0011805214
A. THIS IS A "WORK PLAN" TASK ORDER RFP TO MATOC General Construction, Area IV ONLY.
In accordance w ith FAR 36.204 the magnitude of scope is betw een $1,000,000 and $5,000,000.
This RFP is in accordance w ith terms and conditions of 4th option year of MATOC General Construction contracts issued by 411th Contracting Support Brigade (CSB). The Proposals from offerors other than these MATOC Contractors w ill not be considered for aw ard, Parent Contract number; W91QVN18D0080, 0082, 0084, 0085, 0089, 0091, 0116.
OFFERORS MUST COMPLY WITH THE FOLLOWINGS;
B. Site Visit: Offerors w ho intend to propose on this solicitation are encourage to attend the site visit. See site visit clause FAR 52.236-27 in Section L. Offerors are required to have a valid Korean Identif ication Card and compliant w ith any other health directives required for base access w hen attending the site visit orientation.
C. If MATOC contractor is unable to submit the proposal in response to this RFP, the contractor shall submit the "No-Offer Letter' by date and time specified in this solicitation.
D. The proposal shall be submitted to chonghyon.kw on.ln@army.mil.
MS. KWON, CHONG-HYON 315-763-5693
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
22-Jun-2022
(RFP)
(IFB)
X
CALL:
Construct Pre-Engineered Metal LSA, Camp Carroll*
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________150 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________14 Jul 2022 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
RCO DAEGU, UNIT #15682
APO AP 96218-5682
UNITED STATES
W90VN9
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
01:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
H20-10054-2J
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W90VN922R0074 25
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W90VN922R0074
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Work Class: K
FFP
Construct Pre-Engineered Metal LSA, Camp Carroll* (Work Plan). The Contractor shall provide all necessary resources for this requirement and perform Project No.
H20-10054-2J, in accordance with the Statement of Work (SOW), Specification, Drawings, Terms and Conditions of this contract contained herein.
FOB: Destination
PURCHASE REQUEST NUMBER: 0011805214
PSC CD: Y1EC
NET AMT
0002 1 Job Work Class: L
FFP
Construct Pre-Engineered Metal LSA, Camp Carroll* (Work Plan). The Contractor shall provide all necessary resources for this requirement and perform Project No.
H20-10054-2J, in accordance with the Statement of Work (SOW), Specification, Drawings, Terms and Conditions of this contract contained herein.
FOB: Destination
PURCHASE REQUEST NUMBER: 0011805214
PSC CD: Y1EC
Estimated cost for War Hazard cost
FFP
is zero (0)
Section C - Descriptions and Specifications
SOW
GENERAL DESCRIPTION OF WORK TO BE COMPLETED
PROJECT NO TITLE LOCATION
H20-10054-2J Construct Pre-Engineered Metal LSA (Work Plan) Camp Carroll*
DESCRIPTION: The work to be performed shall be in accordance with all drawings and specifications provided under this contract.
a. Work by Contractor:
(1) The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and specifications.
(2) The contractor shall construct pre-engineered metal LSA at Camp Carroll* in accordance with the specifications and drawings.
b. Work by In-House Labor: Not applicable to this project.
c. Work by Troop Labor: Not applicable to this project.
(3) Performance Period: Shall be 150 calendar days, including 120 days for procurement of US origin materials after Notice to Proceed (NTP) is issued at the Post Award Conference (PAC). There will also be a Pre-Construction Conference (PCC) upon government’s acceptance of the 100% drawing package and respective design analysis.
PRINCIPAL FEATURES: This project shall include the following:
Work Plan Special Requirement
1. It is highly recommended for the contractor to attend the site orientation conducted by the contracting office and DPW to get a clear understanding of the site overview which could impact design and construction.
2. The contractor shall submit conceptual drawings, including scope of work to DPW, Area IV, Design branch via 411th Contracting Support Brigade (CSB) included with their proposal. The conceptual drawing will be reviewed for its acceptability during the technical evaluation stage.
