About this file
This Request for Quotation (RFQ) Sourcing Event #980 is issued by the Idaho Department of Environmental Quality (DEQ) in conjunction with the Nez Perce-Clearwater National Forests to procure services for conducting crossing condition surveys. The project involves assessing aquatic organism passage and road-stream crossing conditions across the Nez Perce-Clearwater National Forests using the U.S. Fish & Wildlife Service Southeast Aquatic Resource Partnership (SARP) survey protocol. Work is targeted at two project zones in 2025: the South Zone (Race-Cow vegetation project covering 76.6 miles with approximately 111 crossings) and the Central Zone (Clear Creek Integrated Restoration covering 68.4 miles with approximately 70 crossings), with desired outcomes of 40-50 crossings per two-person crew per week, totaling 280 crossings annually or 560 crossings if two crews operate simultaneously. The contract period runs from August 15, 2025, through March 1, 2027, with potential renewal for up to an additional three years pending available funding. The deadline for submitting questions is June 24, 2025, and the RFQ closing date is July 7, 2025. Responses must be submitted through IPRO-LUMA. Field work will occur when roads are accessible and free of snow cover, typically between June 15 and October 31 annually, with contractors expected to work eight hours per day, five days per week (or alternatively ten hours per day, four days per week by request).
The cost proposal must provide fully-burdened hourly rates including overhead, salaries, administrative expenses, travel, per diem (at standard Idaho Federal rates), profit, and supplies, along with estimated annual hours of work and project totals. Equipment costs should be itemized for one-time purchases (waders and boots, stadia rod, clinometer, D10 tape measure, and contractor-supplied ArcGIS-compatible device). Mileage reimbursement is calculated at $0.70 per mile. At least two days of training is required annually, provided by NPCNF aquatics staff, with a mandatory one-week training period during the first week of contract work each year. The evaluation criteria weight experience and qualifications at 75 percent, price and cost-effectiveness at 15 percent, and equipment and resources at 10 percent. The successful contractor must maintain comprehensive insurance including Worker's Compensation (statutory coverage plus $1,000,000 each accident), Employer's Liability ($100,000 minimum per occurrence), Commercial General Liability ($1,000,000 combined single limit per occurrence, $2,000,000 annual aggregate), and Commercial Automobile Liability ($1,000,000 combined single limit), with the State of Idaho named as additional insured. Contractors must supply required field equipment and an ArcGIS Online compatible device and are responsible for lodging arrangements during the survey season.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Idaho Department of Environmental Quality RFQ Sourcing Event #980 Nez-Perce Clearwater National Forests Crossing Condition Surveys
Purpose The Idaho Department of Environmental Quality (DEQ) is requesting responses for the Nez-Perce Clearwater National Forests Crossing Condition Surveys.
PROJECT CONTACTS
Solicitation & Contract Lead:
Carrie Champlin Contracts Manager Carrie.champlin@deq.idaho.gov 208-373-0251
Project Lead:
Sujata Connell Lewiston Regional Administrator Sujata.connell@deq.idaho.gov 208-799-4370
CONTRACT PERIOD
August 15, 2025 – March 1, 2027. This could be renewed, pending available funding, up to an additional three (3) year period.
SUBMISSION DEADLINE & INSTRUCTIONS
| Deadline to receive Questions: | 6/24/2025 | |
| RFQ Closing Date: | 7/7/2025 |
Please submit all responses and questions through IPRO-LUMA. To do so, search for "Open Events" and select the corresponding sourcing event number found above. Remember to register and log in to IPRO-LUMA before submitting your response. You can access the platform here: https://sms-idaho-prd.tam.inforgov.com/fsm/SupplyManagementSupplier/page/XiSupplyManagementSupplierPage?csk.SupplierGroup=LUMA
Project Overview
5.1 LOCATION
Survey locations for each field season will precede planned timber sale road work for the South and Central Zones of the Nez Perce- Clearwater National Forests. Paper maps, FieldMaps maps, road numbers. If the contract is extended, additional sites may be considered/added. Forest staff will review crew progress on a bi-weekly basis and update assigned survey areas as necessary.
