This document is a Contract Discrepancy Notice for a contract for TYPE III BARRICADE HAULING TRAILERS between the Idaho Transportation Department (ITD) and the Contractor. The notice identifies discrepancies found by ITD while monitoring the Contractor's performance, including details on the specific discrepancies, the contract requirements the Contractor is out of compliance with, the required corrective actions, and the Contractor's proposed resolutions and estimated resolution dates. The document also includes sections for ITD to indicate whether the Contractor's proposed resolutions are accepted, partially accepted, or rejected, as well as space for the Contractor to acknowledge the discrepancies and their responsibility for resolution.

The related state and local contract opportunity is for the procurement of TYPE III Barricade Hauling Trailers, to be performed in the state of Idaho. No additional details are provided regarding the quantities, pricing, or other terms of this contract opportunity.

View the file

Other files

File Type Posted
RFQ373- Attachment 1 - Requirements Specifications - Barricade Hauling Trailers.docx DOCX document
RFQ373- Attachment 3 - Signature Page.docx DOCX document
RFQ373- Attachment 4 - Deliverable Acceptance Form.docx DOCX document
Solicitation Instructions.pdf PDF
amendment acknowledge.docx DOCX document
Insurance Requirements 2023.docx DOCX document
RFQ373 Attachment 6 - Idaho Code 67-2359 Acknowledgement.docx DOCX document
solicitation_instructions Jan 2017.pdf PDF
RFP Event 204 Administrative Document.docx DOCX document
Event 104 Administration Document.docx DOCX document
Signature Page ITB RFP August 2020.pdf PDF
Standard Terms and Conditions_May 2021.pdf PDF
Event 182 Administration Document.docx DOCX document
4_PERSI_OnBase-Statistics_September-2024.pdf PDF
PERSI OnBase report.pdf PDF
RFQ373 - Attachment 7 - Idaho Disclosure of Abortion Related Matters Acknowledgement.docx DOCX document
RFQ373- Attachment 2 - Price Sheet.docx DOCX document
Attachment 4 Lease agreement.docx DOCX document
ITB_Attachment 2-Bid Schedule.docx DOCX document
1_Arrivos-OnBase Integration.pdf PDF
2_Arrivos WorkFlow Table .xlsx XLSX spreadsheet
3_PERSI-DocTypes-with-Annual-Volume.xlsx XLSX spreadsheet
IDOL's OnBase Screenshots for RFP.docx DOCX document
Labor OnBase Licenses.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ373 - Attachment 5 - Contract Discrepancy Notice

Contract No:
TBD
Contract Name:
TYPE III BARRICADE HAULING TRAILERS

Discrepancy Information: This Contract Discrepancy Notice identifies the Discrepancy(ies) found by ITD while monitoring the Contractor’s performance required per the referenced contract. Items identified as “Discrepancy” require a response from the Contractor. Items identified as “Observation” are areas of concern that may lead to a future Discrepancy if not addressed. Observations do not require a response unless otherwise noted in this notice.

ITD has identified the following Discrepancy(ies):

(Add additional tables for multiple discrepancies)

Description of Discrepancy:
Describe the discrepancy in detail and explain how the contractor is out of compliance. Attach photos or other supporting documents and reference here.
Contract Reference:
Site the document name, attachment #, and section # of the requirement out of compliance.
Required Action:
Site the required corrective action from the contract.
Contractor’s Resolution:
Contractor to describe action that will be taken to correct the discrepancy in order to become compliant with the contract.
Estimated Resolution Date:
Contractor to provide estimated date it anticipates resolving the discrepancy by.

ITD Contract Monitor - Check appropriate box with regard to Contractor’s resolution

Accept ☐
Partially Accept ☐
Reject ☐

Reason for Rejection or Partially Accepted

Anticipated Follow Up Date on Resolution

ITD Contract Monitor Signature

Date

Contractor - Sign below to indicate your understanding of the Discrepancy(ies) and your responsibility for resolution.

Contractor Printed Name

Title

Contractor Signature

Date

Resolution

ITD Contract Monitor – Sign below to indicate that each Discrepancy has been resolved based on the actions detailed in the Contractor’s Resolution for each Discrepancy.

ITD Contract Monitor Signature

Date

ITD has identified the following Observations (no response required):

Description of Observation:
Describe the observation in detail and explain how it may lead to a non-compliance issue in the future. Attach photos or other supporting documents and reference here.
Contractor’s Response (optional):
Contractor to describe action that will be taken to correct the discrepancy in order to become compliant with the contract.

1 | Page dhb