3. The contractor shall submit 50% (Twenty (20) calendar days after the PAC) and 100% (Thirty (30) calendar days after the PAC) structural drawings and structural analysis by registered and certified engineer with bill of material and quantities for approval prior to commencing construction unless otherwise at government’s discretion. It will be up to the Government who may allow concurrent work such as demolition to be ongoing during the design phase.
4. The contractor shall consider that the proposed site layout plan may change depending on the site conditions and therefore, attendance at site survey during the solicitation phase is encouraged.
5. The contractor shall submit and get approval of shop drawings and detail drawings for construction.
6. Construction materials can be carried into the construction site every Tuesday through Thursday.
Schedule #I, Construction/ Alteration (L): All work shall be in accordance with the attached drawings and specifications.
A. Civil Work
1. Install fire water line (D=150, PVC), post indicator valve including tapping sleeve, tapping valve, valve box, other fittings, and necessary accessories, thrust blocks, and anchor blocks.
2. Install sewer lines, surface cleanout, and sewer manhole.
3. Construct sidewalk, concrete curbs, and pavement.
4. Construct storm drain lines and surface inlets, manholes curbs and gutters.
5. Construct landscaping.
B. Architectural Work
1. Construct reinforced concrete foundation and steel structure building
2. Install standing seam metal roof system, roof insulation panel, fasia and soffit, rain gutter, downspout, and wall insulation panel system with necessary accessories
3. Install canopy for 1st floor entrance.
4. Install concrete stoop for 1st floor entrance.
5. Install exterior steel structure type stairway and stair guard rail.
6. Install partition wall with metal stud, blanket insulation, gypsum board with necessary accessories.
7. Install door and door frame with door hardware.
8. Install aluminum window, blind and oak window sill.
9. Install ceiling suspension system with acoustical ceiling tile.
10. Install ceiling suspension system with gypsum board finish.
11. Paint interior surface.
12. Install stair rubber flooring.
13. Install vinyl composition tile and vinyl base.
14. Install epoxy finish flooring.
15. Install building signage and room signage.
C. Mechanical Work
1. Provide new split system heat pump units complete with associated refrigerant pipes, condensate pipes, insulation, insulation jacketing, thermostats, thermostat lock boxes, central controller, access doors, stainless steel wire-mesh screens, concrete pads, concrete splash blocks and all necessary accessories and parts.
2. Provide new ventilation system including dedicated outdoor air system, roof exhaust fan with associated ductwork, control panel, diffusers, registers, dampers, controllers, thermostats, emergency shut-off switches, concrete pads, refrigerant pipes, condensate pipes, insulation, access doors, concrete splash block and all necessary accessories and parts.
3. Provide new electric wall heater and unit heater as indicated.
4. Provide new drainage system for valve room including necessary accessories and parts.
5. Provide new wet pipe fire sprinkler system with all necessary accessories and parts as indicated.(The fire sprinkler routing and pipe sizes indicated in this drawing are at conceptual level. The contractor shall submit drawing(s) with FPE`s (fire protection engineer) stamp in accordance with applicable codes and regulation prior to construction for approval from DPW and Fire Department. The contractor bears the full responsibility for respective costs in meeting these codes and associated regulations.)
D. Electrical Work
1. Install new led lighting fixtures including wiring, toggle switches, occupancy sensors, conduit, and necessary accessories.
2. Install new power system including transformer, watt hour meter, service lateral, panel board, branch circuit breakers, safety switch, motor starters, receptacles, wiring, conduit, and necessary accessories.
3. Install communication system including telephone/ Lan outlets, conduit, splice can, outside plant cable and necessary accessories.
4. Install lightning protection system including air terminal, down conductor, ground rod and necessary accessories.
5. Install new fire alarm system including fire alarm/mass notification control panel, building transceiver, fire alarm detectors, monitor modules, combination audio/visual signal strobes, conduit, wirings, and necessary accessories.
Schedule #II, Repair/ Maintenance (K): All work shall be in accordance with the attached drawings and specifications.
A. Civil Work
1. Remove existing trees, shrubs, boulders, earth berms and ground covers.
2. Remove existing pavers.
3. Remove existing concrete surface inlets.
4. Provide earth works.
5. Sod with top soil and solid sodding.
6. Reroute/relocate existing underground and aboveground utility lines.
B. Electrical Work
1. Replace existing high voltage cable including splice kit, conduit, and necessary accessories.
TECHNICAL DETAIL SPECIFICATIONS
GENERAL: The specifications are from the "Standard Technical Specifications for O&MA Projects, Korea", dated 30 October 2015, issued by the Department of the Army, Installation Management Command. The most current specifications are available (for referral purposes only) on the USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.
SPECIAL CONDITIONS
1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which is incorporated in-to the contract.
2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours (Monday through Saturday) except for Korean Legal Holidays. Any proposed change in working hours must be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR). Please note that there will be an exception for night shift when working on the fire alarm system.
3. NOTIFICATION OF INSPECTION SECTION: The contractor shall also give the project inspector seven (7) working days’ notice prior to each concrete placement, field test, weld application, protective coating application, or any other work deemed by the Government to require inspection.
4. COORDINATION: The contractor shall coordinate his work with all others (subcontractor and government agencies) involved in this project and shall cooperate with all other contractors and government agencies so as to facilitate the general progress of the work. Before proceeding with any work, the contractor and/or subcontractor shall consult applicable drawings and specifications for each trade involved.
5. CONSTRUCTION: The contractor shall submit a request for the construction permit at least ten (10) working days prior to the starting of work. The request shall be submitted to the COR for approval.
6. MATERIALS COMPLIANCE: The contractor shall make certain all materials used meet the requirements of the contract and proof thereof upon request of the COR. Materials not meeting the requirements of the contract shall not be brought to the job site. All materials shall be new and the standard products of a manufacturer regularly engaged in the manufacturing of such materials.
7. HOISTING AND MOVING EQUIPMENT: The Contractor and each subcontractor shall provide and be responsible for all cranes, lifts, and other equipment necessary for proper and efficient movement of materials. The equipment shall be provided with proper guys, bracing, safety devices, and any other items, as required by law.
8. EQUIPMENT: All contractor equipment shall be subject to functional and safety inspection by the COR.
Equipment not completely safe or functional shall be repaired and accepted by the government before work is initiated.
9. RECORD DRAWINGS: During performance of work, the contractor shall accurately record and delineate on a set of full-size blue line prints of contract drawings any changes in such work which constitute any change from the original contract drawings per government’s approval. The set of drawings (one original and one blue line print), thus corrected and changed, usually referred to as “As-Built Drawings”, shall be delivered to the COR at the final acceptance/inspection of the completed work by the Government.
10. US ORIGIN MATERIALS: If applicable, all US Origin Materials will be ordered immediately after Notice to Proceed dependent on Government’s direction if such material is not yet determined.
11. RELEASE OF FACILITIES WITH U.S. ORIGIN MATERIALS: If applicable, Building/facility will not be released to the contractor by the COR until all U.S. origin building construction supplies are available or due within such a time frame that there will be no delay in project completion.
12. UTILITY CUTOVERS AND INTERRUPTIONS: Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and U. S. Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours." Ensure that new utility lines are complete, except for the connection, before interrupting existing service. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruption shall be limited to 4 hours. This time includes for deactivation and reactivation.
13. WORK OUTSIDE REGULAR HOURS: Work outside regular working hours requires Contracting Officer approval. Make request fourteen (14) calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During the period of darkness, associated level of work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours on Saturdays, Sundays, and U. S. Government holidays unless directed otherwise.
14. WINTERIZATION: The contractor may be required to perform the work during the winter season, which may cause the contractor additional cost. These additional incurred costs are contractor’s responsibility. The Contractor shall reflect these costs in the preparation of their proposal.
15. SAFETY: The safety plan must be approved before any work can be performed on this contract. Hard hats, suitable work boots and other necessary personnel protective gear per safety regulations are mandatory. Contractors are required to get a written permission from safety office (POC: Mr. To, Pong Uk, DSN: 768-8971) and Fire and Emergency Service (POC: Fire Communication office, DSN: 768-4120) prior to entering confined spaces (i.e., manholes). Contractors should be properly trained and equipped with PPEs, calibrated air monitoring instrument, to work at confined spaces to insure compliance with OSHA (Occupational Safety and Health Administration) 29 CFR 1910.146.
