQUISITION IS |
| 11. DELIVERY FOR FOB |
| 12. DISCOUNT TERMS |
The Contracting Officer American Embassy Plot 1075 Diplomatic Drive -
|X| UNRESTRICTED
|_| SET ASIDE: % FOR
|_| SMALL BUSINESS
DESTINATION UNLESS BLOCK IS MARKED
|_| SEE SCHEDULE
Central Area
| |_| SMALL DISADV. BUSINESS | |
| |_| 13a. THIS CONTRACT IS A RATED ORDER | |
| UNDER DPAS (15 CFR 700) |
Abuja.
| |_| 8(A) |
| 13b. RATING |
SIC:
SIZE STD:
| 14. METHOD OF SOLICITATION | |||
| |_| RFQ | |_| IFB | |X| RFP |
15. DELIVER TO CODE
16. ADMINISTERED BY CODE
Abujaprocbids@State.gov
Cletus Aimhionota
| 17a. CONTRACTOR/ | CODE |
| OFFEROR |
| FACILITY | |
| CODE |
18a. PAYMENT WILL BE MADE BY
EFT CODE
TELEPHONE NO.
EFT -
| |_| 17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER | |
| 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED | |_| SEE ADDENDUM |
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
| BME for NEC Waste Water Treatment System at the U.S. Embassy Compound, Abuja, Nigeria, for one base year and four option year periods as per SOW. |
| 4 |
| Yr |
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
|X| 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA |X| ARE |_| ARE NOT ATTACHED.
|X| 27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA |X| ARE |_| ARE NOT ATTACHED.
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN ___3__ COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN.
29. AWARD OF CONTRACT: REFERENCE ___________________ OFFER DATED _________________. YOUR OFFER ON SOLICITATION (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
| 30a. SIGNATURE OF OFFEROR/CONTRACTOR |
| 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) |
30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT)
30c. DATE SIGNED
31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) Masha Lance 31c. DATE SIGNED
| 32a. QUANTITY IN COLUMN 21 HAS BEEN |
| ACCEPTED, AND CONFORMS TO THE |
| 33. SHIP NUMBER |
34. VOUCHER NUMBER
35. AMOUNT VERIFIED CORRECT FOR
| |_| RECEIVED | |_| | INSPECTED | |_| | CONTRACT, EXCEPT AS NOTED |
| |_| PARTIAL | |_| FINAL |
| 36. PAYMENT |
| 37. CHECK NUMBER |
| 32b. SIGNATURE OF AUTHORIZED GOVT REPRESENTATIVE | ||
| 32c. DATE | ||
| |_| COMPLETE | |_| PARTIAL | |_| FINAL |
38. S/R ACCOUNT NO.
39. S/R VOUCHER NO.
40. PAID BY
42a. RECEIVED BY (Print)
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
| 41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER |
| 41c. DATE |
| 42b. RECEIVED AT (Location) |
| 42c. DATE REC’D (YY/MM/DD) |
| 42d. TOTAL CONTAINERS |
STATEMENT OF WORK FOR
PREVENTIVE MAINTANENCE SERVICE CONTRACT
Waste Water Collection and Treatment Systems
American Embassy at Abuja, Nigeria
TABLE OF CONTENTS
| 1. | INTRODUCTION | 4 |
| 2. | OBJECTIVES | 4 |
| 3. | TYPE OF CONTRACT | 5 |
| 4. | PERIOD OF PERFORMANCE | 5 |
| 5. | PRICING | 5 |
| 6. | NOTICE TO PROCEED | 10 |
| 7. | GENERAL REQUIREMENTS | 10 |
| 8. | CONTRACTING OFFICER REPRESENTIVE and POST CONTROL OFFICER | 12 |
| 9. | PERFORMANCE CRITERIA | 12 |
| 10. | SPECIFICATIONS | 13 |
| 11. | SAFETY HEALTH AND ENVIROMENTAL MANAGEMENT (SHEM) | 14 |
| 12. | MAINTENANCE SPECIFICATION DETAILS | 14 |
| 13. | SCOPE OF WORK | 15 |
| 14. | ACCESS TO GOVERNMENT BUILDINGS AND STANDARDS OF CONDUCT | 17 |
Attachments:
EXHIBIT A – STATEMENT OF WORK: WASTEWATER COLLECTION AND TREATMENT SYSTEM
RFQ #PR7900975 - BME for NEC Waste Water Treatment System
INTRODUCTION
1.1 The United States Department of State (DOS) requires services at the unclassified clearance level, to provide maintenance services for the sanitary sewer collection system and the wastewater treatment system at the New Embassy Compound, U.S. Embassy, Abuja, Nigeria in accordance with this contract.
1.2 The wastewater treatment and collection systems to be maintained are as follows:
· Sanitary Sewer Collection System
· Waste Water Treatment Plant
1.3 The Overseas Buildings Operations (OBO) has a requirement to obtain wastewater treatment plant maintenance services to execute this work, including logistics, customs, shipping, transportation, labor, wastewater treatment chemicals, tools, wastewater treatment testing kits/equipment, administrative and all associated management support functions. The wastewater treatment service contract includes but is not limited to combinations of physical methods, chemical methods, equipment servicing and testing to control wastewater-related issues such as flow control, blower maintenance & operation, air diffuser operation and adjustment, activated sludge aeration (Dissolved Oxygen), clarifier cleaning and operation, weir cleaning and adjustment, air-lift pumps operation and adjustment, filtration cleaning and operation (if applicable), disinfection control, effluent testing and adjustment. All work shall comply with the requirements described in the following, as a minimum:
· AWWA Standards (American Water Works Association)
· ANSI Standards
· SDS Regulations
· ASTM D NFPA Codes UL Standards IEEE Standards
· NEMA Standards
· OSHA Standards
· And all applicable manufacturer O&M and installation instructions/requirements.