Table 1. Planned timber sale area for culvert survey in 2025).
| Year |
| Zone |
| Vegetation Project |
| Road Number(s) |
| Miles |
| Est. # Crossings |
| 2025 |
| South Zone |
| Race Cow |
| FSRs 241, 245, 246, |
247, 410, 420, 2052, 2060, 2062, 9901, 9903, 9906, 9907, 9909, 9910, 76031 & associated spurs
| 76.6 |
| 111 |
| 2025 |
| Central Zone |
| Clear Creek Integrated Restoration (Big Cedar, Pine Knob, Solo Creek, Kay Creek and Clear Corral) |
| FSRs 286, 470, |
650F,1106, 1114, 1129, 1855,1899, 9409, 9441, 9703, 9705, 9706, 9712, 9731, 9735, 7745, 77755, 77746, 77774, 77781& associated spurs
| 68.4 |
| 70 |
Transect Coordinates
5.1.1 Map of Race-Cow vegetation project roads and crossing that need surveys in 2025
5.1.2 Map of Clear Creek Integrated Restoration project roads and crossing that need surveys in 2025
5.2 DESCRIPTION OF WORK
The Nez Perce-Clearwater National Forests Crossing Condition Surveys project is an assessment of aquatic organism passage (AOP) and condition of road-stream crossings on the Nez Perce-Clearwater National Forests (NPCNF). Surveys targeting roads with upcoming timber harvest or water quality concerns will help the NPCNF identify candidates for replacement or AOP installation as funding becomes available. DEQ has active TMDL projects within the Forest boundary that cite sediment contributions from roads, and undersized culverts with potential for mass failure, as a source of sediment in those watersheds but there is not a comprehensive catalog of culvert crossings or conditions.
This project would start to catalog those crossings and culvert conditions and help inform road management practices in sediment impaired watersheds. Assessment of AOP and crossing condition would be done using the U.S. Fish & Wildlife Service (USFWS) Southeast Aquatic Resource Partnership (SARP) survey protocol. SARP is an inventory and prioritization tool designed to help managers and partners identify high priority AOP barrier removal projects. The surveys feed into the National Aquatic Barrier Inventory, a nationwide tool utilized by the Forest to store, share and explore collected data. SARP field forms are available for download using the Survey123 application, and detailed maps using the FieldMaps application can be created to aid in survey collection and planning. The contractor will work with the Forest hydrologist or other NPCNF aquatics staff to set up maps and survey forms on field collection devices. At least 2 days of training is required to learn how to conduct the survey, and NPCNF aquatics staff are available to do this. The survey would be conducted on all mapped stream crossings on specified roads and road segments. Desired outcomes are 40-50 crossings inventoried per two-person crew per week, for a total of 280 crossings annually. If two crews are working simultaneously, the desired outcome is 560 crossings annually.
5.3 MONITORING/MODELING SPECIFICATIONS
The SARP protocol field form and data collection manual are attached to this solicitation (Appendix A and Appendix B) The manual is an in-depth explanation of how to fill out the form and should be printed and one copy brought with each crew while conducting field work. The field form is a paper copy of the Survey123 form that will be used on crew tablets to make data collection more efficient.
5.3.1 Equipment Required for each crew of 2:
1 device compatible with the ArcGIS Online Field Maps and Survey123 applications (contractor is responsible for having this device complete with the required applications) 1 Stadia rod 1 Clinometer or slope measuring device 1 D10 tape (100+ ft) 2 Waders and Wading Boots
5.4 COMPLIANCE
The project scope includes work similar to work that the United States Forest Service (USFS) and DEQ staff routinely engage in. No additional compliance with appropriate laws and regulations should be needed if the work is completed according to the project plan.
5.5 ENVIRONMENTAL CONSIDERATIONS
The project work as described should require no additional restrictions, requirements, or considerations that the Cooperator must adhere to during implementation, except for weather conditions and other natural factors.
