RFQ1240 - Hot Water Pressure Washer Installed.docx
DOCX document 67 KB Posted
- Attached to
- Stationary Pressure Washer with Installation
- Solicitation number
- 1240
- Issued by
- Idaho County, Idaho
About this file
This is a Request for Quote (RFQ) issued by the Idaho Transportation Department (ITD) for the procurement and installation of a stationary hot water pressure washer system at a new highway maintenance building located at 264 E 8th North Preston, Idaho 83263. The solicitation requests quotes for a single Hotsy 1475N hot water electric pressure washer (or equivalent) with full installation services, including all necessary labor, materials, equipment, and supervision. The washer must meet specified performance requirements including 10 horsepower, 5 gallons per minute at 3,000 PSI, three-phase 208-volt electrical power, and natural gas-fired heating capability with a 378,600 BTU/hour output. Installation must be completed within 90 days of receiving a purchase order, with utilities (electrical, natural gas, and water) to be pre-stubbed within 5 feet of the installation location. The RFQ contact is Kirk Anderson, Contracts Officer, and quotes must be submitted electronically via IPRO or email prior to the deadline established in IPRO. Required submittals include a completed price sheet, signature page, and documentation demonstrating that offered equipment meets all specifications.
The award will be made to the responsive and responsible vendor with the lowest cost. Bidders must be authorized distributors or manufacturers of the equipment offered, and equipment must include a manufacturer's standard warranty with a seven-year warranty on the pump; all warranty work must be completed within 30 calendar days of written notice from ITD. The contractor is responsible for all warranty-related costs including labor, parts, travel, and worksite cleanup. Installation must comply with local building codes, the National Electrical Code, National Fuel Gas Code, and OSHA safety requirements. No set-asides are indicated in the solicitation. Invoicing is due within 30 calendar days of acceptance and must be submitted electronically to D5AP@ITD.Idaho.gov. The file does not specify a budget amount, total contract value, or funding source. Communication regarding the RFQ is restricted to the designated RFQ Lead, and any unauthorized communications with ITD staff may result in vendor disqualification.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation_Instructions-July-2025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IDAHO TRANSPORTATION DEPARTMENT
RFQ 1240
HOT WATER STATIONARY PRESSURE WASHER WITH INSTALLATION
ATTACHMENT 1
GENERAL INFORMATION
Purpose The Idaho Transportation Department (ITD) is requesting quotes for the purchase and installation of a stationary pressure washer (Washer) with installation at 264 E 8th North Preston ID , 83263.
Solicitation Contact The contact for this RFQ is:
Name: Kirk Anderson / Contracts Officer Phone: Email: kirk.anderson@itd.idaho.gov (preferred method of contact) Restrictions on Communications From the issue date of this RFQ, until a contract/purchase order is awarded or the RFQ is cancelled, vendors and their representatives are prohibited from communications (written or verbal) regarding this RFQ with the ITD staff, other than the ITD RFQ Lead. Any communications (written or verbal) with ITD staff other than the RFQ Lead may result in the submitting vendor being found Non-Responsible and Non-Responsive.
Requirements and Specifications See Section 1 – Requirements & Specifications See Attachment 3 – Price Sheet See Attachment 4 – Signature Page Quote Your Quote may be submitted electronically via IPRO Powered by LUMA or email (see below for additional details). ITD will not be accepting manual submissions for this solicitation. Your Quote must include the Required Submittals listed below and be received prior to the deadline established in IPRO Powered by LUMA.
Electronic Submission:
IPRO – Enter your pricing in IPRO (https://purchasing.idaho.gov/information-for-vendors/) and upload all Required Submittals.
Email:
Send an email to the Solicitation Contact (see Section 2) and attach all Required Submittals.
Required Submittals:
Attachment 3 – Price Sheet Attachment 4– Signature Page
Documentation, which demonstrates, to ITD’s satisfaction, that the item offered meets the requirements of the solicitation. Failure to provide satisfactory documentation may eliminate the Vendor from further consideration.
(See Sections 1 & 2 – Requirements and Specifications)
| List of Attachments |
| Required Submittal Items |
Attachment 1 – General Information Attachment 2 – Requirements and Specifications Attachment 3 – Price Sheet Attachment 4 – Signature Page Attachment 5 – State of Idaho Insurance Exhibit 1 - Deliverable Acceptance Form Exhibit 2 - Contract Discrepancy Form State of Idaho Standard Terms and Conditions
Attachment 3 – Price Sheet Attachment 4 – Signature Page Equal Compliance Documentation
BACKGROUND INFORMATION
Idaho Transportation Department District 5 is in the final phases of the construction of a new highway’s maintenance building located at 264 E 8th North Preston ID , 83263. This building is to support expanded operational needs, improve service delivery, and provide modern, efficient infrastructure for staff and highways maintenance. As part of the facility’s operational readiness, the agency requires the procurement and installation of a commercial-grade hot water pressure washer system. Power, water, and natural gas are stubbed out to the installation area. This solicitation seeks qualified contractors to furnish all labor, materials, equipment, and supervision necessary to supply and install a complete, fully operational hot water pressure washer system integrated into the building’s mechanical and plumbing systems.