OBJECTIVES
2.1 The purpose of this scope of work is to define the requirements for the preventive maintenance of the wastewater collection and treatment systems located at the US Embassy Compound Abuja. All work shall be executed in accordance with this SOW, approved wastewater treatment plant practices and shall be compliant with all applicable local and federal safety, equipment and building codes and standards. The intent of this service contract is as follows:
Sanitary Sewer Collection System: to optimize the performance of the collection system, and reduce (or eliminate) the frequency of overflows, basement back-ups, sewer pipe failures, lift station failures and peak flows.
Wastewater Treatment Plant: to adjust the wastewater treatment plant based on plant operating parameters, descale and adjust plant operations, prevent/monitor/ plant corrosion, verify local operating procedures within the manufacture’s guidelines, and familiarize operators on wastewater treatment plant operations and regulations.
TYPE OF CONTRACT
This is a firm fixed price contract payable entirely in ______s (US dollars). Prices for all Contract Line Item Numbers (CLIN) shall include proper disposal of toxic substances where applicable. No additional sums will be payable for any escalation in the cost of materials, equipment or labor, or because of the contractor's failure to properly estimate or accurately predict the cost or difficulty of achieving the results required. The contract price will not be adjusted due to fluctuations in currency exchange rates.
PERIOD OF PERFORMANCE
The contract will be for a period of one-year, with a maximum of four one-year optional periods of performance and will be expected to commence no later than July 2017.
PRICING
The rates below include all costs associated with providing preventive maintenance services in accordance with the attached scope of work, and the manufacturer’s warranty including materials, labor, insurance (see FAR 52.228-4 and 52.228-5), overhead, profit and GST (if applicable).
5.1 Base Year. The Contractor shall provide the services shown below for the base period of the contract and continuing for a period of 12 months.
Identify and describe each CLIN for purposes of contract award and payment. The CLINs collectively must cover all the work in the contract.
| CLIN |
| Description |
| Quantity of Equipment |
| Type of services |
| No. of service |
| Unit price / service ($) |
| Total per year ($) |
| 001 |
| Waste Water Treatment Plant |
| 1 |
| Annual PM visit |
| 1 |
| 001-A |
| Sewage Lift Station |
| 2 |
| Annual PM Visit |
| 1 |
Total Base Year
5.2.
Option Year 1. The Contractor shall provide the services shown below for Option Year 1 of the contract, and continuing for a period of 12 months.
| CLIN |
| Description |
| Quantity of Equipment |
| Type of services |
| No. of service |
| Unit price / service ($) |
| Total per year ($) |
| 001 |
| Waste Water Treatment Plant |
| 1 |
| Annual PM visit |
| 1 |
| 001-A |
| Sewage Lift Station |
| 2 |
| Annual PM Visit |
| 1 |
Total Base Year
5.3. Option Year 2. The Contractor shall provide the services shown below for Option Year 2 of the contract, and continuing for a period of 12 months.
| CLIN |
| Description |
| Quantity of Equipment |
| Type of services |
| No. of service |
| Unit price / service ($) |
| Total per year ($) |
| 2001 |
| Waste Water Treatment Plant |
| 1 |
| Annual PM visit |
| 1 |
| 201-A |
| Sewage Lift Station |
| 2 |
| Annual PM Visit |
| 1 |
Total Base Year
5.4. Option Year 3. The Contractor shall provide the services shown below for Option Year 3 of the contract, and continuing for a period of 12 months
| CLIN |
| Description |
| Quantity of Equipment |
| Type of services |
| No. of service |
| Unit price / service ($) |
| Total per year ($) |
| 301 |
| Waste Water Treatment Plant |
| 1 |
| Annual PM visit |
| 1 |
| 301-A |
| Sewage Lift Station |
| 2 |
| Annual PM Visit |
| 1 |
Total Base Year
5.5. Option Year 4. The Contractor shall provide the services shown below for Option Year 4 of the contract, and continuing for a period of 12 months.
| CLIN |
| Description |
| Quantity of Equipment |
| Type of services |
| No. of service |
| Unit price / service ($) |
| Total per year ($) |
| 401 |
| Waste Water Treatment Plant |
| 1 |
| Annual PM visit |
| 1 |
| 401-A |
| Sewage Lift Station |
| 2 |
| Annual PM Visit |
| 1 |
Total Base Year
| 5.6. Total for all years: | Base Year | $__________ | ||
| Option Year 1 | $__________ | |||
| Option Year 2 | $__________ | |||
| Option Year 3 | $__________ | |||
| Option Year 4 | $__________ | |||
| TOTAL | $__________ |
5.7 Repair option. Repairs are NOT included under this agreement and are to be done outside this contract. However, we would like to have current labor rates in the event that there is an issue discovered during the preventive maintenance of the specified equipment. Please provide your current labor rates in the Repair Option fields below. Any necessary repairs or parts will be submitted for approval and then billed against a separate purchase order (PO). The Contractor is not approved to do any additional work without approval.
Repair Labor Rates
| Base Year | $__________/hr. |
| Option Year 1 | $__________/hr. |
| Option Year 2 | $__________/hr |
| Option Year 3 | $__________/hr |
| Option Year 4 | $__________/hr |
5.8 Emergency Service Option. Emergency Service is NOT included under this agreement and will be billed outside this contract. However, we would like to have the rates in the event of an emergency. Emergency Service, with a four-hour response time, must be available 24-hours per day, 365 days a year. Submit cost for Emergency Services below. Please indicate how the emergency service will be billed (hourly, trip charge, etc.).