5.6 PRE-WORK MEETING
Prior to any field work, the Forest will provide instructions to download and activate ArcGIS FieldMaps and Survey123 forms to the crew lead (see appendix A, B, C). The Forest Representative(s) can assist in setting up these maps for use, if requested. For the first week of the contract annually the crew(s) will be trained on the SARP data collection protocol on Forest roads in the same area covered by the contract. This training will take one week. During trainings, the crew and Forest Representative will review the field protocol, safety, data entry, and deliverables. Contractors will be paid by DEQ via the GNA agreement. USFS and DEQ staff will be paid through their routine budgets. The following Forest Representative(s) are required to attend the trainings with those who complete the work and to provide maps and survey assistance:
Jenna Rolle Forest Hydrologist Nez Perce – Clearwater National Forests (208)-935-4287 jenna.rolle@usda.gov 1008 Hwy 64 Kamiah, ID 83536
5.7 QUALITY ASSURANCE PROCESS AND ACCEPTANCE
The Forest Representative(s) identified in Section 5.6 is responsible for project quality assurance. The Forest hydrologist will conduct quality assurance and control on the first week of collected data annually and provide feedback by the second Monday of the contract. To ensure that this can happen, surveys will need to be sent to ArcGIS Online nightly. The second week of data will also be reviewed by the Forest hydrologist, with feedback given by the third Monday of the contract. The SARP (Southeast Aquatic Resources Partnership) database has its own set of procedures in place to ensure the quality of data collected. The database is maintained by the US Fish and Wildlife Service.
5.8 CONTRACTOR WORK DETAILS
Contractors will be expected to work for 8 hours a day, 5 days a week. This can be amended to 10 hours a day, 4 days a week if the contractor requests.
5.9 PERFORMANCE PERIOD
Surveys can be conducted at any time of year when roads are accessible and free of snow cover. These dates will vary year-to-year dependent on weather conditions but will likely fall between June 15th and October 31st of each year. Over the life of the contract, we would like to fund one to two crews of 2 people for an 8-week period.
| Monitoring Year |
| Start Date |
| End Date |
| 2025 |
| August 15, 2025 |
| October 31, 2025 |
| 2026 |
| June 15, 2026 |
| October 31, 2026 |
SUBMISSION REQUIREMENTS
| 6.1 | Experience and Qualifications: Documentation of your company's experience in similar environmental monitoring projects, including project descriptions, client references, and resumes of key personnel who will be involved in this project. Highlight any experience working in the Nez-Perce Clearwater National Forests. |
| 6.2 | Cost Proposal in Section 10: |
A detailed breakdown of your proposed costs for completing the project, including labor rates, equipment costs, travel expenses, and any other relevant costs.
6.3. References:
Provide at least three professional references from similar projects. Include contact names, phone numbers, and email addresses.
6.4 Required Documents:
Include all relevant licenses, certifications, and insurance documentation. (outlined in section 7)
6.5 Appendix D – Certification Regarding Debarment, Suspension and other Responsibility Matters Form Complete and submit with response
6.6 Appendix E – Certification of Independent Price Determination Form Complete and submit with response
GENERAL TERMS AND INSURANCE REQUIREMENTS
| 7.1 | The successful offeror will be required to sign the DEQ RFQ Signature Page states that the successful CONTRACTOR will adhere to the State of Idaho Terms and Conditions. |
| 7.2 | The following is a brief explanation of the insurance coverages that the DEQ requires of the |
CONTRACTOR. A certificate of insurance will be required of the CONTRACTOR selected.
7.2.1 Worker’s Compensation. The CONTRACTOR, its subcontractor(s), if any, and all employers providing work, labor or materials under this contract are subject employers under the Idaho Worker’s Compensation Law and shall comply with Idaho Statues regarding Worker’s Compensation.
Coverage A – Statutory Coverage B – $1,000,000 each accident for bodily injury by accident; $1,000,000 each employee for bodily injury by disease; $1,000,000 policy limit for bodily injury by disease. If there is an exposure of injury to Contractor’s employees under the U.S. Longshore and Harbor Workers Compensation Act, the Jones Act, or under laws regulations or statutes applicable to maritime employees, coverage shall be included for such injuries or claims. Coverage shall include a waiver of subrogation in favor of the State, its officers, employees, agents, and volunteers.