16. SECURITY: All prime contractor and subcontractor personnel will be required to obtain a station pass from the Base Security Office. It is the prime contractor’s responsibility to provide information to security regarding all prime and subcontractor personnel and a list of all vehicles that will be driven on the site.
17. WARRANTY: The contractor shall be responsible for resolution on any defect/ failure on the contract during the one (1) year warranty period. The contractor shall provide services or/and repair and replacement to the satisfaction of the government. The one (1) year warranty starts the day after final inspection approval from the authorized government personnel.
18. ANTITERRORISM/OPRATIONS SECURITY REQUIREMENTS.
18.1. AT Level 1 Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.
18.2. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area.
Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
18.3. For contractors that do not require CAC but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
18.4. iWATCH TRAINING. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
19. ENVIRONMENTAL MANAGEMENT SYSTEM (EMS): Recycling all eligible material, including glass, paper (including magazines), plastic, aluminum, and cardboard to the maximum extent practicable;
Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content;
Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling;
Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must;
20. CONTAMINATION FIND CLAUSE: When contaminated soil is encountered during excavation work, contractor shall report the findings to the Environmental Office immediately and contractor will segregate contaminated soil from clean soil.
21. INADVERDENT FIND CLAUSE: When potential cultural or historic items are inadvertently found during construction activities, contractor shall cease activities in the vicinity of the discovery and report the findings to the Environmental Office immediately. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch.
12, Para 12-3 J)
22. FUEL TANK AND LINES: If applicable, underground piping associated with POL storage containers shall be tested for integrity and leaks at the time of installation, modification, construction, relocation, or replacement. New underground piping must be protected against corrosion IAW recognized industry standards. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 9, Para 9-3.b. (5))
23. Non-PCB TRANSFORMER CERTIFICATION: If applicable, before contractor replace/install any transformer at USAG Daegu, contractor shall submit two copies of non-PCB (Polychlorinated Biphenyl) transformer certification to COR for each installed transformer. New transformer will be installed after COR's approval for non- PCB transformer certification for each to be installed transformer.
TECHNICAL EXHIBIT I: DELIVERABLE SCHEDULE
DELIVERABLE FREQUENCY
FORMAT OF
COPIES
SUBMIT TO
Preliminary Project Schedule
Within 5 calendar days after the NTP is acknowledged
Electronic copy. COR
Initial Project Schedule
Within 30 calendar days after NTP Electronic copy. COR
Preconstruction Submittals
Within 15 days after NTP Electronic copy. COR
Quality control plan
(QCP)
Within 15 days after NTP Electronic copy. COR
Safety Plan Para. TPIII. 15
Prior to the date of NTP Electronic copy. COR
Construction permission Para.
TPIII. 5
10 working days prior to the starting of work Electronic copy. COR
Notification of need for inspection Para. TPIII. 3
7 working days prior to any work deemed by the Government to require inspection
Electronic copy. COR
DD Form 1354, Transfer, and acceptance of DoD real property
Prior to final inspection Electronic copy. COR
As-built drawings Para. TPIII. 9
Prior to final inspection Electronic copy. COR
AT Level I Training Certificate Para. TPIII. 18.1
NLT 30 calendar days after contract award
All Training Certificates
COR
iWATCH Training Certificate Para. TPIII. 18.4
NLT 30 calendar days after contract award
All Training Certificates
COR
Section F - Deliveries or Performance
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 calendar days, including 120 days for procurement of US origin materials after NTP is issued at the Post Award Conference (PAC). There will also be a Pre-Construction Conference (PCC) upon government’s acceptance of the 100% drawing package and respective design analysis.
* The time stated for completion shall include final cleanup of the premises.
*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.203-2 Certificate Of Independent Price Determination APR 1985 52.204-24 Representation Regarding Certain Telecommunications and
Video Surveillance Services or Equipment
NOV 2021
52.204-26 Covered Telecommunications Equipment or Services-- Representation.