Emergency Service Rates
| Base Year | $_______________ |
| Option Year 1 | $_______________ |
| Option Year 2 | $_______________ |
| Option Year 3 | $_______________ |
| Option Year 4 | $_______________ |
NOTICE TO PROCEED
After Contract award and submission of acceptable insurance certificates and copies of all applicable licenses and permits, the Contracting Officer will issue a Notice to Proceed. The Notice to Proceed will establish a date (a minimum of ten (10) days from date of Contract award unless the Contractor agrees to an earlier date) on which performance shall start.
GENERAL REQUIREMENTS
7.1 This statement of work (SOW) describes the preventive maintenance and testing services and deliverables to be performed by the contractor at the New Embassy Compound, U.S. Embassy Abuja, Nigeria.
7.2 The assigned Contracting Officer and Contracting Officer's Representative are the sole points of contact for all technical and contractual discussions or issues regarding the scope of work and its intent and execution. The contractor shall take no direction verbal or otherwise from personnel other than the Contracting Officer or Contract Officer's Representative.
7.3 This Statement of Work requires the Contractor to provide site assessment and survey services, project management, professional wastewater treatment services, wastewater treatment logistics and material procurement services, preventive maintenance and testing services, cost estimating and scheduling services, and general support services for this wastewater treatment maintenance contract.
7.4 The contractor’s proposed and U. S. Government (USG) accepted maintenance contract cost proposal and maintenance schedule, including completion dates shall be incorporated into the task order. Additionally, the task order shall be a firm fixed price task order.
7.5 This statement of work and applicable deliverables and documents as developed by the contractor and accepted by the USG shall serve as the basis for describing and delineating the scope of the required services and work limits for service contract to be furnished and executed by the contractor.
7.6 All deliverables, documents, proposals, etc. submitted by the contractor under this statement of work shall remain the property of the USG. All USG documents and data provided to the contractor shall remain the property of the USG. The contractor shall limit duplication and dissemination of all USG documents and contractor developed documents under this statement of work to/within the contractor’s execution team. Duplication or distribution of project documents outside the contractor’s team is strictly prohibited without the express written approval and authorization of the Contracting Officer. Upon completion of each service visit all documents, electronic media, photos, etc. shall be submitted to the USG, including all documents and data that the USG provided to the contractor. All service contract documents and media shall be submitted to the USG along with the contractor’s service report.
7.7 The Contractor shall schedule, coordinate and arrange all work so as to cause the least interference with the normal occurrence of post operations. In those cases where some interference is unavoidable, the Contractor shall make every effort to minimize the impact of the interference and its effects on the occupants or users. All detailed work schedules required by this statement of work shall be electronically documented and updated and made available to the Contracting Officer's Representative (COR) upon request, oral or written. If the COR determines that the Contractor’s schedule conflicts with critical post operations, the Contractor shall modify the schedule as required.
7.8 The contractor shall ensure that all Embassy/Post facilities, equipment and systems recommended for and maintained or installed by the contractor are done so with the highest quality and cost effective materials, finishes, fixtures, equipment and system that provide for sustained operational reliability, dependability and durability. The contractor shall assure that any equipment/wastewater treatment chemicals furnished and installed are maintainable and equipment/parts can be readily replaced with locally available supplies and services, as practical taking into consideration local economy and resources. The contractor shall utilize reliability-centered maintenance (RCM) principles and methodologies during and for all project activities and tasks. Uniformity of parts and components shall be taken into consideration to maximize part interchangeability with other existing Post systems. Except as otherwise directed by the contracting officer all parts, materials, components, equipment, systems, etc. furnished by the contractor shall be new – not used or manufactured by third party entities. Except as otherwise directed by the contracting officer, all replacement or warranty parts shall be new and equal to or better than manufacturer recommended replacements.
7.9 After review of the USG Statement of Work and provided technical data by the contractor, any discrepancies, errors, conflicts, etc. that are discovered by the contractor, the contractor shall forward those items to the CO via written correspondence. Submittal of this written correspondence shall be completed, within 3 days upon receipt of the US Government Statement of Work.
7.9.1 The contractor shall provide 3 customer references of similar scope of work and its US dollar value.
7.9.2 The Contractor will not use any method or substances that may cause damage to the equipment or systems. Any damage or loss through negligence and/or maintenance practices by the Contractor, sub-contractor, or Contractor's staff shall be the whole responsibility of the Contractor. The U.S. Embassy, Abuja, Nigeria will require the Contractor to repair/replace any damaged systems or pay for the cost of rectification.
7.9.3 The Contractor must, for the duration of the contracted Services, continue to maintain a quality control process that has been agreed to by the U.S. Embassy, _Abuja, Nigeria COR and the Contractor.
7.9.4 The Contractor shall provide the technician’s resume and training documentations within twenty (20) calendar days of the notice to proceed.
7.10 No work on any portion of the collection system or the wastewater treatment plant shall be permitted on the last regular work day of the week. All work under this contract must be scheduled to assure that the day following the work is a normal working day for the US Embassy. Further, the contractor must certify availability to return immediately to the US Embassy compound to correct any operating issues that may arise following contractor work.
CONTRACTING OFFICER REPRESENTIVE and POST CONTROL OFFICER
8.1 All technical questions concerning the scope and requirements of the U.S. Embassy, _Abuja,_ wastewater treatment service contract shall be directed to the Contracting Officer’s Representative (COR):
COR
Heroux, Donald_-Facility Manager HerouxDJ@state.gov
8.2 The Post Control Officer (PCO) will be the contractor’s point of contact at the U.S. Embassy, ___Abuja,_Nigeria_. All questions concerning coordination of wastewater treatment service activities while at post shall be directed to the Post Control Officer, with weekly reporting to the COR:
PCO
John Ogboyi-Post Control Officer (PCO) OgboyiJE@state.gov
PERFORMANCE CRITERIA
9.1 Performance Objective
The objective of this Agreement is to provide, within the Term of this Contract, a professional level of service, which provides:
· US Embassy satisfaction in respect to the maintenance of wastewater collection and treatment system; prompt reaction to any change in arrangements or operational requirements of the US Embassy;
· compliance with the statutory and regulatory provisions of the laws of the jurisdiction;
· best in class practices within the industry;
· risk reduction for the US Embassy;
· preservation of asset value; and
· reduction in operating costs.
The Contractor agrees that its performance under the Contract shall be measured against performance criteria specified in this document or otherwise agreed at the time of commencement.
9.2 Performance Benchmarks
The Contractor must for the duration of the contracted Services continue to maintain a quality control process, which has been agreed by the US Embassy and the Contractor.
The Contractor must allow the US Embassy access to the quality control system as well as the relevant quality systems of its subcontractors to enable monitoring and quality auditing of the maintenance service.
The US Embassy may reject any aspect of the Services that fails to comply with the requirements of the Contract, or its quality system, at any time.
9.3 Performance Monitoring and Reporting
The Contractor shall monitor its own performance against the criteria and benchmarks identified in this document, and shall provide reports when reasonably required by the US Embassy.
WASTEWATER TREATMENT AND COLLECTION SYSTEM SPECIFICATIONS
10.1 All equipment, chemicals, and testing procedures and kits shall be approved by the COR prior to use in the service contract.
10.2 The contractor will be responsible for submitting the manufacture specifications; MSDS sheets and equipment cut sheets for all equipment, chemicals (including chemical composition), and testing procedures in English language.
10.3 The Contractor shall test the wastewater treatment system for proper operating conditions through field-testing and shall adjust the plant to bring it into compliance with the required operating parameters as specified in Exhibit A Statement of Work
10.4 The Contractor will be responsible for the sewer collection system cleaning, inspection and maintenance as specified in Exhibit A Statement of Work.
SAFETY HEALTH AND ENVIROMENTAL MANAGEMENT (SHEM)
11.1 The Contractor shall take all reasonable and proper safety precautions to prevent death or injury to any person or damage to any property at the US Embassy _New Embassy___ Compound and in particular all equipment used by the Contractor shall be used in such a manner and maintained so as to minimize the danger of accident, death, injury, loss or damage arising from the use of such equipment. In addition to relevant statutory requirements, standards and other provisions of this Contract, the Contractor shall have the following requirements:
1.1.1 The Contractor’s personnel shall be knowledgeable with and adhere to all relevant occupational health and safety rules, regulations, standards, and SDS sheets.
1.1.2 All electrical equipment and associated materials for the Services Contract comply with UL requirements.
1.1.3 Follow all NFPA guidelines against fire, production of smoke or the venting of any noxious substances
1.1.4 Ensure that the Contractor’s personnel comply with all safety procedures and requirements
1.1.5 Ensure that the Contractor’s personnel are adequately trained and instructed in the safe and correct usage, handling and operation of materials and equipment relevant to the Services and provide reasonable proof of such to the US Embassy Abuja on request.
1.1.6 Ensure the Contractor’s personnel are certified as having completed occupational health and safety training and have been issued all the necessary Personal Protection Equipment (PPE) required for safe implementation of this contract;
1.1.7 Training program(s) shall be presented and must satisfy the US Embassy Abuja during the submittal process.
MAINTENANCE SPECIFICATION DETAILS
12.1 Precedence of Specifications. If and to the extent that there is an inconsistency between this maintenance specification and any Manufacture’s maintenance specification, the Manufacture’s maintenance specification shall prevail.
12.2 Hours of Work. The Contractor shall schedule all preventive maintenance during normal working hour which are defined as 07:30 – 16:30 hours, Mondays to Thursdays and 07:30 – 13:30 hours on Fridays, inclusive of periodic maintenance that may be required on Saturdays, with the exception of any regular or special public holidays (see 2017 holiday table below) on which the US Embassy Compound is not open, or as agreed with the US Embassy prior to commencement of the contract.
| Month |
| Date/Day of the Week |
| Holiday |
| US or Nigerian Holiday |
| JAN |
| 01 / Tuesday |
| New Year’s Day |
| US / Nigeria |
| JAN |
| 21 / Monday |
| Martin Luther King Day |
| US |
| FEB |
| 18 / Monday |
| Presidents’ Day |
| US |
| APR |
| 19 / Friday |
| Good Friday |
| Nigeria |
| APR |
| 22 / Monday |
| Easter Monday |
| Nigeria |
| MAY |
| 01 / Wednesday |
| Workers’ Day |
| Nigeria |
| MAY |
| 27 / Monday |
| U.S. Memorial Day |
| US |
| JUN |
| 05 / Wednesday |
| Eid-El-Fitri** |
| Nigeria |
| JUN |
| 12 / Wednesday |
| Democracy Day |
| Nigeria |
| JUL |
| 04 / Thursday |
| Independence Day |
| US |
| AUG |
| 12 / Monday |
| Eid-El-Kabir** |
| Nigeria |
| SEP |
| 02 / Monday |
| Labor Day |
| US |
| OCT |
| 01 / Tuesday |
| Independence Day |
| Nigeria |
| OCT |
| 14 / Monday |
| Columbus Day |
| US |
| NOV |
| 11 / Monday |
| Eid-El-Maulud** |
| Nigeria |
| NOV |
| 11 / Monday |
| Veterans Day |
| US |
| NOV |
| 28 / Thursday |
| Thanksgiving |
| US |
| DEC |
| 25 / Wednesday |
| Christmas Day |
| US / Nigeria |
| DEC |
| 26 / Thursday |
| Boxing Day |
| Nigeria |
US = American Holidays; Nigeria = Nigerian Holidays; US & Nigeria = American and Nigerian Holidays.** These dates are Muslim holidays and subject to change on Lunar Cycle.