For the duration of this contract, and until all work specified herein is complete, the CONTRACTOR, its subcontractor(s), if any, and all employers providing work, labor or materials under this contract shall provide Idaho Worker’s Compensation coverage that satisfies Idaho law for all their subject workers.
The CONTRACTOR must have a valid Worker's Compensation insurance policy in effect prior to the DEPARTMENT generating the contract. The CONTRACTOR must show proof of such coverage by presenting to the DEPARTMENT a valid certificate of insurance showing statutory coverage.
7.2.2 Employer's Liability. This coverage is written in conjunction with Worker's Compensation and provides insurance for the employer's liability to its employees in circumstances where the injury is not covered by the Worker's Compensation law and the employer may be subject to common law liability. Employer's liability insurance shall be a minimum amount of $100,000 per occurrence.
7.2.3 Liability Insurance. For the duration of the contract and until all work specified in the contract is completed, the CONTRACTOR shall have and maintain, at CONTRACTOR’S expense, the liability insurance set forth below and shall comply with all limits, terms and conditions of such insurance.
Work under this contract shall not commence until evidence of all required insurance is provided to the DEPARTMENT. Evidence of insurance shall consist of a completed certificate of insurance signed by the insurance agent for the CONTRACTOR and made a part of this contract.
| 7.3 | Required Insurance: |
| 7.3.1 | Commercial General Liability Insurance. The CONTRACTOR shall have and maintain |
Commercial General Liability (CGL) Insurance covering bodily injury and property damage. This insurance shall include personal injury liability coverage; blanket contractual liability coverage for the indemnity provided under this contract and products/completed operations liability. The combined single limit per occurrence shall not be less than $1,000,000 or the equivalent. Each annual aggregate limit shall not be less than $2,000,000, when applicable, and will be endorsed to apply separately to each job site or location.
| 7.3.2 | Commercial Automobile and Commercial Umbrella Liability Insurance. The combined single limit per occurrence shall not be less than $1,000,000 or the equivalent. Coverage shall include additional insured status in favor of the State, its officers, directors, employees, agents, and Volunteers. |
| 7.4 | Additional requirements: |
| 7.4.1 | State of Idaho as Additional Insured. The liability insurance coverage required for |
performance of the contract shall include the State of Idaho, the Department of Environmental Quality and its division, officers and employees as additional insured, but only with respect to the CONTRACTOR’S activities to be performed under this contract.
7.4.2 Notice of Cancellation or Change. The CONTRACTOR shall ensure that all policies of insurance are endorsed to read that there shall be no cancellation, material change, potential exhaustion of aggregate limits or intent not to renew insurance coverage(s) without sixty (60) days prior written notice from the CONTRACTOR or its insurer to the Department of Environmental Quality. CONTRACTOR shall further ensure that all policies of insurance are endorsed to read that any failure to comply with the reporting provisions of this insurance, except for the potential exhaustion of aggregate limits, shall not affect the coverage(s) provided to the State of Idaho, Department of Environmental Quality and its divisions, officers and employees.
7.4.3 Terms of Coverage. If coverage is not available on an occurrence basis, coverage shall be provided on a claims-made basis. For claims made policies, the Retroactive Date must be shown and must be before the date of the contract or the beginning of contract work; insurance must be maintained and evidence of insurance must be provided for at least five (5) years after completion of the contract of work; if coverage is canceled or non-renewed, and not replaced with another claims-made policy form with a Retroactive Date prior to the contract effective date, the contractor must purchase “extended reporting”(tail) coverage for a minimum of five (5) years after completion of contract work.
7.4.4 No Waiver of Sovereign Immunity. In no event shall this Agreement or any act by the State, be a waiver of any form of defense or immunity, whether sovereign immunity, governmental immunity, immunity based on the Eleventh Amendment to the Constitution of the United States or otherwise, from any claim or from the jurisdiction of any court. If a claim must be brought in a federal forum, then it must be brought and adjudicated solely and exclusively within the United States District Court for the State of Idaho. This Section applies to a claim brought against the State only to the extent Congress has appropriately abrogated the state’s sovereign immunity, and is not consent by the State of Idaho, to be sued in federal court, or a waiver of any form of immunity, including, but not limited to, sovereign immunity, and immunity based on the Eleventh Amendment to the Constitution of the United States.