OCT 2020
52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least 51 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
52.244-2 SUBCONTRACTS (JUN 2020)
(a) Definitions. As used in this clause--
Approved purchasing system means a Contractor's purchasing system that has been reviewed and approved in accordance with Part 44 of the Federal Acquisition Regulation (FAR).
Consent to subcontract means the Contracting Officer's written consent for the Contractor to enter into a particular subcontract.
Subcontract means any contract, as defined in FAR Subpart 2.1, entered into by a subcontractor to furnish supplies or services for performance of the prime contract or a subcontract. It includes, but is not limited to, purchase orders, and changes and modifications to purchase orders.
(b) When this clause is included in a fixed-price type contract, consent to subcontract is required only on unpriced contract actions (including unpriced modifications or unpriced delivery orders), and only if required in accordance with paragraph (c) or (d) of this clause.
(c) If the Contractor does not have an approved purchasing system, consent to subcontract is required for any subcontract that—
(1) Is of the cost-reimbursement, time-and-materials, or labor-hour type; or
(2) Is fixed-price and exceeds—
(i) For a contract awarded by the Department of Defense, the Coast Guard, or the National Aeronautics and Space Administration, the greater of the simplified acquisition threshold, as defined in FAR 2.101 on the date of subcontract award, or 5 percent of the total estimated cost of the contract; or
(ii) For a contract awarded by a civilian agency other than the Coast Guard and the National Aeronautics and Space Administration, either the simplified acquisition threshold, as defined in FAR 2.101 on the date of subcontract award, or 5 percent of the total estimated cost of the contract.
(d) If the Contractor has an approved purchasing system, the Contractor nevertheless shall obtain the Contracting Officer’s written consent before placing the following subcontracts:
(e)(1) The Contractor shall notify the Contracting Officer reasonably in advance of placing any subcontract or modification thereof for which consent is required under paragraph (b), (c), or (d) of this clause, including the following information:
(i) A description of the supplies or services to be subcontracted.
(ii) Identification of the type of subcontract to be used.
(iii) Identification of the proposed subcontractor.
(iv) The proposed subcontract price.
(v) The subcontractor’s current, complete, and accurate certified cost or pricing data and Certificate of Current Cost or Pricing Data, if required by other contract provisions.
(vi) The subcontractor’s Disclosure Statement or Certificate relating to Cost Accounting Standards when such data are required by other provisions of this contract.
(vii) A negotiation memorandum reflecting—
(A) The principal elements of the subcontract price negotiations;
(B) The most significant considerations controlling establishment of initial or revised prices;
(C) The reason certified cost or pricing data were or were not required;
(D) The extent, if any, to which the Contractor did not rely on the subcontractor’s certified cost or pricing data in determining the price objective and in negotiating the final price;
(E) The extent to which it was recognized in the negotiation that the subcontractor’s certified cost or pricing data were not accurate, complete, or current; the action taken by the Contractor and the subcontractor; and the effect of any such defective data on the total price negotiated;
(F) The reasons for any significant difference between the Contractor’s price objective and the price negotiated; and
(G) A complete explanation of the incentive fee or profit plan when incentives are used. The explanation shall identify each critical performance element, management decisions used to quantify each incentive element, reasons for the incentives, and a summary of all trade-off possibilities considered.
(2) The Contractor is not required to notify the Contracting Officer in advance of entering into any subcontract for which consent is not required under paragraph (c), (d), or (e) of this clause.
(f) Unless the consent or approval specifically provides otherwise, neither consent by the Contracting Officer to any subcontract nor approval of the Contractor’s purchasing system shall constitute a determination—
(1) Of the acceptability of any subcontract terms or conditions;
(2) Of the allowability of any cost under this contract; or
(3) To relieve the Contractor of any responsibility for performing this contract.
(g) No subcontract or modification thereof placed under this contract shall provide for payment on a cost-plus-a-percentage-of-cost basis, and any fee payable under cost-reimbursement type subcontracts shall not exceed the fee limitations in FAR 15.404-4(c)(4)(i).
(h) The Contractor shall give the Contracting Officer immediate written notice of any action or suit filed and prompt notice of any claim made against the Contractor by any subcontractor or vendor that, in the opinion of the Contractor, may result in litigation related in any way to this contract, with respect to which the Contractor may be entitled to reimbursement from the Government.