SCOPE OF WORK
13.1 The Contractor shall visit the US Embassy annually for a 5-day consecutive intervals (agreed to between the COR, Facility Manager, and the Contractor). The contractor shall be responsible for all logistics including but not limited to transportation and hotel reservations for their staff.
13.2 The Contractor shall provide documented chemicals that have a storage life expectance of at least 1 year.
13.6 The Contractor shall determine the dosage levels of chemicals and stay within the operating parameters specified under Exhibit A Statement of Work.
13.8 The Contractor shall provide 5 hours of instruction annually in English to familiarize operators in necessary water treatment tests, the control ranges for each treatment chemical, safe handling of equipment and chemicals, and new water treatment procedures/technologies.
13.9 During each site visit to the plant, the Contractor shall review the plant operator daily operating logs to verify safe and effective operation of the plant. The Contractor will highlight all areas where plant-operating conditions are outside of acceptable operating range, and shall provide instruction on how to correct the deficiency.
13.10 The Contractor shall review the routine wastewater treatment testing results from the US Embassy monthly and respond to the facility management staff at the US Embassy within 24 hours if changes to the collection system and/or treatment plant operations are recommended to reestablish effective and efficient wastewater treatment to meet discharge standards. This contract shall also discuss the wastewater treatment plant conditions and the water quality of the effluent with the COR, Facility Manager and operating engineers and follow up with a written service report within ten (10) business days after each visit. The report shall be in English and contain the results of wastewater treatment contractor’s on-site tests, comments on the status of each system, and specific recommendations for action if necessary.
13.11 The Contractor shall perform the required services as described in Exhibit A – Wastewater Collection and Treatment System.
ACCESS TO GOVERNMENT BUILDINGS AND STANDARDS OF CONDUCT
14.1 The Contractor shall designate a representative who shall supervise the Contractor’s technicians and be the Contractor's liaison with the US Embassy Abuja. The Contractor's employees shall be on-site only for contractual duties and not for any other business or purposes. Contractor employees shall have access to the systems dedicated rooms with or without security escorts, only with specific permission by the Facility Manager, Contracting Officer, or the COR.
14.2 Personnel Security: The US Embassy reserves the right to deny access to U.S owned and U.S.-operated facilities to any individual. The Contractor shall provide the names, biographic data and police clearance on all Contractor personnel, who shall be used on this contract prior to their utilization on this contract.
14.3 STANDARDS OF CONDUCT.
14.3.1 General: The Contractor shall maintain satisfactory standards of employee competency, conduct, cleanliness, appearance, and integrity and shall be responsible for taking such disciplinary action with respect to employees as necessary. Each Contractor employee shall adhere to standards of conduct that reflect credit on themselves, their employer, and the United States Government. The US Embassy reserves the right to direct the Contractor to remove an employee from the worksite for failure to comply with the standards of conduct. The Contractor shall immediately replace such an employee to maintain continuity of services at no additional cost to the Government.
14.3.2 Uniforms and Personal Equipment. The Contractor's employees shall wear clean, neat and complete uniforms when on duty. The Contractor shall provide, to each employee and supervisor, uniforms and personal equipment. The Contractor shall be responsible for the cost of purchasing, cleaning, pressing, and repair of the uniforms.
14.3.3 Neglect of Duties. Neglect of duties shall not be condoned. This includes sleeping while on duty, unreasonable delays or failures to carry out assigned tasks, conducting personal affairs during duty hours and refusing to render assistance or cooperate in upholding the integrity of the worksite security.
14.3.4 Intoxicants and Narcotics. The Contractor shall not allow its employees while on duty to possess, sell, consume, or be under the influence of intoxicants, drugs or substances which produce similar effects.
EXHIBIT A
Statement of Work Wastewater Collection and Treatment System
I. GENERAL INFORMATION:
The United States Embassy in Abuja requires professional services and contractor cost proposals to perform preventive maintenance services of the facility’s Waste Water Collection and Treatment System.
II. PROJECT REQUIREMENTS:
1. The sanitary sewer collection system includes the following Oil/water Separators Quantity: 1
Lift Stations Quantity: 2 Pumps: Quantity 4 Manufacturer/model: GOULDS Pump. Model B3888ZD4 Electrical (1.5-5HP, 200-380voltage, 50Hz, 3phase):
2. The wastewater treatment package plant information is as follows
Wastewater Treatment Package Plant:
Manufacturer:_JET INC., Model No._MBBR 26500GPD
The plant’s rated capacity is 26,500 gallons per day domestic sewage
DESCRIPTION OF EQUIPMENT:
Attachment 1 provides a detailed equipment list of the items to be maintained.
III. GENERAL REQUIREMENTS:
The Contractor SOW shall provide all labor, tools, and materials required to carry out all preventive maintenance as outlined in this SOW. US Embassy staff may have service manuals for all equipment included in this SOW. If they do not, the Contractor shall assist Embassy Staff in obtaining the manuals.
