RESPONSE_TO_QUESTIONS_-_PR___7899019.docx

DOCX document 15 KB Posted

Attached to
PM FOR POWER MONITORING AND CONTROL SYSTEM
Solicitation number
RFQ7899019
Issued by

About this file

ANSWERS TO QUESTIONS RAISED AND HOW TO PRESENT YOUR OFFER

View the file

Other files

File Type Posted
7899019__COVER_LETTER.pdf PDF
7899019__REVISED_SOW_FOR_PM_OF_NEC_PMCS_2019.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RESPONSE TO QUESTIONS

RFP # 7899019/GSA e-Buy RFQ1343791 "Preventive Maintenance For Power monitoring and Control System"

· Is the most convenient airport for personal to utilize Nnamdi Azikiwe International Airport? Yes, but your travel agent will advise you better on travel matters

· What type of Visa is required? Normal regular visa

· Is there any lodging available on the embassy property? None

· Are there any meals available on the embassy property? There is a cafeteria, but not free

· Will any of this scope be performed in a CAA or PCC area? Yes Reference SOW Section 7.1.6

· If so can a secret clearance be issued for this purpose? Is there such a thing a job specific or temporary clearance?

· Can one of our people with a top-secret clearance escort our other personnel?

· How and where are tools and equipment received in the embassy? To be Coordinated with COR

· Is there any standard means of this for construction projects? No

· Can contractor tools and equipment be stored on the embassy property? Yes

· Will Federal Express packages be received by the embassy? Yes

· Does the embassy offer a truck dock and fork truck for contractor use? If required, the need will be addressed as appropriate.

· Is a one-line diagram of each of the electrical distribution systems in this scope available? Yes to be provided during project performance

· Is there a count and type of equipment / breakers available including trip unit model numbers? Yes to be provided during project performance

· Is the embassy served by a public electric utility? Yes

· If so will an electrical outage for this scope be required? N/A

· Who is responsible for facilitating any required electrical outage with public utility?N/A

· Will it be possible to work 4 continuous days at a minimum of 8 hours each day? Yes

· Is any site-specific training or orientation required? To be coordinated with the COR

· If so, how much time should be allowed?

NOTE: PROPOSALS SHOULD BE SUBMITTED IN TWO ATTACHMENTS:

1. PRICE PROPOSAL USING THE FORMAT IN THE RFP

2. TECHNICAL PROPOSAL WITHOUT PRICING INFORMATION USING THE SOLICITATION PACKAGE INCLUDING INFORMATION SHOWING CAPACITY TO PERFORM THE CONRACT