AWARD
Awards will be made to the responsive responsible vendors with the lowest cost.
The State reserves the right not to evaluate or make an award in the best interest of the State.
Though it is not mandatory to submit your Quotation electronically via IPRO, all vendors participating in a solicitation issued through IPRO must establish an account in the IPRO system (even if submitting a quote outside of IPRO). It is free to establish an account and only takes a few minutes of your time.
RFQ 1240
ATTACHMENT 2 – REQUIREMENTS & SPECIFICATIONS
HOT WATER STATIONARY PRESSURE WASHER WITH INSTALLATION
SECTION 1 – REQUIREMENTS
1. MANUFACTURER BRAND COMPONENTS – BRAND NAMES
Any Manufacturer Brand Components referenced in this solicitation are intended to be descriptive—not restrictive—and serve only to illustrate the quality and characteristics required. Bidders proposing an equivalent Manufacturer Brand Component must provide documentation demonstrating, to the State’s satisfaction, that the offered item(s) meet all minimum requirements outlined in the solicitation with the Quote submittal.
If your product offered does not meet any of the specifications, Bidder must provide an explanation of how the product offered is functionally equivalent to the stated specification, as well as descriptive literature that supports the product offered with the Quote Submittal.
Warranty Manufacturer standard warranty must cover the Washer for manufacturers’ standard warranty.
Pump must have a seven (7) year warranty.
Warranty must include all tools, parts, equipment, labor, and freight to repair or replace a defective warranted item, which may also include the entire Washer. All warranty work must be completed within thirty (30) calendars days after receipt of written notice from ITD. If approved in writing by ITD, the Contractor may perform warranty work on-site, at installation location identified in Section 6, in lieu of pick-up and return shipping. The Contractor shall be responsible for all travel costs and work-site clean-up associated with any necessary repairs. The timeframe for corrective action will still be as identified above. If the Contractor is unable to repair the Washer on-site within thirty (30) calendars days, or if the Washer continuously malfunctions and causes it to be out of service on multiple occasions, ITD reserves the right to require the Contractor to pick up, repair, return and install the Washer at no additional cost to ITD.
Authorized Distributor Submitting vendors must be an authorized distributor or manufacturer of the Washer offered. An authorized distributor shall be defined as a company or organization that has a written agreement with the manufacturer to sell or service its products. Quotes from Contractors who are not an authorized distributor by the manufacturer shall not be considered.
Awarded vendor is responsible for all warranty requirements. No third-party warranties will be allowed.
Termination and Cure See section 1.4. State of Idaho Contract Terms and Conditions in the Attachment Tab in IPRO Powered by Luma.
Acceptance ITD will conduct a comprehensive inspection prior to acceptance. The inspection shall include, but not be limited to, inspection and verification of mechanical, electrical, safety, gas, and operational systems; confirmation of manufacturer-recommended fluid levels; installation of all standard and specified equipment; and verification that the washer is free of damage or defects. If the washer fails to meet acceptance requirements it may be rejected.
In the event the specifications are not met, the Contractor must, correct any discrepancies, at no additional cost to ITD. In the event that the Washer does not meet the requirements, specifications, or found with discrepancies that are not fixed by the Contractor during the Acceptance period, ITD reserves the right to reject the Washer via email notification and;
The Contractor will be responsible for providing all labor, tools, parts, supplies, and worksite clean up to make any necessary corrections. The timeframe for corrective action will still be as identified above.
Installation and Delivery The Contractor must be normally engaged in the installation of a Washer similar to that specified within this solicitation;
The Contractor must complete the installation, and delivery must be within ninety (90) days after receiving a Purchase Order from ITD;
ITD understands that timelines may need to be adjusted due to manufacturer delays. Proof of delay is required. ITD requires Contractor to give weekly updates if delays are forthcoming;
Installation Location:
264 E 8th North Preston ID, 83263 Insurance See Attachment 6 – Insurance Requirements Invoicing The Contractor must submit its invoice within thirty (30) calendar days of acceptance to the billing contact identified on the Contract. Invoices submitted prior to acceptance, or without the required information listed below, will be returned to the Contractor for correction and resubmission. The following information must be included with each invoice:
ITD Purchase Order (PO) number;
Contract Name and Order Number;
Invoice Number and Date;
Contractor Contact Information;
Itemization of Property (description, quantity, unit of measure, unit price, and total price);
Washer serial number.
Invoices must be submitted electronically to:
D5AP@ITD.Idaho.gov
RFQ1240
HOT WATER STATIONARY PRESSURE WASHER WITH INSTALLATION
SECTION 2 - SPECIFICATIONS
The Washer must meet the minimum specifications provided in Attachment 2 – Requirements and Specifications. The Washer latest model of the manufacturer's current standard production, as offered to commercial trade. Though they are not specifically covered herein, all parts necessary to provide a complete and functional Washer must be included. All parts must conform in design, strength, quality of materials, workmanship to current engineering practices and accepted standards of the industry. All parts must be the manufacture’s standard unless otherwise specified in this RFQ.
1. Hotsy Hot Water Electric Pressure Washer 1475N ten (10) horsepower (HP) or equal and must at a minimum meet the following;
Performance Pump volume at pump head, five (5) Gallon per Minute (GPM);
Pump pressure at pump head three thousand (3000) Pressure per Square Inch (PSI);
Three (3) Phase Power (Ph), two hundred (200) volt alternating current (VAC), thirty-four (34) ampere (Amp) ;
Belt drive pump;
Power and Drive Motor Power: Ten (10) Horsepower (HP) (electric motor);
Motor Speed: Seventeen hundred twenty five (1725) revolutions per minute (RPM);
Voltage / Phase: Two hundred eight (208) volt/three (3) phase;
Amperage: Thirty-four ~(34) ampere and;
Drive: Belt drive to pump.
Heat and Fuel Fuel Type: Natural Gas (NG) burner;
British Thermal Units (BTU) Output: Three hundred seventy eight thousand six hundred ~(378,600) BTU/hour and;
Hot-Water Capability: Gas-fired coil/heat exchanger.
Certifications Edison Testing Laboratories (ETL) certifications and;
Underwriters Laboratories (UL) certifications;
Assembly Features Industrial-duty frame construction;
Locking lid for secured access;
Belt and pulley safety guards;
Pressure relief valve;
Hose reel;
Smart relay (remote-ready auto start/stop control) and;
Heavy-duty heating coil.
Standard Accessories Fifty (50) ft high pressure hose;
Trigger gun;
Insulated spray lance and;
Quick-connect spray nozzles.
SECTION 3 – INSTALLATION
Contractor shall furnish all labor, mounting hardware, fittings, and interconnections necessary to install, connect, commission, and test one Hotsy 1475N hot water pressure washer where electrical power, natural gas, and water services are pre-installed and stubbed within 5 feet of final equipment location.
1. Site conditions (by others) The following utilities shall be present and properly sized prior to installation:
Electrical (Stubbed);
Two Hundred eight (208) Volt, Three (3) Phase, 60 Hertz (Hz);
Fused disconnect or breaker within line-of-sight of equipment;
Proper grounding conductor;
Natural gas (Stubbed);
Natural gas supply line sized to support three hundred seventy eight thousand six hundred ~(378,600) BTU/hr demand;
Manual shutoff valve within 6 feet of appliance;
Drip leg/sediment trap per code and;
Supply pressure per manufacturer burner requirements.
Water Supply (Stubbed) Clean cold water supply;
Minimum six (6) GPM flow available;
Inlet pressure between twenty (20) – eighty (80) PSI;
Isolation ball valve at stub and;
Backflow prevention device (if required by local code).
Equipment Placement Install unit on level, non-combustible surface;
Maintain minimum twelve (12) in clearance on sides and rear (or per manufacturer guidelines);
Provide adequate service access to pump, motor, and burner and;
Anchor unit to floor.
Mechanical Connections Water Inlet Connection;
Connect supply line to unit inlet using flexible high-pressure-rated hose or approved plumbing connection;
Install inlet shutoff valve if not already present;
Install water filtration to prevent pump damage and;
Verify no air leaks in suction line High-Pressure Discharge Install high-pressure hose reel;
Connect discharge line to wash bay plumbing or hose assembly and;
Pressure test all fittings.
Natural Gas Connection Connect stubbed gas line to burner inlet;
Perform leak test using approved method;
Verify manifold pressure per burner specification and;
Confirm proper combustion air supply and ventilation.
Venting Requirements Connect flue stack to approved vent piping;
Vent per local building and mechanical code;
Maintain proper vertical rise and termination clearance;
Use double-wall vent pipe where required and;
Ensure adequate combustion air in mechanical room.
Electrical Connection Hardwire unit to disconnect;
Verify correct phase rotation;
Confirm proper motor amperage draw;
Test overload protection and;
Confirm operation of smart relay / auto start-stop controls.
Startup & Commissioning Contractor must:
Prime pump and verify water flow;
Start unit and confirm operating pressure three thousand (3000) PSI nominal);
Verify five (5.0) GPM output;
Fire burner and confirm ignition;
Measure outlet water temperature rise;
Inspect for leaks (water and gas);
Verify safety controls and pressure relief operation and;
Provide operator demonstration.
Code Compliance Installation must comply with:
Local building codes;
National Electrical Code (NEC);
National Fuel Gas Code;
Applicable fire and ventilation regulations and;
OSHA safety requirements.
EXCLUSIONS (Unless Specifically Noted) Utility upgrades;
Gas line resizing;
Electrical panel modifications;
Structural modifications;
Core drilling;
Vent roof penetration and;
Backflow preventer supply (if not stubbed).
| 4 | Page | dcc | |
| RFQ 1240 | HOT WATER STATIONARY PRESSURE WASHER WITH INSTALLATION 3/26 |
image1.png
File details come from the government source that posted it. Updated .