IV. SCOPE OF WORK - PREVENTIVE MAINTENANCE
Contractor shall provide all materials, supervision, labor, tools and equipment to perform preventive maintenance. All personnel working in the vicinity shall wear and /or use appropriate safety protection while all work is performed. Any questions or injuries shall be brought to the attention of the Post Occupation Safety and Health Officer (POSHO) immediately. Safety Data Sheets (SDS) shall be provided by the Contractor for all HAZMAT materials. Copies shall be submitted to the COR for approval.
At a minimum, the following work must be done:
Waste Water Collection and Treatment Plant Preventive Maintenance:
i. MAINTENANCE DESCRIPTION:
The maintenance tasks and procedures provided below describe the checks, tests, analysis and tasks required to perform annual, semi-annual and quarterly preventive maintenance for the wastewater collection system and treatment plant.
ii. SAFETY & SPECIAL INSTRUCTIONS:
1. Follow procedures in the O&M Manuals for specific equipment.
2. Follow site safety procedures and your supervisor’s instructions.
3. Record and report any equipment damage or deficiencies.
4. Record maintenance information.
5. Maintenance personnel shall be trained on the health hazards of working near sewage plant operations.
6. Maintenance personnel shall be trained, certified, have appropriate equipment and safety plans before and Post approval prior to confined space entry.
7. Follow the manufacturer’s instructions.
8. Wear proper protective equipment.
9. DO NOT ENTER THE SEPTIC TANK. Hazards exist in a septic system. All precautions must be followed when inspecting the system. Keep tank openings covered at all times. Only authorized service personnel should service a septic system. Lethal gases, high voltage electricity, and other deadly hazards associated with the system. Only qualified service staff should open access ports and/or covers. Infectious organisms exist in a septic tank. If any contact with wastewater, immediately wash and disinfect all exposed areas and contact personal physician. Failure to do so could result in severe sickness or death. DO NOT use flame or spark near a septic tank access points. Gases emanating from septic tanks can explode if ignited or deadly if inhaled.
iii. MAINTENANCE PROCEDURES:
Wastewater Collection System
Sewage Lift Station
1. Inspect each lift station in the sanitary collection system and assure that all pumps are operational, that all pump control systems are operating correctly, that on-off floats and high-level alarm floats are operating correctly, and that pump lead-lag controls are operating correctly.
2. Check lift station lighting, power and ventilation systems for proper operation.
3. Check for leaks on suction and discharge piping, seals, packing glands, etc., make minor adjustments as required.
4. Disconnect the lift station pumps discharge pipe from the inlet bar screen of equalization tank, and then connect it to the existing by-pass system.
5. Drain the wastewater from all the tanks.
6. Remove all the sludge and deposits from the tanks.
7. Wire brush, clean and power wash the lift station.
8. Remove the pumps, check and clean.
9. Check the air diffuser and clean.
10. Paint all rusted metal.
11. Connect the lift station pumps discharge pipe back to the inlet bar screen.
12. Clean-up area and return to normal service.
13. Inspect electrical wiring for damage.
14. Check V-belts for proper tension and wear. Replace when necessary
Wastewater Treatment Plant
Pretreatment (Bar Rack and Grit Drive)
1. Check with facilities and operation staff for deficiencies.
2. Inspect the bar rack for integrity and cleanliness. Clean Bar rack and properly dispose of solid wastes if necessary.
3. Check condition and clearance of cutting knives and inspect base seal.
4. Check oil level in gearbox, add oil if necessary.
5. Wire brush and lubricate directional flow valve stem.
6. Check for rust and corrosion; scape, wire brush and spot paint as necessary.
7. Check grit pump packing for leakage.
8. Inspect grit chamber
9. Sharpen /replace comminutor blades when cutting edge is worn
10. Fill out maintenance checklist and report deficiencies.
Annually:
1. Change oil in gearbox
Equalization Tank
1. Inspect the equalization tank and remove any accumulated solids from the bottom. Inspect the submersible transfer pumps in the equalization tank and assure that all pumps are operational, that all pump control systems are operating correctly, that on-off floats and high-level alarm floats are operating correctly, and that pump lead-lag controls are operating correctly.
2. Check level sensor for proper operation and level settings
3. Check pump valves for proper setting on flow to splitter box and feed–back
4. Clean any grease and floating solids from walls and water surface of equalization tank.
5. Measure the discharge rate from the equalization tank to the aeration tank. Adjust the return weir to assure the lowest transfer rate into the aeration tank possible within the limitations of the equalization tank volume and ability to equalize post maximum daily flow rates.
6. Fill out maintenance checklist and report deficiencies.
Aeration
1. Inspect the aeration tank for evidence of proper rolling of mixed liquor suspended solids (MLSS), fine bubble production from the air diffuser heads, and even diffusion along the length of the aeration tank.
2. Measure the dissolved oxygen in the aeration tank and adjust the blower run intervals accordingly to maintain an average of 1-2 mg/L DO.
3. Conduct a mixed liquor suspended solids (MLSS) settling test of one sample from the aeration basin and one from the effluent from the settling tank. Take readings at five, thirty, and sixty minutes.
4. Inspect the blowers for proper operation. Replace the air filters if dirty, but no less frequently than once every 6-months
5. Visually check aeration system for even air distribution, with no dead spots
6. Check oil level in mechanical aerator gear cases. Add or remove as necessary per manufacturer’s instructions.
7. Check oil level in blower gear cases. Add or remove as necessary per manufacturer’s instructions.
8. Check for air leaks around base and fitting of blower
9. Check and inspect blower belts for wear and tension.
10. Check bolts and tighten if necessary: foundation, cylinder head, belt guard, etc.
11. Check tension, condition, and alignment of V-belts on blower; adjust or replace as necessary.
12. Check oil level of commutator. Add or remove as necessary per manufacturer’s instructions.
13. Check the blower to make sure that belts and drives are free of obstruction and all electrical connection are complete including thermal protection if applicable.
14. Check that effluent weir trough and weir is level and set to the correct elevation and adjust if necessary
15. Check blowers at a minimum speed and listen for unusual noises
16. Check the airlift pumps operate continuously and the total pumping rate should be approximately equal to the incoming raw sewage average flow rate
17. Inspect the sludge digester (also known as the holding tank) where applicable. Pump and clean the tank if settled sludge exceeds 75% of the depth of the tank. Check the airflow in the digester for proper operation.
18. Scrape walls and hoppers of settling tank
19. Fill out maintenance checklist and report deficiencies.
Semi-Annually:
1. Change blower / mechanical aerator / comminutor oil
Clarification
1. Inspect the clarifier for cleanliness and clean if required. Inspect the overflow weir cleanliness and uniformity of overflow along the weir. Clean the weir with a brush if required.
2. Inspect the Return Activated Sludge (RAS) airlift pump for proper operation and flow.
3. Inspect the clarifier skimmer airlift pump for proper operation and flow. Clean and adjust the pump as required.
4. Clean clarifier drive and surrounding area.
5. Fill out maintenance checklist and report deficiencies Annually:
1. Check unit for rust and corrosion; scape, wire brush and paint as required.
2. Drain and refill gearbox oil reservoir.
UV Disinfection. No UV and Chlorination System on the WWTP.
Semi-Annually:
1. Disassemble and clean the various components of the system, such as meters and floats.
Annually:
1. Inspect and clean valves and springs
2. All tanks, boxes and basins, should be drained, inspected for scale buildup, rust, corrosion, and cleaned as necessary. Any painted surfaces should be inspected for rust and corrosion, cleaned and re-painted if necessary
EXHIBIT A:
Wastewater Testing and Operating Parameters
Dissolved Oxygen (DO) Goal: DO = 1.0 – 2.0 mg/L Turn blowers off, and wait 5 – 10 minutes. Take sample from aeration basin and test immediately after sampling. If over the course of several tests during the 2-day maintenance visit, the DO is consistently too low, increase the amount of time that blowers are running. If the DO is consistently too high, decrease the amount of time that blowers are running. The wastewater treatment plant contractor will decrease/increase blower run times by small intervals not to exceed 15-minute increments.
Free and Total Chlorine Goal Free Chlorine = 0.5 – 1.5 mg/L If the plant has a chlorine contact tank, test the effluent being discharged from the plant. If free chlorine residuals do not meet the goals, the wastewater treatment plant contractor will adjust the chlorination rate. If free chlorine readings are consistently above the goal, reduce the amount of chlorination. If the readings are consistently below the goal, increase the amount of chlorination.
Chlorine Contact Time Goal CT = 20 mg/L-minutes The wastewater treatment plant maintenance contractor will measure the flow rate of the effluent discharged from the plant at peak hour flows and will calculate the disinfection contact time of the plant (time between injection of chlorine and the discharge of the effluent from the plant). The CT is calculated by multiplying the free chlorine residual (in mg/L) by the contact time. The wastewater treatment plant maintenance contractor will notify the Facility Manager if the CT is significantly less than the goal.
Chemical Oxygen Demand (COD) Goal = 50 mg/L The wastewater treatment plant contractor will sample the plant effluent for Chemical Oxygen Demand (COD). If the COD significantly exceeds the goal, the cleanliness of the plant and the effectiveness of the clarifier weirs will be checked and corrected by the contractor.
Total Suspended Solids (TSS) Goal = 30 mg/L The wastewater treatment plant contractor will sample the plant effluent for Total Suspended Solids. If the TSS readings consistently exceeds the goal, the contractor will increase the frequency of scraping the clarifier and scrubbing the overflow weirs. The contractor will check for proper operation of the clarifier skimmer.
RFQ #PR7900975 - BME for NEC Waste Water Treatment System
Attachment 1: Equipment List:
END OF STATEMNT OF WORK
SECTION 2 - CONTRACT CLAUSES
FAR 52.212-4 CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS (OCT 2018), is incorporated by reference (see SF-1449, Block 27A)
52.212-5 Contract Terms and Conditions Required To Implement Statutes or Executive Orders - Commercial Items (OCT 2018) and (Deviation 2017-02) (June 2017)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).
(3) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).
(4) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004)(Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
[Contracting Officer check as appropriate.] __ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sept 2006), with Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).
__ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Oct 2015) (41 U.S.C. 3509)).
__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (June 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)
_x_ (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Oct 2016) (Pub. L. 109-282) (31 U.S.C. 6101 note).
__ (5) [Reserved].
__ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
_ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
_x_ (8) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (Oct 2015) (31 U.S.C. 6101 note).
__ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Jul 2013) (41 U.S.C. 2313).
__ (10) [Reserved].
__ (11)(i) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Nov 2011) (15 U.S.C. 657a).
__ (ii) Alternate I (Nov 2011) of 52.219-3.
__ (12)(i) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Oct 2014) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).