(i) The Government reserves the right to review the Contractor’s purchasing system as set forth in FAR Subpart 44.3.
(j) Paragraphs (c) and (e) of this clause do not apply to the following subcontracts, which were evaluated during negotiations:
Section J - List of Documents, Exhibits and Other Attachments
DRAWINGS
APPENDIX "A"
LIST OF APPLICABLE CONTRACT DRAWINGS
GENERAL: The work shall conform to the standard detail drawings (dated 30 November 2015, issued by the Department of the Army, Installation Management Agency, Korea Region Office and located USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK), all of which form a part of the specifications.
Drawing No. Ref. No. Sheet No. Description Date
D-22-20 R-1 1 of 1 Title Sheet 13 Jun 22
" C - 1 1 of 59 Location Plan "
" C - 2 2 of 59 Site Layout Plan "
" AE001 3 of 59 Abbreviations, Material Indications & Symbols "
" AE002 4 of 59 Scope of Works, Structural General Notes, General Notes "
" AE101 5 of 59 1st/2nd Floor Plan & Roof Plan "
" AE201 6 of 59 Elevations "
" AE301 7 of 59 Cross Sections "
" AE401 8 of 59 1st & 2nd Floor Wall Section & Wall Partition Type Key Plans "
" AE402 9 of 59 Exterior Wall Sections "
" AE403 10 of 59 Interior Wall Sections "
" AE404 11 of 59 Stair-1 Section "
" AE405 12 of 59 Interior Wall Partition Type Details-1 "
" AE406 13 of 59 Interior Wall Partition Type Details-2 "
" AE501 14 of 59 Ceiling Details-1 "
" AE502 15 of 59 Ceiling Details-2 "
" AE503 16 of 59 Misc. Details-1 "
" AE504 17 of 59 Misc. Details-2 "
" AE601 18 of 59 Ext/ Int Finish Schedule "
" AE602 19 of 59 Material Color Schedule, Roof Details (Typical) "
" AE603 20 of 59 Signage Plan & Schedule "
" AE604 21 of 59 Signage Details "
" AE605 22 of 59 Door/ Window Types, Schedule & Hardware Schedule "
" AE606 23 of 59 Door/ Window Types, Schedule & Hardware Schedule "
" S-001 24 of 59 General Notes, Design Data and Typical Details "
" SF101 25 of 59 Foundation and Ground Plan "
" SF102 26 of 59 2nd Floor Framing Plan "
" SF103 27 of 59 Roof Framing Plan "
" SF104 28 of 59 Purlin Layout & Wind Load Data "
" S-301 29 of 59 Cross Section-1 "
" S-302 30 of 59 Cross Section-2 "
" S-303 31 of 59 Cross Section-3 "
" S-401 32 of 59 Stair 1 & 2 Plans "
" S-402 33 of 59 Stair-1 Enlarged Section "
" S-403 34 of 59 Stair-2 Enlarged Section "
" S-404 35 of 59 Enlarged Section at Base "
" S-501 36 of 59 Slab / Base and Pier Details "
" S-502 37 of 59 Steel Connection Details "
" S-503 38 of 59 Foundation / Pad and Joint Details "
" S-504 39 of 59 Stair Details "
" M - 1 40 of 59 Legend and Abbreviations "
" M - 2 41 of 59 Equipment Schedule "
" M - 3 42 of 59 General Notes and Scope of Work "
" M - 4 43 of 59 HVAC Piping Plan "
" M - 5 44 of 59 HVAC Duct Plan "
" M - 6 45 of 59 Refgerant Piping Isometric Diagram "
" M - 7 46 of 59 Control Diagram "
" M - 8 47 of 59 Detail Drawings - 1 "
" M - 9 48 of 59 Detail Drawings - 2 "
" M - 10 49 of 59 Detail Drawings - 3 "
" M - 11 50 of 59 Detail Drawings - 4 "
" M - 12 51 of 59 Fire Protection Piping Plan "
" E - 1 52 of 59 Legend, Notes and Scope of Work "
" E - 2 53 of 59 Lighting and Power Plan "
" E - 3 54 of 59 HVAC Power Plan and Lighting Fixture Schedule "
" E - 4 55 of 59 Communication System Plan, One Line Diagram and Lightning Protection System Plan "
" E - 5 56 of 59 Fire Alarm & Mass Notification System Plan, One Line Diagram and Notes "
" E - 6 57 of 59 Panel Schedule "PA" and "PB" "
" E - 7 58 of 59 Power Single Line Diagram and Panel Schedule "MDP" "
" E - 8 59 of 59 Electrical Site Plan "
Section K - Representations, Certifications and Other Statements of Offerors
ATTACHMENT: CONTRACTOR’S TAX EXEMPTION DECLARATION
(1) References:
(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."
(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.
(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.
(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.
(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
This item will be imported specifically for this contract? Yes _________ No ________
(ii) Special Excise Tax:
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
Name of item manufacturer
(iii) Value Added Tax (VAT):
Input VAT on materials purchased for this contract. _________ Input VAT on transportation leased/rented for this contract. _________ Input VAT on equipment leased/rented for this contract. _________ Input VAT on services purchased for this contract. _________ Output VAT on total contract amount. _________
(iv) Special Excise (Petroleum) Tax:
No. of Unit Price Total Tax Liters w/o Tax Tax/Unit Amount
Regular Gasoline __________ (L) ₩_________ ₩________ ₩_________
Premium Gasoline __________ (L) ₩_________ ₩________ ₩_________
Diesel __________ (L) ₩_________ ₩________ ₩_________
Other __________ (L) ₩_________ ₩________ ₩_________
(v) Education Tax.
(3) Name of the oil company from which POL products will be purchased:
Oil Company: _________________________________________ (Name only)
(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.
Contractor’s Signature
Section L - Instructions, Conditions and Notices to Bidders
INSTRUCTIONS TO OFFEROR
1. GENERAL INSTRUCTIONS FOR PREPARATION OF PROPOSAL:
a. Site Visit: Offerors who intend to propose on this solicitation are strongly encouraged to attend the site visit. See site visit Clause FAR 52.236-27. Offerors are required to have a valid Korean Identification card when attending the site visit orientation.
b. Offeror(s) are cautioned to follow the detailed instructions fully and carefully, as the Government reserves the right to make award based on initial offers received, without discussions of such offers.
c. Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted. The proposal is intended to be evaluated, and award made, without discussions with the offerors unless discussions are determined to be necessary. If the Government conducts discussions, the Government shall conduct discussions with all offerors in the in accordance with FAR 15.306, Exchanges with offerors after receipt of proposals.
2. SUBMISSION DOCUMENT: Offers shall be via email to chonghyon.kwon.ln@army.mil by the due time and date specified in block 13.A. of this solicitation. All questions are due No Later than 13:00 hours (01:00PM) Local Time, three (3) workdays after the site visit date specified in Provision FAR 52.236-27 within this solicitation.
a. TECHNICAL PROPOSAL: The pricing proposal shall include the following:
(1) Design Data Submittal: Provide a project specific conceptual drawing(s) which meet “Minimum Requirement for Work Plan”, design data, and other documents indicating offeror’s ability to satisfactorily accomplish the Government design intent and achieves the desired quality end-products in accordance with Work Plan Specifications. As part of the Design Data Submittal, Offeror shall provide:
(a) Drawings
(b) Data Analysis
b. PRICING PROPOSAL: The pricing proposal shall include the following:
(1) Completed Pricing Schedule: Provide a project specific schedule with the proposed project duration (in calendar days) clearly identified (from Government task order award to closeout documents approval), and with adequate detail in the schedule for the repair/construction action to communicate milestones for this project. A schedule which only states the start and end dates/period for the repair/construction action is not acceptable.
(2) Offer Breakdown: Offerors shall submit an offer breakdown that identifies Materials, Labor, and Transportation and Equipment (T&E), and other resources upon which the offeror intends to rely to perform this contract in accordance with the Statement of Work. The offer breakdown must demonstrate that the offeror understands the requirement in the RFP by listing an appropriate amount of materials, labor, and transportation and equipment required to perform the contract in accordance with the Statement of Work and drawings. The Offeror’s proposal must contain all contractor’s costs including mobilization, demobilization, overhead, profit, insurance, design fee and all other costs including but not limited to compliance with environmental laws, tax laws, protection or moving of Government property, engineering services (to include survey work and drawings) and waste disposal inherent to accomplish the work request. No allowance will be made later for any other purpose whatsoever unless specifically allowed elsewhere in the contract. Offeror shall provide one (1) original offer breakdown with price and one (1) copy of the offer breakdown without price in accordance to the provided template below:
(a) Materials:
(I) Local Materials:
(A) Type of material with item description, capacity or model number;
(B) Quantity
(II) U.S. Origin Materials:
(A) Type of material with item description, capacity or model number;
(b) Quantity Labor:
(I) Category of labor;
(II) Quantity (man-days in each category);
(c) Transportation and Equipment:
(I) Description of all transportation and equipment (category and capacity);
(II) Quantity (per trip or equipment-day);
(d) Other Critical Resource(s): Must be fully described.
(3) Section K: Offerors must complete all portions of Section K. The offeror shall review all expenses to ensure that all applicable taxes are excluded from the overall price. In addition, any proposed exemption of a specific ROK tax shall be legitimate, attributable to the contract, and authorized by the applicable stated references.
(4) Design effort on a Work Plan is critical for the offeror to identify their subcontractor who will be submitting the 100% of the drawings and respective design analysis for the Government’s review and acceptance (This is assuming the prime does not have design capabilities). Therefore, it is required as an evaluation factor for the offeror to submit the following information regarding their design subcontractor if the Prime does that have such capability within their company. The following information is required to be submitted with the proposal for Government’s technical review and acceptance:
(I) Design company’s past experience during the past three (3) years on US Government contracts (II) Resumes of the key personnel design team who has experience on construction design projects during the past five (5) years.
Failure to submit the above requirements may be grounds for determining the proposal to be non-responsive and not eligible to be considered for award.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
- Date/Time: 30 June 2022 @ 0830 hrs.
(c) Participants will meet in front of 남김천 휴게소 at 0830 and move to the Camp Carroll* together.
(d) Point of Contact
- POC: Mr. Yi, Tong Ki
- Phone number: 763-5370 (DSN) / 05033-63-5370 (Comm.)
- Email: tongki.yi2.ln@army.mil
Access guidance:
1. The contractor should fill out attached manifest and provide it to Mr. Yi, Chung Pae (chungpae.yi.ln@army.mil) NLT 1300, 27 June 2022.
2. The contractor must possess their own AREA 4 access authorize, due to the escort is unavailable for Camp Carroll*.
3. The contractor must show COVID-19 booster shot record to gate guard, when access to Camp Carroll*.
4. The departure available time for Camp Carroll* is after 14:00 only.
(End of provision)
FAR 15.208
15.208 SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS.
(a) Offerors are responsible for submitting proposals, and any revisions, and modifications, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. Offerors may use any transmission method authorized by the solicitation (i.e., regular mail, electronic commerce, or facsimile). If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposals are due.
(b) (1) Any proposal, modification, or revision, that is received at the designated Government office after the exact time specified for receipt of proposals is "late" and will not be considered unless it is received before award is made, the contracting officer determines that accepting the late proposal would not unduly delay the acquisition;
and-
(i) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of proposals and was under the Government’s control prior to the time set for receipt of proposals; or
(iii) It was the only proposal received.
(2) However, a late modification of an otherwise successful proposal, that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the Government office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation closing date, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Proposals may be withdrawn by written notice at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. The contracting officer must document the contract file when oral withdrawals are made. One copy of withdrawn proposals should be retained in the contract file (see 4.803(a)(10)).
Extra copies of the withdrawn proposals may be destroyed or returned to the offeror at the offeror’s request. Where practicable, electronically transmitted proposals that are withdrawn must be purged from primary and backup data storage systems after a copy is made for the file. Extremely bulky proposals must only be returned at the offeror’s request and expense.
(f) The contracting officer must promptly notify any…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .