rfq2404dhart00086rb.pdf
PDF 1 MB Posted
- Attached to
- TxDOT Aviation Division- Notice to Consultants
- Solicitation number
- RFQ2404DHART00086
- Issued by
- Dallam County, Texas
About this file
This document is a Request for Qualifications (RFQ) issued by the Texas Department of Transportation (TxDOT) on behalf of the City of Dalhart for professional engineering services related to the Dalhart Municipal Airport. The scope of work includes providing engineering and design services, including construction administration, for the rehabilitation of the airport apron. The DBE goal for the design phase is 4%, and the goal will be re-set for the construction phase. Responses to the RFQ must be submitted through the TxDOT eGrants system by August 6, 2024, at 2:00 p.m. (CST). The selection committee will review and rank the responses, and the top-rated firm will be contacted for fee negotiations for the design and bidding phases. The selected firm must have a Texas-licensed Professional Engineer as the project manager, and an Architect registered in Texas if applicable.
The evaluation criteria for the RFQ include the project team's recent experience with comparable airport projects, the proposed technical approach, the project design schedule and ability to meet deadlines, and the firm's construction management experience. The consultant selection committee will be composed of local government representatives, and interviews may be conducted with the top-rated firms if deemed necessary.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| rfq2404dhart00086rb.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
DALHART MUNICIPAL AIRPORT - REBID
TXDOT SOLICITATION NO.: RFQ-2404DHART-00086RB
1. REQUEST FOR QUALIFICATIONS SOLICITATION
2. EVALUATION CRITERIA
3 INSTRUCTIONS FOR RESPONDING TO A SOLICITATION IN EGRANTS
4. PROJECT DIAGRAM
5. AIRPORT LAYOUT DRAWING
TxDOT Solicitation No.: RFQ2404DHART00086RB TxDOT CSJ/Project No.: 2404DHART
Texas Department of Transportation Aviation Division
Request for Qualifications (RFQ) for Professional Engineering Services
The City of Dalhart, through its agent, the Texas Department of Transportation (TxDOT), intends to engage a professional engineering firm for services pursuant to Chapter 2254, Subchapter A, of the Government Code. TxDOT Aviation Division will solicit and receive qualification statements for the current aviation project as described below.
Current Project: City of Dalhart; TxDOT CSJ/Project ID: 2404DHART.
The TxDOT Project Manager is Paul Slusser.
Scope: Provide engineering and design services, including construction administration, to: Apron Rehabilitation.
The Agent, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat.
252, 42 U.S.C. §§ 2000d to 2000d-4) and the Regulations, hereby notifies all respondents that it will affirmatively ensure that for any contract entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full and fair opportunity to submit in response to this solicitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.
The proposed contract is subject to 49 CFR Part 26 concerning the participation of Disadvantaged Business Enterprises (DBE).
The DBE goal for the design phase of the current project is 4%. The goal will be re-set for the construction phase.
To assist in your qualification statement preparation, the criteria, project diagram, and most recent Airport Layout Plan are available online at http://www.dot.state.tx.us/avn/avninfo/notice/consult/index.html by selecting “Dalhart Municipal Airport.” The qualification statement should address a technical approach for the current scope only.
Response Procedure:
The successful firms will be selected on the basis of a Response. A prime provider may only submit one Response. If a prime provider submits more than one Response, that prime provider will be deemed non-responsive. The Response must contain the required information, and should address the recommended information, as listed below. Response submissions will be scored accordingly.
If the Response is non-compliant with any of the following requirements, the Response may be deemed non-responsive.
http://www.dot.state.tx.us/avn/avninfo/notice/consult/index.htm
1. Qualifications Statement (QS) – The QS shall contain no more than nine
8.5x11-inch single-sided pages.
a. QS Format:
i. Readability – The submitter has latitude in formatting the QS for visual effectiveness. Graphics, tables, photos, and other visual aids are permitted within the nine allotted pages, except that Quick Response (QR) codes or other external link(s) are not permitted. There is no specific font, font size, color, or other formatting requirements, although a font size smaller than 10 is not recommended. Selection committee members may consider legibility and readability when scoring. Unreadable text will not be considered and may cause the QS to be deemed non-responsive. It is the submitter’s responsibility to provide a legible, readable document.
b. QS Content - It is recommended the QS include:
i. The RFQ number, airport name, name of firm, firm address, email address, telephone number and contact information for key personnel. The response shall also identify each proposed project team member, each proposed member’s time commitment to this project as a percentage of their total work week, and whether the proposed member is an employee of the responding firm or a sub-contractor to that firm.
c. QS Content – For scoring purposes, the QS must include:
i. Information showing the firm’s project understanding and technical approach, including similar project-related experience of the project manager and each task leader responsible for a major work category. For each project referenced, identify either the project manager’s or the task leader’s specific role(s) and work contributed. The project manager is required to be a Professional Engineer registered or licensed in Texas, by the submission deadline. If applicable to project, an Architect, is required to be registered or licensed in Texas, by the submission deadline. License number(s) must be included in the response submission.
ii. In addition to individual project-related experience of the project manager and task leaders required under (ii), list no more than ten relevant projects performed by the responding firm within the last 10 years. This shall include airport name, location, phone number, and airport contact person’s name, title, and phone number. It shall also include the original project completion time estimate vs. the actual completion time for the cited design project, as well as a brief narrative description of the project and whether or not your firm served as the prime or the sub on each project cited.
iii. Project Design Schedule: Indicate the number of weeks necessary to design the project in accordance with “Project Design Schedule Information” below.
The Response must be submitted in eGrants following the Submission Procedures at the end of this notice.
Project Design Schedule Information
Based on the published project scope and your technical approach, indicate the number of weeks necessary for each phase and total design time to design the project. Some of the basic responsibilities within each design phase are included for reference. Do not include TxDOT review time. Assume, however, that your work will require some revision after TxDOT review, and that the time required to address these comments should be included within your schedule. If time is required for specialized studies, indicate the additional time.
NOTE: This proposed schedule will set the basis for the contract deadlines in the professional services agreement if your firm is selected.
Preliminary Report Phase Attend pre-design conference Obtain and analyze necessary survey data Obtain and analyze necessary geotechnical data Prepare comprehensive report
Final Design Phase Attend project meeting(s) Finalize drawings and contract documents (100%) Provide a revised opinion of probable total project costs Prepare a Construction Management Plan Update, if necessary, the Preliminary Report Prepare and submit airspace study to FAA
Evaluation Criteria for Architectural/Engineering Qualifications
1. Recent experience of the project team with comparable airport projects within the past ten years. (25 points)
Do the qualifications indicate that the project team has recent direct experience on other general aviation airports designing similar improvements to those proposed at this location?
2. Proposed technical approach (30 points)
Does the architect/engineer provide evidence of understanding of the project; and any unique architectural/engineering aspects associated with the proposed project and how to address them?
3. Project design schedule and ability to meet schedules and deadlines (25 points)
Does the proposed design team have sufficient time to work on this project? Has the firm demonstrated an ability to meet design schedules in the past? Reasonableness of proposed schedule.
4. Construction Management Experience (20 points)
The architect/engineer will oversee the airport construction. Therefore, it is critical that the architect/engineer be involved in the day-to-day construction activities through a full-time resident project representative and periodic site visits. What evidence do the qualifications provide as to the architect/engineer’s commitment to proactive and consistent representation during construction?
Submission Procedure:
The completed Response must be received in the TxDOT Aviation eGrants system no later than August 6, 2024, 2:00 p.m. (CST).
Firms that wish to submit a Response to this solicitation must be a user in the TxDOT Aviation eGrants system no later than one business day before the solicitation due date. To request access to eGrants, please complete the Contact Us web form located at http://txdot.gov/government/funding/egrants-2016/aviation.html
The consultant selection committee will be composed of local government representatives. The final selection by the committee will generally be made following the completion of review of Responses. The committee will review all Responses and rate and rank each. All firms will be notified, and the top-rated firm will be contacted to begin fee negotiations for the design and bidding phases. The selection committee does, however, reserve the right to conduct interviews for the top-rated firms if the committee deems it necessary. If interviews are conducted, selection will be made following interviews.
Please contact TxDOT Aviation for any technical or procedural questions at (800)-68-PILOT (74568). For procedural questions, please contact Noemi Rios, Contract Specialist. For technical questions, please contact Paul Slusser, Project Manager.
For questions regarding responding to this solicitation in eGrants, please contact the TxDOT Aviation help desk at 1-800-687-4568 or avn-egrantshelp@txdot.gov.
http://txdot.gov/government/funding/egrants-2016/aviation.html mailto:avn-egrantshelp@txdot.gov eGrants Workflow:
RFQ Response eGrants Role:
Subgrantee Administrator (SA)
Subgrantee Staff (SS) eGrants link eGrants help:
https://apps2.dot.state.tx.us/apps/egrants2/logout2.aspx eGrants help desk Monday – Friday 8AM – 4PM CD/ST (excluding state/federal holidays) avn-egrantshelp@txdot.gov or 1-800-687-4568
STEP ROLE ACTIONS NOTES
SA
Go to View Opportunities.
a. Select Apply Now to the opportunity
b. The RFQ Response Menu is opened
Very important to click on the name of the document and not the organization name.
Make a note of the opportunity due date to ensure you respond in time
SA/SS
Click on View, Edit and Complete Forms
a. Select RFQ Applicant Form
b. Confirm Project information and address
c. Upload RFQ response
PLEASE MAKE SURE YOU SELECT
THE CORRECT PDF FILE BEFORE
CHANGING STATUS.*
d. Hit Save
You should print the proposal document to a PDF so that it becomes un-editable.
SA
When you are ready to submit your response, click on "Save and submit to CS review". YOU ARE
DONE
You will get an email saying the response was successfully submitted; the status must be changed to RFQ Response in CS Review by the due date and time posted in the solicitation.
04 SA/SS WAIT UNTIL A SELECTION NOTIFICATION
IS SENT TO YOU
SS/SA
AFTER SELECTION NOTIFICATION IS
RECEIVED Log in to view status of response.
Once the scores are verified, TxDOT will move the response to an interview, selected or not selected status of which you can log in to see the status of your response.
The selection notification will refer users to eGrants to view the status of their response.
User may also view the TxDOT website for selection information.
Aviation Division https://apps2.dot.state.tx.us/apps/egrants2/logo
*If the responder posts the incorrect file.
• If status has been changed and the due date for the response has not expired, contact the help desk to ask for the status to be administratively changed back to Response in Process.
• If the incorrect submission was posted, the incorrect file may be deleted and the correct one posted as long as the status has not been changed to Response in CS Review. Respondent will need to check the “delete” box and hit save. The page refreshes. Then post the correct submission, save, and change the status.
If you are not set up in eGrants and wish to respond to a posted solicitation, you may contact the aviation help desk for assistance by using the webform available at eGrants Help Desk Form
Some organizations will have many user members. Each organization should determine which user member will submit the completed submission in eGrants. After the opportunity is selected for the organization, it will no longer appear on any other user’s home page unless the initiating user cancels the response.
https://form.jotform.com/62164883455160
Apron Area 1 Rehabilitation
Apron Area 2 Rehabilitation
Dalhart Municipal Airport (KDHT)
Not for design purposes
| Project Exhibit 828863_344022-DHTApronRehabExhibit.pdf |
| Slide 1 |
File details come from the government source that posted it. Updated .