7.4.5 Approval. The required insurance shall be subject to the approval of the State, but any acceptance of insurance by the State shall in no way limit or relieve Contractor of the duties and responsibilities stipulated in the Agreement.
Self-insured retentions must be declared to and approved by the State. The State may require the contractor to provide proof of ability to pay losses and related investigations, claim administration, and defense expenses within the retention.
Contractor will maintain, at its sole expense, the required insurance purchased from an insurer licensed/authorized to transact business in the State of Idaho. Insurance carriers must have an AM Best’s Rating of A-VII or better.
7.4.6 Cancellation. Policies shall provide a minimum of 30 days’ advance written notice of cancellation, material change, or nonrenewal of policies required under the contract to the State. NOTE: Most insurance companies will not provide notice to parties other than the Named Insured. However, in those situations where the insurance carrier refuses to provide notice to the State, the Contractor shall notify the State of any cancellation or reduction in coverage or limits of any insurance within seven days of receipt of insurer’s notification to that effect.
7.4.7 Contribution. Contractor’s insurance shall be issued on a primary basis, non-contributory with any other insurance coverages and/or self-insurance carried by the State. Self-insured retentions must be declared to and approved by the State. The State may require the contractor to provide proof of ability to pay losses and related investigations, claim administration, and defense expenses within the retention.
Evaluation Criteria
| Criterion |
| Weight (%) |
| Description |
| Experience & Qualifications |
| 75 |
| Demonstrated experience in similar environmental monitoring projects, qualifications of key personnel, understanding of relevant regulations and protocols (TMDL). |
| Price/Cost-Effectiveness |
| 15 |
| Reasonableness of the proposed budget, cost breakdown, value for money. Make sure that the bidder can satisfy all the requirements stated in the document without asking for more money after project started. |
| Equipment & Resources |
| 10 |
| Availability of necessary equipment and resources (waders, etc.) and ability to mobilize quickly. |
| TOTAL |
| 100 |
Appendices
· Appendix A SARP Stream Crossing Survey Data Form (see separate attachment)
· Appendix B SARP Instructions for Field Data Form (see separate attachment)
· Appendix C National Fish Passage Coordination Map User Guide (see separate attachment)
· Appendix D Certification Regarding Debarment, Suspension and other Responsibility Matters Form (see separate attachment)
· Appendix E Certification of Independent Price Determination Form (see separate attachment)
Cost Sheet
Cost Sheet must be completed and submitted with your Response. The Offeror must provide a fully-burdened rate which must include, but not be limited to, all operating and personnel expenses, such as: overhead, salaries, administrative expenses, travel (lodging, fuel), per diem (standard Idaho Federal per diem rates apply) profit, and supplies.
Provide cost information for the position you anticipate using for Nez-Perce Clearwater National Forests Crossing Condition Surveys project as described in RFQ Section 5 & 6. Required working hours are listed in Section 5.8
| Fully-burdened Hourly Rate |
| *Hourly Rate (including insurance) |
| Housing/per diem rate |
| Days of Work |
| Total per person |
| Estimated Annual Hours of Work per person |
| Extended Cost |
| $ |
| $ |
| $ |
| 40 |
Project Total
*Housing arrangements will be made by the contractor
Project Mileage per FY
| Estimated Total Miles |
| Current Mileage Rate |
| Total |
$0.70
*Equipment (one time purchase if you don’t have them already, please provide a cost)
| Item |
| Cost per Item |
| # |
| Total |
Waders & Boots
Stadia Rod
Clinometer (or slope measuring device)
D10 Tape Measure (100 + feet)
*The contractor will be expected to supply a device compatible with ArcGIS Online Field Maps and Survey123 applications
Company Name: _ Name of Individual submitting bid:
Phone: Fax:
E-mail: