This Request for Qualifications (RFQ) is issued by the City of Olean Department of Community Development for professional consulting services related to the Connecting Communities multi-modal vision project for West State Street in Olean, New York. The project encompasses approximately 2.5 miles of complete street improvements to West State Street (NYS Route 417) between North Union Street (NYS Route 16) and Francis Road at St. Bonaventure University. Requested services include design and engineering work advancing from 30% conceptual design to final construction documents, environmental review and NEPA/SEQRA clearance, project administration and management, public involvement coordination, and construction management and inspection services. The scope includes roadway design, traffic design, utility coordination, drainage design, stormwater management planning, landscaping design with green infrastructure, streetscape and lighting design, geotechnical services, pavement design, and right-of-way acquisition support. The RFQ package is available as of November 10, 2026, with a question deadline of December 1, 2026, and proposals due electronically and in five hard copies by December 15, 2026, at 2:00 p.m. Public proposal opening and evaluation are scheduled for December 15, 2026, with interviews for top-ranked firms during the weeks of January 4, 2027, and a Notice of Award anticipated on January 13, 2027, with an approximate design and engineering start date of January 25, 2027. The City expects design and engineering completion within 12 months of Notice to Proceed to meet the scheduled construction completion date.
The project is funded through a $25 million award from the U.S. Department of Transportation Fiscal Year 2025 BUILD Program, with the City of Olean committing an additional $5,580,000 in local funding for infrastructure repair, replacement, and contingency to ensure sufficient funds for potential cost overruns. The total project budget is $27.8 million, with a 12% contingency included in construction estimates and an additional 10% contingency authorized by City resolution. This is a qualifications-based procurement process where cost negotiation will occur following evaluation and selection of the highest-ranked firm. Evaluation criteria are weighted as follows: demonstration of understanding of project objectives (30%), qualifications of the project team (20%), experience with FHWA-funded projects of similar size, scope, and complexity (20%), project approach (15%), and organization, timeframe, and scheduling (15%). Proposers must have documented experience working on NYSDOT or FHWA-funded projects of similar scope and scale and must provide at least three references of completed projects within the last five years involving design and construction administration/inspection services. The City reserves the right to reject any or all proposals and conduct investigations regarding responsibility, qualifications, and financial ability of potential proposers. All work must comply with Federal Highway Administration terms and conditions, New York State and General Municipal Law, and prevailing wage requirements will apply.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ-Notice.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUALIFICATIONS (RFQ)
Professional Consulting Services
Connecting Communities: A Multi-Modal Vision for West State Street
Issue Date: 11/10/2026 Question Deadline: 12/01/2026 Final Addendum Posted: 12/08/2026 Submissions Must be Received by: 12/15/2026 by 2:00 p.m.
Public Opening of Proposals: 12/15/2026 Interviews, the weeks of: 01/04/2027 Notice of Award: 01/13/2027 Approximate Design and Engineering Start Date: 01/25/2027
Designated Contact: Keri Kerper, kkerper@cityofolean.gov (716) 376-5647
Introduction:
Olean is a brave, can-do city that has borrowed from role models to the point where we could now become THE role model for rural revitalization and master transitioning a small city’s economy from agriculture and manufacturing to knowledge and choice with a dynamic and sustainable economy.
We want to undo mistakes of the past by remaking our streets in favor of residents. We recognize that our population that’s been lost still lives a mile or two outside of the City limits and we need to attract them back and convince current residents to stay and invest while attracting new populations. The project should support and integrate New York State Smart Growth Principles.
The City of Olean has identified a need to install enhancements to approximately 2.5-miles of Complete Street improvements on West State Street (NYS 417) between North Union Street (NYS 16) and Francis Road at St. Bonaventure University. Improvements include a two-way protected bike lane or shared-use path, bump-outs and pedestrian refuge islands, marked crosswalks, pedestrian crossing signals and ADA improvements, green infrastructure, approximately five traversable mini-roundabouts, and pedestrian and public transit amenities.
The project is funded by the City of Olean and the U.S. Department of Transportation Fiscal Year 2025 Build Program. In order to access these funding sources, the City of Olean must obtain all project permits, NEPA clearance, temporary construction easements, utility clearances, approved bidding documents, etc. for FHWA to authorize and obligate funding for construction.
All work must be completed in accordance with “General Terms and Conditions Under the Fiscal Year 2025 BUILD Program: FHWA Projects,” dated April 23, 2025, which is available at:
https://www.transportation.gov/BUILDgrants/grant-agreements.
mailto:kkerper@cityofolean.gov https://www.transportation.gov/BUILDgrants/grant-agreements
Notifications:
The Recipient in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252, 42 U.S.C. §§ 2000d to 2000d-4) and the Regulations, hereby notifies all bidders that it will affirmatively ensure that for any contract entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full and fair opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.
The Recipient assures and certifies, with respect to this Grant, that it will comply with all applicable Federal laws, regulations, executive orders, policies, guidelines, and requirements as they relate to the application, acceptance, and use of Federal funds for this Project. A listing of these laws and regulations may be found at:
https://www.transportation.gov/sites/dot.gov/files/2025-05/build-fy2025-fhwa-exhibits- 20250423.pdf.
General Terms and Conditions Under the Fiscal Year 2023 RAISE Program: FHWA Projects (draft; 2023-06-05)
Buy America - Construction Program Guide - Contract Administration - Construction - Federal Highway Administration
All New York State and General Municipal Laws shall be abided by to ensure proper procurement.
Administrative Instructions:
RFQ Package – Available 11/10/2026, online at the New York State Contract Reporter webpage at https://www.nyscr.ny.gov/Home/Contracts and online at the City of Olean’s webpage at https://www.cityofolean.gov/departments/public-works/request-for-proposal/
Question Deadline - 12/01/2026 at 2:00 p.m. All questions regarding the meaning or intent of this RFQ are to be emailed to Keri Kerper at kkerper@cityofolean.gov. Written responses to questions will be posted on the New York State Contract Reporter and on the City of Olean’s webpage via addendum no later than 12/08/2026, at 2:00 p.m. It is the vendor’s responsibility to download, review, sign and include addenda with their proposal.
Proposal Submission Cut-off – 12/15/2026, at 2:00 p.m., proposals shall be submitted electronically to:
kkerper@cityofolean.gov
All electronic submissions must be no larger than 20 MB to ensure proper email delivery.
https://www.transportation.gov/sites/dot.gov/files/2025-05/build-fy2025-fhwa-exhibits-20250423.pdf https://www.transportation.gov/sites/dot.gov/files/2025-05/build-fy2025-fhwa-exhibits-20250423.pdf https://www.transportation.gov/sites/dot.gov/files/2025-11/BUILD-fy2025-fhwa-general-terms-and-conditions-20251104.pdf https://www.transportation.gov/sites/dot.gov/files/2025-11/BUILD-fy2025-fhwa-general-terms-and-conditions-20251104.pdf https://www.fhwa.dot.gov/construction/contracts/buyam_qa.cfm https://www.fhwa.dot.gov/construction/contracts/buyam_qa.cfm https://www.nyscr.ny.gov/Home/Contracts https://www.cityofolean.gov/departments/public-works/request-for-proposal/
Five hard copies of the proposals shall also be delivered prior to the deadline to:
Ms. Keri Kerper City of Olean Department of Community Development Municipal Building, Room 209 101 East State Street Olean, NY 14760
Late proposals will not be accepted and it is the responsibility of the respondent to ensure that proposals (including signed addenda, if necessary) arrive by 2:00 p.m. on the date listed above.
The City of Olean reserves the right to reject any or all proposals without disclosing reason, therefore, to waive any information in the proposals received, and to accept the proposals deemed most advantageous, responsible and in the best interest of the City of Olean.
A. Request for Services
Introduction
The City of Olean has identified a need to install complete street enhancements to approximately 2.5-miles of West State Street (NYS 417) between North Union Street (NYS 16) and Francis Road at St. Bonaventure University. Improvements include a two-way protected bike lane or shared-use path, bump-outs and pedestrian refuge islands, marked crosswalks, pedestrian crossing signals and ADA improvements, green infrastructure, approximately five traversable mini-roundabouts, and pedestrian and public transit amenities.
The project has been planned to a 30% level conceptual design. Budgeting was also based upon the 30% design concept to include the following activities and improvements:
Replacement of the water lines from Union to Independence Drive.
Sanitary sewer lines and manholes replaced from Union Street to Francis Road. (20” Union to Independence, 18” Independence Drive to Francis Road.)
Storm sewer: In the areas which are just box widening to allow the curb to move, estimate includes cleaning the existing system and modify each drop inlet that will be affected by the curb relocation. In areas that are being reconstructed, the entire storm system shall be replaced.
Curbs:
• Union to 15th Streets: North and South curb lines shall be replaced.
• 15th Street to Francis Rd.: The estimate includes replacing the curb on the south side. It may not be necessary from 16th Street to Independence Drive since there is enough room to accommodate the shared-use path and a green buffer; however, the estimate assumes a box out along the curb in this section to replace the sanitary sewer, so we included the cost of curb replacement too. South curb will likely need to move in a little from Independence Drive to Francis Rd. to accommodate the shared-use path and a buffer.
Lighting: The only lighting costs estimated for the sections of the corridor west of 13th Street are for the roundabouts at Independence Drive and at 20th Street. East of 13th Street the cost includes new poles & heads, and burying the electric supply.
15th Street intersection: $150,000 is designated for signal improvements at 15th Street, as 114 accidents occurred over a 6-year period. The estimate assumes that we would reconstruct that 170’ block as full-width reconstruction (starts immediately east of 15th Street).
The compressed narrative including the conceptual design plans and budget may be found in Attachment A.
The City of Olean was awarded a BUILD grant in January 2025 as a Project of Merit under Round 1 in the amount of $25,000,000. The City of Olean committed an additional $5,580,000 dedicated to infrastructure repair and replacement as well as additional contingency to ensure sufficient funding for any potential unanticipated cost increases and potential cost overruns that could occur with the project. The City of Olean expects design, environmental work and engineering to be completed within 12 months of Notice to Proceed to meet the scheduled construction completion date. The awarded consultant will be asked to propose a specific completion date for design and engineering that aligns with the overall timeline of the project.
Work Scope
Work Element 1 – Project Administration/Management
Consultant to provide contract administration and invoice processing. Project management services including coordination and product review shall be provided throughout the duration of the project. Consultant shall maintain the design schedule, a project risk matrix and potential response strategies.
The following meetings are included in this scope of work:
• Kickoff Meeting (virtual is acceptable)
• Design Review Field Meeting (in-person)
• Review meeting with New York State Department of Transportation (virtual is acceptable)
• Monthly progress meetings (virtual is acceptable)
Work Element 2 – Environmental
The consultant shall conduct necessary site investigation, environmental, social and economic analysis, and prepare sufficient documents for FHWA to review and approve. All National Environmental Policy Act and New York State Environmental Quality Review Act work will be investigated, prepared and properly submitted by the consultant.
Work Element 3 – Roadway Design
Consultant will advance roadway design from 30% to final design and incorporate comments.
Roadway design includes horizontal layout and geometry, vertical design, roadway modeling, median design, roadway details, asphalt reconstruction limit refinement, and related design checks. Consultant to coordinate with the City on multimodal planning and design for off-highway networks. Entire corridor shall be designed in accordance with the Americans with Disabilities Act (ADA) and the Public Right-of-Way Accessibility Guidelines (PROWAG).
Work Element 4 – Landscaping Design to include Green Practices
Consultant will advance the landscaping design from conceptual to final design and incorporate best practices that may include but are not limited to green stormwater infrastructure, energy efficiency, water efficiency and environmental innovation. The creation of cutting-edge green technologies is preferred as a project outcome.
Consultant to conduct analysis of existing tree canopy for removal and development a replacement plan for new trees and plantings. Develop conceptual landscape and possible irrigation design for the areas in the project corridor and include a probable cost. City comments on the landscape design shall be incorporated and resubmitted with the 90% submittal package.
Work Element 5 – Public Involvement
Conduct public meetings throughout the design process to gather input on final design, landscape and streetscape details. Public meeting to include:
• Kick-off meeting with project partners – St. Bonaventure University officials, Town of Allegany officials, businesses and property owners to gather input that can inform final design and project phasing. This meeting should occur prior to 60% design, but early enough to inform the design process. Emphasis of the meeting should include landscaping and streetscape concepts.
• At least one open house with 60% design exhibits for public review and input.
• At least one open house at 90% design with information about proposed project phasing and construction strategy.
• The consultant will be responsible for creating a project website and updating the information and documentation accordingly throughout the project.
Work Element 6 – Traffic Design
Consultant will advance traffic design from 30% to final design and incorporate comments.
Traffic should be designed to be user friendly, safe and vibrant along the entire corridor.
Work Element 7 – Ingress/Egress Modifications
Refine access design as shown in the 30% plans and support limiting access/curb cuts, where appropriate.
Work Element 8 – Utility Coordination and Plan Development
Consultant will provide overall utility coordination/management, including subsurface utility engineering for the project, develop and maintain a utility conflict matrix and accompanying utility plans. Up to two virtual meetings will be provided for each utility owner to facilitate discussion of conflicts and potential relocations needed during the project. Additional one-on-one coordination via phone and email will be provided to coordinate relocation plans, estimates, agreements, etc.
Work Element 9 – Drainage Design
The proposed drainage improvements need to account for the roadway improvements, which may result in changes to the gutter flow lines, reduction in spread width capacity and impacts on existing drainage infrastructure. Consideration of the existing underground stormwater system and future improvements should be given as part of the design. Stormwater management to include building runoff shall be considered. This includes drainage analysis of the existing offsite and tributary areas to West State Street, which evaluates the street capacity and meets the levels required by applicable criteria. The chosen consultant shall model the entire stormwater system and provide proposed improvements that will be compatible with future improvements from initial inflow to final discharge to water body. A section of the project is located in a floodplain at Gargoyle Park Road and Franklin Street; therefore, floodplain work will be necessary.
Work Element 10 – Storm Water Management Plan & Storm Water Pollution Prevention Plan
(SWPPP)
Consultant to provide storm water management plan consistent with DOT requirements for the project. The project disturbance will be over one acre therefore a SWPPP will be required.
Consultant to prepare template and erosion control plans. Storm water management to include building runoff needs to be incorporated. Any improper or illegal tie-ins from gutters needs to be addressed.
During heavy rainfalls parts of the project corridor floods. In addition, storm water and waste water discharges have occurred into the Allegheny River during significant weather events from the Waste Water Treatment Plant and various pump stations. There are connections between storm water and sanitary sewer that are illegal and need to be remedied. In addition, the City of Olean is under a Consent Order by the NYS Department of Environmental Conservation aimed at bringing discharge from its waste water treatment plant into compliance with SPDES effluent limits along with other serious compliance items. This project needs to help address achievable deliverables, improvements, I/I elimination, etc. as outlined in the Consent Order.
Work Element 11 – Supplemental Survey and Right-of-Way
Survey will be needed for the entire corridor. The awarded consultant will be able to utilize previous survey data however, additional survey at critical tie-in locations to verify signal poles or removal and above-ground visible utility features including traversable mini roundabout locations will be required at a minimum. Consultant will include verification points at each intersection for matching purposes in the supplemental survey. Approximate right-of-way lines were used during the design concept and consultant shall define the existing right-of-ways.
Temporary and permanent easements may be needed for the proposed improvements. All right-of-way incidentals and acquisitions will be addressed by the consultant and services provided for temporary and permanent easements in consultation with the City, FHWA, NYSDOT, etc.
Though no property can be acquired until after the completion of the PS&E Document (Final Design), the selected consultant will need and understanding of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 (Uniform Act), right‑of‑way acquisition for any Federal‑aid project must follow strict Federal procedures for appraisals, negotiations, just compensation, and relocation assistance. These requirements apply whenever an agency acquires real property or property interests—such as easements—for a federally funded project.
Work Element 12 – Subsurface Utility Engineering
Consultant shall conduct, document, stamp and seal a SUE investigation of the project area while documenting utilities in accordance with American Society of Civil Engineers Construction Institutes Standard to include televising and all video will be turned over to the City.
Work Element 13 – Streetscape and Lighting Design
Consultant to develop conceptual streetscape and lighting design for the areas designated in the 30% plans and include an opinion of probable costs. The consultant will coordinate with the Department of Public Works, City officials, etc.
Work Element 14 – Plan Production and Quality Assurance (QA) and Quality Control (QC)
The consultant will submit 60%, 90% Design Review Plans, PS&E Plans and Advertisement Documents. Engineer’s opinion of probable cost of all items to be included in all submittals.
Consultant will provide QA/QC review for the project to confirm the appropriateness of methodologies used, accuracy of documents, reasonableness of conclusions, document completeness and overall clarity.
Consultant will prepare specifications in the FHWA format, including project special provisions, at the 90% design level.
Final PS&E Plan Package The final design will respond to comments from the 90% submittal and consist of final plans, specifications and the engineer’s opinion of probable cost. Final versions of reports will be delivered with the PS&E package.
Suggested Construction Phasing Concept
The consultant will develop a construction phasing concept with traffic control concepts that limit impacts on West State Street businesses and residences. Traffic control and construction phasing plans are to be included at 60%.
Permitting The consultant will identify all permits, reviews, and approvals required that are necessary for the project and shall obtain all such permits and approvals.
Advertisement/Bid Package & Services The Advertisement Set will respond to comments from the PS&E package, as needed. The consultant will provide bid alternatives, as needed, based on the engineer’s opinion of probable cost and allotted construction funding. Advertisement drawings and specifications shall be sealed by a Professional Engineer, as appropriate. The consultant will answer any contractor questions that may arise during the project advertisement. Consultant will attend the pre-bid meeting and bid opening.
Work Element 15 – Geotechnical Services and Pavement Design
The consultant will provide geotechnical services and a pavement design report for pavement reconstruction areas.
Work Element 16 – Construction Management and Inspection Services
The consultant will provide construction management and full-time inspection services throughout the project. If work is being done in multiple locations, consultant shall add additional personnel to make sure work is done per plans and specs.
Services may include but are not limited to:
• Construction observation, contract management and inspection.
• Design services during construction.
• General conditions for construction contract.
• Construction management.
• Materials testing.
Work Element 17 – Project Reporting and Closeout
The consultant will complete all necessary reporting throughout the life of the project including but not limited to project closeout.
B. Submittal Instructions
Proposals should be submitted electronically to kkerper@cityofolean.gov prior to 12/15/2026, at 2:00 p.m.
All electronic submissions must be no larger than 20 MB to ensure proper email delivery.
Proposals must be submitted in PDF format via email attachment and the subject line must state Request for Qualifications: Connecting Communities.
Five hard copies of the proposals shall also be delivered prior to the deadline (date and time specified above) to:
Ms. Keri Kerper City of Olean Department of Community Development Municipal Building, Room 209 101 East State Street Olean, NY 14760
The submitted proposal should include the following:
• Introduction
• Project approach and schedule
• Experience with similar projects and qualifications of team members
• References
C. Proposal Format and Content
Introduction
Proposals must include information stating the complete legal name and type of legal entity (e.g., corporation) of the vendor submitting the Proposal, the mailing address, the telephone number, the project lead and the name of the person the City should contact regarding the Proposal.
Proposal Outlining Project Approach and Schedule
Provide information pertaining to how your company intends to deliver or manage the project.
Provide a detailed statement of the Proposer’s understanding of the goals of this project, scope of work, and the services required of the Consultant. Demonstrate a clear methodology and approach to meet the needs of this project.
The response to this RFQ should serve as a complete and detailed approach to providing the Services. Responses may create a team or use subconsultants to fulfill the services. Any proposed subconsultants/team members should be identified and their roles clearly defined in the Proposal. Be sure to include the project schedule to ensure the project is completed by the FHWA contract deadline.
Experience and Qualifications
Proposals must provide a narrative description of the organization of the project team and Statement of Qualifications. A personnel roster must be provided that identifies each person who will work on the contract and provide the following information about each listed person:
• Title
• Resume
• Location, where they work
This is a qualification-based procurement process. Proposers must have documented experience working on NYSDOT or FHWA funded projects of similar scope and scale and qualified personnel who are capable of providing all of the required services. The City of Olean is seeking qualified firms that are financially and technically qualified to perform the scope of work outlined, i.e., engineering, design, construction administration/inspection, etc.
References
Each proposal must include a list of at least three (3) projects that the respondent completed within the last five (5) years. The project must be a project where the respondent has provided or is providing design and construction administration/inspection services similar to the project outlined in this RFQ. References should include the project name, project location/address, the project size, a description of the project, the date the project was or is scheduled to be completed, the final construction cost of the project, and a contact person, email and telephone number for the owner of the project.
D. Award Process
Proposal Opening, Evaluation Process and Recommendation for Award
Proposals will be opened at the Olean Municipal Building and then provided to the selection committee for evaluation. The committee will evaluate and rank each proposal following all due diligence and procurement procedures, and submit a recommendation for award to the City Attorney and then to the Common Council for ultimate approval.
The committee may decide to invite the highest ranked firms to meet with the committee and present their team, discuss their proposals and answer questions. These will be scheduled for the weeks of 01/04/2027. Invited companies’ key staff, including the proposed project manager or lead must be in attendance.
The City shall evaluate and select proposals to provide the required services based on the completed proposal responses. The City shall be the sole judge in determining how the evaluation process shall be conducted and which Proposer shall be considered for award as deemed to be in the best interest of the City of Olean.
The City may conduct such investigations as the City considers necessary to assist in the evaluation of any proposal to establish the responsibility, qualifications, and financial ability of any potential Proposer to perform the services specified under this RFQ within the prescribed time.
The evaluation criteria noted below are the criteria to be used for the evaluation of this RFQ.
Based on the evaluation process, a rank-ordered list of responsive Proposers shall be established.
Evaluation Criteria
Incomplete submissions that do not address all of the requested components and meet the qualification standards shall not be accepted for review and consideration. The proposals shall be evaluated based upon an overall best value determination with the criteria listed below in relative order of importance:
a. Demonstration of understanding of the project objectives 30%
b. Qualifications of the project team 20%
c. Experience with FHWA Funded Projects of similar size, scope and complexity 20%
d. Project Approach 15%
e. Organization, timeframe and scheduling 15%
Total 100%
Cost Negotiation
Once the top ranked firm is determined, the City of Olean will request a Fee Proposal. The City shall then determine whether the highest-ranking proposal can be accepted as is without negotiations. In the event, that the City determines that negotiation of a proposal is necessary, the Proposer shall be notified, and the negotiation process will begin. Should the City be unable to negotiate an acceptable service agreement with the highest-ranked Proposer, then the process described in this paragraph will being with the second-highest-ranked Proposer. This process shall continue until a satisfactory service agreement is negotiated or until all negotiations with qualified ranked Proposers are exhausted. The City shall be the sole judge in determining when negotiations are to be concluded.
Suspension and Debarment
Proposer acknowledges that as of the solicitation submittal date, neither the Proposer/Contractor, nor its subcontractor(s), is (a) debarred, suspended, or subject to any proceeding for debarment or suspension with a final determination still pending; declared ineligible or voluntarily excluded (as such terms are defined in any of the Debarment Regulation) from participating in procurement or non-procurement transactions with any Federal, State or City government department or agency pursuant to any of the Debarment Regulations, or (b) indicted, convicted or had a Judgment rendered against the Proposer/Contractor, or its subcontractor(s) for any of the offenses listed in any of the Federal, State or City’s Debarment Regulations and no events has occurred and no condition exists that is likely to result in the debarment or suspension of the Proposer/Contractor, or its subcontractor(s), from contract with the City of Olean, Federal or State government, or any agency or instrumentality thereof.
Reservation of Rights
The City of Olean reserves the right to refuse any and all proposals, in part, or in their entirety, or select certain products from various consulting proposals, or to waive any informality or defect in any proposal should it be deemed to be in the best interest of the City of Olean. The City is not committed, by virtue of this RFQ, to award a contract, or to procure or contract for services.
The proposals submitted in response to this request become the property of the City and are not considered confidential.
Rejection of Proposal
No proposal shall be accepted from, or contract awarded to, any person, company, or corporation that is in arrears to the City, upon debt or contract or that is a defaulter, as surety or otherwise, upon any obligation to the City, or that may be deemed irresponsible or unreliable by the City of Olean. Proposers may be required to submit satisfactory evidence that they have the necessary financial resources and experience to perform and complete the work outlined in this RFQ/P.
The City of Olean reserves the right to request any additional information as needed to make a sound evaluation and decision.
CONNECTING COMMUNITIES
A Multi-Modal Vision for West State Street, Olean, NY
FY 2024 RAISE Transportation Grant Application
Prepared by CPL and Molly Vendura Landscape Architect, PLLC for the City of Olean, NY
Proposed Improvements - West State Street from Union Street to St. Bonaventure University
Attachment A
CONNECTING COMMUNITIES
Table of Contents
Project Description
Project Budget
Merit Criteria Safety Environmental Sustainability Quality of Life Mobility & Community Connectivity Economic Competitiveness State of Good Repair Partnership Innovation
Project Readiness
Appendix A: Concept & Plans
Appendix B: Benefit Cost Analysis Narrative
Appendix C: Letters of Support
Appendix D: Funding Commitment Documentation
Appendix E: Conditions Summary
Appendix F: iTree Ecosystem Analysis
Appendix G: Public Input Summary
Appendix H: Key Reference Documents
Connecting Communities
2024 RAISE Grant Program Page | 1
Project Description Connecting Communities: A Multi-modal Vision for West State Street, Olean, NY is ta $27.8 million capstone project to remake Olean into a walkable, sustainable, equitable place of opportunity. This 2.5-mile complete-street make-over of West State Street (NYS 417) between North Union Street (NYS 16) and Francis Road at St. Bonaventure University will transform safety, environmental sustainability, quality of life, multi-modal mobility and community connectivity, and economic competitiveness for underrepresented groups in this area labelled as both a Historically Disadvantaged Community and Area of Persistent Poverty.
Olean is an Appalachian small city in southwestern NY, on the Allegheny River. The City population is 13,786;
22,989 people live within a 5-mile radius (2021 US Census estimates), and the service area of Olean General Hospital counts 102,000 people.
Being 1½ hours from Buffalo, and 2 hours from Rochester, Olean is the civic center for a large rural region.
West State Street is our most important street. The Olean Area Chamber of Commerce counts 184 businesses and institutions, with over 1,600 jobs on this Street, in the project area. There are big-box stores, restaraunts, owner-operted shops, boutiques & salons, government and non-profit agencies, religious places, social clubs, parks and schools (within 2 blocks) and medical offices.
Constructed in 1896 and 1917, West State Street was designed for trucks and travelers through downtown Olean when this was the major east-west highway across New York’s Southern Tier.
Today, Interstate 86 carries this traffic around Olean, leaving West State Street with few trucks, but many shoppers, commuters, and residents who use the street for local access.
West State S. is the most travelled street in Olean, featuring mostly light vehicles. Through-travelling trucks utilize I-86.
Olean lies in Appalachian southwestern New York
2024 RAISE Grant Program Page | 2
Change in use-case motivates our redesign. Currently, West State Street has no facilities for bikes, scooters, or mobility chairs. Pedestrian crosswalks are 50-feet long, many without crossing signals. Accident data shows this is Olean’s most dangerous street, three-times more dangerous than streets of its type in New York State. The Connecting Communities project will solve problems of safety, environmental sustainability and resilience, while improving quality of life and mobility for underrepresented residents and visitors.
The project area traverses the City of Olean and Town of Allegany, up to St. Bonaventure University.
Most of this 2.5 mile-long project lies within census tracts (9616 and 9617) labelled as both Areas of Persistent Poverty and Historically Disadvantaged Communities, with poverty rates above 20 percent.
91% of the project cost will be spent within these areas.
Acknowledging West State Street is a corridor of opportunity, New York State and HUD designated these census tracts as Qualified Opportunity Zones. Opportunity Zone incentives, together with our Connecting Communities complete-street makeover, will spur private investment strengthening businesses on West State Street, reactivating vacant and underutilized properties, and encouraging affordable housing and job creation. These investments will also improve property values in adjoining Areas of Persistent Poverty/Historically Disadvantaged Communities where many of the homes are owner-occupied.
Functionally obsolete, with a use-case defined in the last century and subsurface infrastructure being 120 years old, the City of Olean understands that major reconstruction is needed in the next 10 years. West State Street’s pavement within the City limits is rated in “fair” condition, but this rating continues to go down each year. To simply rebuild, “as-is” would cost more than $21 million. The RAISE program could enable this $27.8 million Connecting Communities project, unlocking $88 million of benefits, based on 20-year, present value analysis.
Olean prioritized West State Street when including it as a priority project in the City’s Comprehensive Development Plan. Additionally, in 2017, Olean’s Downtown Revitalization Initiative identified a complete-street makeover of West State as a Priority Project. The City passed a resolution in February 2024 authorizing this application for $25 million in RAISE grant funding, while also appropriating $2.8 million to complete the project funding budget. Although the project budget includes a 12% contingency, the City also authorized a further $2.78 million (10%) additional contingency, to address any unanticipated cost increases and cost overruns, thus adding a contingency plan on-top of the budgeted contingency ($30, 580,000 total).
The Project Area includes two census tracts that are both Areas of Persistent Poverty and Historically Disadvantaged Communities (shown above in pink), where 91% of project costs will be spent.
2024 RAISE Grant Program Page | 3
Neither residents nor businesses will be displaced because this project will be completed within the existing right-of-way. Its design improvements will benefit the City and it’s under-served population, yielding a calculated Benefit – Cost ratio of 3.18:1.
Seeking a more equitable, sustainable, and resilient West State Street, we employ best practices identified by US DOT, including in the National Roadway Safety Strategy:
1. From N. Union Street through 11th Street a road-diet and relocation of the curbs makes space for a two-way protected bike lane, sidewalks, and pedestrian amenities.
2. From 11th Street, to St. Bonaventure, curb locations are maintained except at roundabouts and bump-outs. A shared-use path continues the connection west to St. Bonaventure University for a multi-modal town-gown connector.
2024 RAISE Grant Program Page | 4
3. Curb bump-outs and pedestrian refuge islands from N. Union Street to 20th Street will make West State Street safe to cross.
4. Five mini-roundabouts reduce peak speeds while improving traffic flow and safety.
5. Rain gardens mitigate flash flooding and icing, and reduce stormwater run-off.
Our design, at 30% to prove feasibility, scope, and budget, is embraced by motorists because in Olean, we like roundabouts! Our existing downtown roundabouts improve traffic flow and safety. Traffic calming elements feature large in our design. While motorists appreciate this, our real goal is to make it most attractive to park, and then walk, roll, or ride a bus in this corridor.
Traversable mini-roundabouts are also resilient to extreme weather – which in our region looks like deep snow or fast flooding, with high winds. Since they do not require electricity, and they are easy to plow, roundabouts work when traffic signals are dark, or mired in snow and ice.
Curb bump outs, added for pedestrian safety, will include storm water rain gardens. These will prevent millions of gallons of runoff into in the Allegheny River, thus protecting this cherished recreational asset that is also home to protected species including our native Rayed Beam and Hellbender (a freshwater mussel and a super-sized salamander), and our beloved Bald Eagles.
Children’s safety is a primary purpose of this project. All of Olean’s primary schools are north of West State Street. 494 school children live in neighborhoods south of West State. They are too close to ride a bus so they cross this Street twice each day. Bump-outs and pedestrian refuge islands will shorten their crossing distance and enable drivers to see them and yield, while high-visibility crosswalks and pedestrian signals will help them to cross safely.
Context-sensitive design: Multi-modal choice is added by reapportioning the right-of way. No residents or businesses will be displaced or inconvenienced. For instance, this left-turn lane at 3rd St. will accommodate local delivery trucks servicing a bakery that employs over 100 people.
Mode-shift is the cornerstone of our plan to empower underrepresented groups with new mobility options while taking a transformational step toward environmental sustainability. We are adding bus stops with shelters and pull-off areas to increase the utility of the Olean Area Transit System.
This will encourage walking and bus trips, thus reducing car dependency, and the accompanying greenhouse gas emissions, pollution, and noise in these historically disadvantaged neighborhoods with persistent poverty. With 267 businesses and institutions, West State Street is lined with destinations, but for our underserved residents, access is difficult without a car. New features will change this, shortening perceived distances, while improved crosswalks make both sides of the street safely accessible.
2024 RAISE Grant Program Page | 5
Public, on-street EV chargers will enable Olean, characterized as an “EV Charging Desert”, to become a rural leader with EV adoption. Renters will be able to charge overnight. Visitors could top-up while running errands. Through travelers on I-86 will pull-off in Olean to charge, perhaps becoming tourists. The goal, of course, is to do our part toward State and Federal de-carbonization goals, while expanding mobility choices for residents.
Today, Administrators at St. Bonaventure guess that fewer than half of their 2,400 students ever visit Olean – just 2.5 miles away. The cycle track, multiuse path, improved sidewalks and streetscape amenities will connect communities from St. Bonaventure to downtown Olean.
Students, people isolated in car-dependent poverty in trailer homes between Olean and St.
Bonaventure, and those living in Olean’s neighborhoods of persistent poverty, will soon feel connected to a broad, and diverse collection of civic assets, services, and neighbors.
The design is informed by our partners at the NYS DOT, St. Bonaventure University, and the Town of Allegany, as well as enthusiastic public input. In fact, our most recent public hearing brought unanimous support for one more roundabout to solve the most vexing intersection in the corridor. Citizens are eager to make Olean more walkable, equitable, and vibrant.
The Connecting Communities project embodies the City of Olean’s commitment to walkability first begun in 2013 with a $6.5 million TIGER5 FY13 grant. That project, Walkable Olean, transformed adjacent North Union Street. The City removed all seven traffic lights in this 0.68-mile historic downtown, introduced five new roundabouts, a continuous tree-lined median, all new subsurface infrastructure, and rain gardens.
Since then, Olean has implemented additional walkability and rollability improvements:
• Walkable Olean – Phase II, with traffic calming, a shared-use side path, beautification, and storm water filtration, connects Downtown with Olean General Hospital.
• Wider sidewalks/shared-use path, bump-outs and a roundabout will be added to South Union
Street, funded by a $3.0-million Downtown Revitalization Initiative (DRI) grant by New York State, thus extending the downtown walkable/rollable makeover into affordable neighborhoods, including low-income housing south of the river.
• Walkable Olean – Phase III: Improvements along East State Street from Union Street to East Avenue include a traffic-calming mini-roundabout and a shared-use path that will create a safe, bike, pedestrian, and wheel chair route to the recreational assets at War Vets Park and Bradner Stadium, as well as connecting east side neighborhoods. This is funded by a DRI grant of $1.2 million, a NYSDOT TAP award ($663,498), and local funds ($165,874).
• City-wide, Olean is improving walkability and rollability. With reference to best-practice, the City has installed ADA ramps and curb bump-outs while reducing corner radii in order to improve pedestrian visibility and calm traffic at intersections.
The Connecting Communities project will be the largest, most impactful investment that inclusively serves all users, most importantly, those underrepresented groups who tend to live in the areas designated as both Areas of Persistent Poverty and Historically Disadvantaged Communities. With help from the US DOT, Olean is excited to transform West State Street and transform opportunity and equity for our most underserved residents.
See Appendix A for a complete set of conceptual design plans.
2024 RAISE Grant Program Page | 1
Merit Criteria Safety Safety is a primary purpose of this project and this redesign will improve it. Roundabouts added to North Union Street in Olean have nearly eliminated motorist injury in that corridor. Pedestrian safety has dramatically improved even as ped/bike utilization has grown 400% since the walkable/rollable makeover of North Union Street. Overall, Injury accidents are down 80%.
We anticipate comparable benefits on West State Street – where pedestrian safety is even more important. For instance, today, all of Olean’s schools are north of West State Street but 494 school children walk to school from neighborhoods south of West State. This project will provide multiple safe routes to school for those 494 children.
Before the Walkable Olean transformation of North Union Street, that was Olean’s most dangerous corridor. West State Street now bears that unfortunate distinction – being 86% more dangerous than the average among streets of this type in New York State.
This 2.5 mile stretch of roadway, with an AADT of 15,626, has 6.31 accidents per million miles of travel (mvm). This is 1.86 times greater than the most recent New York State average of 3.39 accidents per mvm for three lane, undivided urban roadways. In a recent four-year period (2020-2023), reported accidents included 355 involving motor vehicles alone (72 with injuries), 11 involving pedestrians or bicyclists (all with injuries), four collisions with animals, and the remaining involving fixed objects. In total, over 70 accidents involved personal injuries.
Nearly a third of all accidents occurred at controlled intersections. (Source: NYS DOT CLEAR Crash Data Viewer)
Restriping in 2020 to reduce the street from four lanes to two lanes with a center turn lane may have resulted in the reduction in vehicular accidents between 2019-2020, but accidents are still high, and injuries and accidents involving pedestrians and bikes remain unchanged. Additionally, the COVID pandemic brought people outdoors. Many families bought bikes. Many others discovered the joy of walking. Now with new cyclists sharing the road, and even more pedestrians, it is urgent that we redesign West State Street with features advocated in the National Roadway Safety Strategy Plan. Our community has confidence in this strategy because it has already transformed safety on North Union Street. The Strategy, applied to West State Street features:
• Safe routes to school. Pedestrian crossing signals with audible alerts will be added to all signal-controlled intersections to improve pedestrian safety.
• Curb bump-outs, high-visibility crosswalks and pedestrian refuge islands to provide traffic calming, shorten crossing distances and improve pedestrian visibility to drivers.
• Mini, traversable roundabouts at five intersections will reduce vehicle collisions with injuries, and provide safe places for pedestrians to cross.
ACCIDENT STATISTICS
Accidents Injuries Ped/Bike 2018 110 25 4 2019 135 30 5 2020 94 14 1 2021 92 23 5 2022 79 12 1 2023 90 23 4
2024 RAISE Grant Program Page | 2
• A continuous, 10’-wide protected bike lane/shared-use path will finally create that safe “Town-to-Gown” connector for college students and others using bikes, scooters, and mobility chairs all the way to St. Bonaventure University.
• Street furniture along the corridor will provide respite for pedestrians and transit users.
• Enhanced bus stops with dedicated pull-offs and shelters will make public transit more convenient, safe, and comfortable.
Modern roundabouts reduce intersection crashes and they dramatically reduce crash injuries.
However, most American roundabouts require too much space for cities – where they might offer their greatest benefit. That is why the Federal Highway Administration is promoting demonstration projects with mini-roundabouts, those with a small, completely traversable center island, typically 16 - 45 ft.in diameter.
The FHWA recommends mini-roundabouts where truck and cross street traffic is light:
https://edocs-public.dot.state.mn.us/edocs_public/DMResultSet/download?docId=20079406.
West State Street provides the perfect context. Since the construction of I-86, through-travelers, including most trucks, now bypass Olean. Today, West State Street is a neighborhood connector and small business corridor. Trucks amount to less than 2% of traffic in the downtown zone, and less than 6% at St. Bonaventure University.
A promising aspect of mini-roundabouts is their small footprint. Three mini-roundabouts in downtown, between North Union and 7th streets, will fit neatly within the City’s right-of-way.
Crosswalks will require minimal setbacks. These roundabouts will eliminate two signal intersections and add 4-way utility to a third intersection that is currently limited to right turns only. That intersection is currently one of the most dangerous places for a pedestrian to cross.
Fully traversable mini-roundabouts improve traffic flow while reducing peak speeds and improving pedestrian safety. Truck turning templates have been used to ensure feasibility of these roundabouts.
https://edocs-public.dot.state.mn.us/edocs_public/DMResultSet/download?docId=20079406
2024 RAISE Grant Program Page | 3
During the 2023 public meeting on project goals and options, a consensus emerged that we needed one more roundabout – at a vexing, off-set intersection at Independence Drive that is notorious for accidents. Traffic is often heavy and misalignment of the right-of-way puts left-turning traffic into the path of through traffic. A traversable, mini-roundabout will solve this problem and save many drivers the trauma of an injury accident.
The precedent image is from Queenstown, New Zealand, a resort town with many pedestrians, tourist buses, and logging trucks. This could be a lethal mix but mini-roundabouts in downtown Queenstown keep pedestrians safe in this compact, walkable district. They improved the flow of mixed traffic, too.
The Connecting Communities project, which yields a 3.18:1 benefit cost ratio, will improve safety; environmental sustainability, quality-of-life, mobility and community connectivity, and economic competitiveness of the underserved populations living in the Historically Disadvantaged Communities and Areas of Persistent Poverty adjoining West State Street.
Using the NYS DOT Safe-Eval rubric and the values from the Benefit Cost Analysis Guidance 2024 Update, we calculate the annual monetized savings due to improved safety will be $5,059,600. This represents 82% of all calculated benefits. Please see our BCA Narrative and BCA Calculations for our analysis.
Environmental Sustainability Environmental sustainability is a primary project purpose that we can achieve because we are updating the design of West State Street to embrace its new use-case. Before I-86 was constructed, West State Street was a major east-west highway, optimized for through-travelers and trucks. Today, West State Street is a neighborhood connector in a business district.
The biggest change to the use case has been the explosion in pedal-powered and battery-powered personal mobility. During COVID, it seemed that everyone bought bikes. Electric scooters have become popular. Older and disabled residents are newly empowered with battery-powered mobility chairs. Today, West State Street has no facilities for these travelers.
Equally, pedestrian utilization is up. On adjoining North Union Street, pedestrian utilization is up 400% during summer, due to its inclusive makeover. People are walking for pleasure and exercise, and we would like to encourage walking and rolling to work, and for errands, too.
New, complete-street design features, and mode-shift will advance our Environmental sustainability goals:
• Reduced traffic delay and mode-shift will reduce transportation-related air pollution and greenhouse gas emissions in the Historically Disadvantaged Communities, representing Areas of Persistent Poverty that line West State Street. (91% of the project budget will be invested in Areas of Persistent Poverty)
Traversable mini- roundabout in Queenstown, NZ
2024 RAISE Grant Program Page | 4
• The protected bike lane and shared-use path will…