__ (ii) Alternate I (Jan 2011) of 52.219-4.
__ (13) [Reserved] __ (14)(i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2011) (15 U.S.C. 644).
__ (ii) Alternate I (Nov 2011).
__ (iii) Alternate II (Nov 2011).
__ (15)(i) 52.219-7, Notice of Partial Small Business Set-Aside (June 2003) (15 U.S.C. 644).
__ (ii) Alternate I (Oct 1995) of 52.219-7.
__ (iii) Alternate II (Mar 2004) of 52.219-7.
__ (16) 52.219-8, Utilization of Small Business Concerns (Nov 2016) (15 U.S.C. 637(d)(2) and (3)).
__ (17)(i) 52.219-9, Small Business Subcontracting Plan (Jan 2017) (15 U.S.C. 637(d)(4)).
__ (ii) Alternate I (Nov 2016) of 52.219-9.
__ (iii) Alternate II (Nov 2016) of 52.219-9.
__ (iv) Alternate III (Nov 2016) of 52.219-9.
__ (v) Alternate IV (Nov 2016) of 52.219-9.
__ (18) 52.219-13, Notice of Set-Aside of Orders (Nov 2011) (15 U.S.C. 644(r)).
__ (19) 52.219-14, Limitations on Subcontracting (Jan 2017) (15 U.S.C. 637(a)(14)).
__ (20) 52.219-16, Liquidated Damages.Subcon-tracting Plan (Jan 1999) (15 U.S.C. 637(d)(4)(F)(i)).
__ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (Nov 2011) (15 U.S.C. 657 f).
__ (22) 52.219-28, Post Award Small Business Program Representation (Jul 2013) (15 U.S.C. 632(a)(2)).
__ (23) 52.219-29, Notice of Set-Aside for, or Sole Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (Dec 2015) (15 U.S.C. 637(m)).
__ (24) 52.219-30, Notice of Set-Aside for, or Sole Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (Dec 2015) (15 U.S.C. 637(m)).
__ (25) 52.222-3, Convict Labor (June 2003) (E.O. 11755).
_x_ (26) 52.222-19, Child Labor. Cooperation with Authorities and Remedies (Oct 2016) (E.O. 13126).
__ (27) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).
__ (28) 52.222-26, Equal Opportunity (Sept 2016) (E.O. 11246).
__ (29) 52.222-35, Equal Opportunity for Veterans (Oct 2015)(38 U.S.C. 4212).
__ (30) 52.222-36, Equal Opportunity for Workers with Disabilities (Jul 2014) (29 U.S.C. 793).
__ (31) 52.222-37, Employment Reports on Veterans (Feb 2016) (38 U.S.C. 4212).
__ (32) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).
_x_ (33)(i) 52.222-50, Combating Trafficking in Persons (Mar 2015) (22 U.S.C. chapter 78 and E.O. 13627).
__ (ii) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).
__ (34) 52.222-54, Employment Eligibility Verification (Oct 2015). (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)
__ (35)(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (May 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
__ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
__ (36) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) (E.O. 13693).
__ (37) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (Jun 2016) (E.O. 13693).
__ (38)(i) 52.223-13, Acquisition of EPEAT®-Registered Imaging Equipment (Jun 2014) (E.O.s 13423 and 13514).
__ (ii) Alternate I (Oct 2015) of 52.223-13.
__ (39)(i) 52.223-14, Acquisition of EPEAT®-Registered Televisions (Jun 2014) (E.O.s 13423 and 13514).
__ (ii) Alternate I (Jun 2014) of 52.223-14.
__ (40) 52.223-15, Energy Efficiency in Energy-Consuming Products (Dec 2007) (42 U.S.C. 8259b).
__ (41)(i) 52.223-16, Acquisition of EPEAT®-Registered Personal Computer Products (Oct 2015) (E.O.s 13423 and 13514).
__ (ii) Alternate I (Jun 2014) of 52.223-16.
_x_ (42) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging While Driving (Aug 2011) (E.O. 13513).
__ (43) 52.223-20, Aerosols (Jun 2016) (E.O. 13693).
__ (44) 52.223-21, Foams (Jun 2016) (E.O. 13693).
__ (45)(i) 52.224-3, Privacy Training (JAN 2017) (5 U.S.C. 552a).
__ (ii) Alternate I (JAN 2017) of 52.224-3.
__ (46) 52.225-1, Buy American.Supplies (May 2014) (41 U.S.C. chapter 83).
__ (47)(i) 52.225-3, Buy American.Free Trade Agreements.Israeli Trade Act (May 2014) (41 U.S.C. chapter 83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub. L. 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.
__ (ii) Alternate I (May 2014) of 52.225-3.
__ (iii) Alternate II (May 2014) of 52.225-3.
__ (iv) Alternate III (May 2014) of 52.225-3.
__ (48) 52.225-5, Trade Agreements (Oct 2016) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).
_x_ (49) 52.225-13, Restrictions on Certain Foreign Purchases (June 2008) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
__ (50) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).
__ (51) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).
__ (52) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov 2007) (42 U.S.C. 5150).
_x_ (53) 52.232-29, Terms for Financing of Purchases of Commercial Items (Feb 2002) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).
__ (54) 52.232-30, Installment Payments for Commercial Items (Jan 2017) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).
_x_ (55) 52.232-33, Payment by Electronic Funds Transfer.System for Award Management (Jul 2013) (31 U.S.C. 3332).
_x_ (56) 52.232-34, Payment by Electronic Funds Transfer.Other than System for Award Management (Jul 2013) (31 U.S.C. 3332).
__ (57) 52.232-36, Payment by Third Party (May 2014) (31 U.S.C. 3332).
__ (58) 52.239-1, Privacy or Security Safeguards (Aug 1996) (5 U.S.C. 552a).
__ (59) 52.242-5, Payments to Small Business Subcontractors (Jan 2017)(15 U.S.C. 637(d)(12)).
__ (60)(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx. 1241(b) and 10 U.S.C. 2631).
__ (ii) Alternate I (Apr 2003) of 52.247-64.
(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of…
This is the start of the file's text. The full file is on GovTribe.