This is a Request for Qualifications (RFQ) issued by the City of Seattle, Washington, for a Seattle Center Master Planning Consultant. The City seeks qualified consultants to provide master planning services for Seattle Center. Qualifications must be submitted no later than 3:00 pm on Thursday, January 7, 2027. All questions regarding the RFQ must be submitted through the e-procurement portal at https://procurement.opengov.com/portal/seattle no later than 3:00 pm on Tuesday, December 8, 2026. The file does not specify the contract term, renewal options, site visit requirements, or bidders' conferences.
The RFQ document does not contain information regarding pricing terms, set-asides, incumbent contractors, funding sources or amounts, or other financial details. Additional information regarding evaluation criteria, selection methodology, award timeline, and specific scope requirements would be contained within the full RFQ documentation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUALIFICATION # SC-2026-06
Consultant Contract
Project Title: RFQ: Seattle Center Master Planning Consultant
Table 1: Solicitation Schedule
Solicitation Release November 24, 2026
Pre-Submittal Conference (Non-Mandatory) December 2, 2026, 2:00pm
In-Person: Seattle Center Armory, Loft 2 (3rd Floor)
- 305 Harrison St, Seattle, WA, 98109 Virtual:
https://teams.microsoft.com/meet/246815258353
8857?p=2ejShWzKB3oX4UE1sf
Deadline for Questions December 8, 2026, 3:00pm
Response Deadline December 11, 2026, 5:00pm
Response Submission Deadline January 7, 2027, 3:00pm
Interviews if Conducted (estimated) 2/8/2027 - 2/12/2027
305 Harrison St, Seattle, WA 98109
The City reserves the right to modify this.
Changes will be posted on the City website or as otherwise stated.
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://procurement.opengov.com/portal/seattle/projects/327428 https://teams.microsoft.com/meet/2468152583538857?p=2ejShWzKB3oX4UE1sf https://teams.microsoft.com/meet/2468152583538857?p=2ejShWzKB3oX4UE1sf
Procurement Contact Information
Procurement Contact: Christian Mower, Planning and Project Finance Coordinator, christian.mower@seattle.gov,
(206) 719-3706
Unless authorized by the Procurement Contact, no other City official or employee may speak for the City regarding this solicitation until award is complete. Any Proposer contacting other City officials or employees does so at Proposer’s own risk. The City is not bound by such information.
TABLE OF CONTENTS
1. Procurement Contact Information
2. Purpose and Background
3. Performance Schedule
4. Solicitation Objectives
5. Minimum Qualifications
6. Scope of Work
7. Contract Modifications
8. Procedures and Requirements
9. Selection Process
10. Evaluation Section
11. Award and Contract Execution
12. Response Materials and Submittal
Attachments:
A - CEN A & E Consultant Agreement Template_11.12.2026
B - City of Seattle Consultant Questionnaire
C - Consultant Inclusion Plan
D - Seattle Center Century 21 Master Plan
E - Seattle Center Strategic Vision and 10-Year Action Plan
F - Seattle Center Economic Impact Analysis
1. Procurement Contact Information
Procurement Contact: Christian Mower, Planning and Project Finance Coordinator, christian.mower@seattle.gov, (206) 719-3706
Qualifications are to be submitted through the e-Procurement portal at https://procurement.opengov.com/portal/seattle, no later than 3:00 pm on Thursday, January 7, 2027.
Unless authorized by the Procurement Contact, no other City official or employee may speak for the City regarding this solicitation until award is complete. Any Respondent contacting other City officials or employees does so at Respondent’s own risk. The City is not bound by such information.
2. Purpose and Background
2.1 The Opportunity
Seattle Center seeks a multidisciplinary planning and design team to update and reenvision a master plan for its 74-acre campus. This plan will shape Seattle’s most beloved civic place for the next generation. It will also guide the most significant public reinvestment in the campus since the 1962 World’s Fair.
Seattle Center is a living campus that has grown and evolved over six decades in response to changing needs, while keeping its sense of play, wonder, and discovery. Today, it welcomes more than 11 million visits a year, hosts more than 30 partner organizations, and carries generations of civic memory. The selected team will honor that legacy while rethinking how the campus works, how it connects to a rapidly growing city, and how it inspires the people who use it.
Seattle Center is looking for big thinkers who are also good listeners. We seek a team that can synthesize a deep body of existing plans and studies, imagine bold and unexpected possibilities, and then ground those ideas in the realities of funding, phasing, operations, and partnership. The result should be a plan that uniquely belongs to this place, one that grows from Seattle Center’s history, landscape, and people and looks to future generations.
The master plan will serve three purposes:
• A long-range vision for the campus, its open space, its buildings, and its connection to Uptown, South Lake Union, Queen Anne, Belltown, Downtown, and the region.
• A practical framework for capital investment over time, including priorities, phasing, relocation, and surge strategies that minimize disruption to campus operations and partner organizations during construction.
• A guide for the proposed Seattle Center bond program, shaping how bond-funded projects are designed and sequenced, and a foundation for future public, private, and philanthropic investment.
The selected Consultant will lead the master plan. Based on its performance, the City may also retain it to design and implement selected public realm improvements on the campus during the bond program.
2.2 Seattle Center Today
Seattle Center is a 74-acre civic, arts, and cultural gathering place in the heart of Seattle. Born from the 1962 World’s Fair, the campus exists to delight and inspire the human spirit and to build stronger communities.
More than 30 partner organizations call it home, including Climate Pledge Arena, Marion Oliver McCaw Hall, the Museum of Pop Culture, Pacific Science Center, KEXP, and the city’s leading theaters. Seattle Center also https://procurement.opengov.com/portal/seattle produces hundreds of free and affordable events each year, anchors the Uptown Arts and Cultural District, and operates Waterfront Park, extending its stewardship of public life from Uptown to Elliott Bay.
The campus provides significant value as one of the region’s most important economic and cultural engines:
• 11.34 million campus visits in 2025, plus more than 9 million visits to Waterfront Park
• 362 campus events in 2025, including free cultural festivals, Winterfest, Bumbershoot, Northwest
Folklife, and civic gatherings.
• Nearly $3.3 billion in economic output, 19,400 jobs, and nearly $1.1 billion in labor income in 2024
(Seattle Center Economic Impact Analysis, March 2026)
• 2.29 million Seattle Center Monorail riders in 2025, connecting the campus directly to Downtown.
Seattle Center also serves important functions for the city in times of need. The campus has served as an emergency weather shelter, a free health clinic serving more than 33,000 patients over the course of 10-years, and a gathering place for the community to celebrate, protest, and mourn.
Despite its continued success, the campus is showing its age. Core facilities, building systems, and infrastructure, many dating to 1962, are at or near the end of their useful life. From 2003 to 2023, only about half of identified asset preservation needs were funded through capital programs. The most recent voter-approved campus investments date to the 1991 and 1999 levies. Partner organizations on campus face their own capital and financial challenges.
2.3 A Legacy of Bold Planning
Seattle Center has been shaped by a series of ambitious plans, each building on the last:
• 1962 Century 21 Exposition. The World’s Fair established the campus, its landmarks, and its identity as a place for gathering to imagine the future.
• 1990 Master Plan. After nearly three decades of evolving use following the Fair, the 1990 Master Plan reenvisioned how the Center could best fulfill its then-established civic and cultural role.
• Century 21 Master Plan (adopted 2008). This 20-year update to the 1990 Master Plan reclaimed and unified open space at the heart of the campus and emphasized connections between buildings at the edge and open space at the center, between the campus and its neighborhoods, and between the Center’s past and future. It was developed through more than 60 public meetings and remains the governing plan for the campus today. The plan was designed to be flexible and was not intended to be funded in one piece. Instead, each element was to be developed as demand, opportunity, and resources emerged. Its outcomes include the redevelopment of the former Fun Forest site, Artists at Play, and new open space around the Space Needle.
• Recent transformations. Climate Pledge Arena opened in 2021 within the landmarked roof of the former Coliseum. The Seattle Public Schools Memorial Stadium redevelopment is under construction and expected to open in fall 2027. The Seattle Center Monorail Station reconfiguration is underway.
The Thomas Street Redesign completed schematic design.
The Century 21 Master Plan was written for a different city than we are today. Since its adoption, Seattle’s population and employment have grown dramatically around the campus. Light rail is coming to Seattle Center. The climate crisis demands new standards of performance. Patterns of entertainment, work, and public life have changed. The new master plan must respond to these shifts while carrying forward the enduring ideas of Seattle Center and the Century 21 Master Plan: open space as the connective tissue of the campus, a whole greater than the sum of its parts, and flexibility to evolve as opportunity and resources converge.
2.4 Strategic Vision and 10-Year Action Plan
In 2025, Seattle Center and the Seattle Center Foundation completed the Seattle Center Strategic Vision and 10-Year Action Plan. The plan’s vision is that “Seattle Center is where community comes together: an iconic, inclusive destination that delights and inspires the human spirit.” It sets three goals that the master plan will translate into physical form:
A. Cultural Heart. Advance Seattle Center as the region’s heart for arts, culture, sports, and civic engagement.
B. Gathering Place. Boldly reinvest in Seattle Center’s public spaces, create new gateways and connections, enhance the green heart of the campus, address critical infrastructure needs, and make the campus carbon neutral.
C. Financial Sustainability. Secure Seattle Center’s long-term financial sustainability as a social enterprise that leverages earned revenue, reliable public funding, and private investment.
The Action Plan’s second Big Move calls for a comprehensive capital funding proposal for the campus. This master plan is a critical step in delivering on that commitment.
2.5 Bond Planning and Studies Completed to Date
In June 2026, the Seattle City Council unanimously adopted Resolution 32205, a joint resolution with the Mayor supporting reinvestment in Seattle Center. The resolution states the Council’s intent to consider a bond measure for the 2027 ballot. It also requests funding for the Armory renovation and encourages partnership with Seattle City Light and Seattle Public Utilities to move the campus toward carbon-neutral operations.
Seattle Center has completed a substantial body of work to inform the bond and this master plan effort. The selected team will build on these studies:
Seattle Center Campus Modernization and Enhancement Cost Study. This study (Arup, 2026) consolidates Seattle Center’s facility condition assessments, electrification and district energy studies, public realm concepts, and Armory visioning into a campus-wide view of modernization and enhancement needs, with planning-level cost estimates. It covers 12 buildings and campus open space, including the Armory, McCaw Hall, the theaters, the Northwest Rooms, Fisher Pavilion, the Central Utility Plant and two garages. Its scope includes mechanical, electrical, and plumbing renewal with conversion to all-electric systems, roofing and envelope, seismic, fire and life safety, elevators, and open space and site infrastructure. The study organizes costs by building and line item, and sequences them in several construction phases from 2028 to 2038. It serves as the foundation for Seattle Center’s bond planning to date.
Facility Condition Assessments. These reports document the condition, remaining service life and deficiencies of Seattle Center’s buildings and campus systems, with prioritized recommendations and rough-order-of-magnitude costs, and serve as the primary technical basis for the Arup study. They include:
o Roofs: surveys and budgets (Stemper AC, 2021) o Mechanical: HVAC assessments of 17 buildings (Wood Harbinger, 2023) o Plumbing and fire protection: assessment of campus buildings and site steam distribution (Wood
Harbinger, 2024) o Electrical: power system studies of 16 buildings with cost estimates for correcting under-rated equipment (Harris Group and Cochran, 2024) o Seismic: Tier 1 seismic evaluations to ASCE 41-17 (Lund Opsahl, 2025) o Other: cladding and windows, elevators, accessibility, and fire alarm systems
Electrification and Eco-District Studies. The Seattle Center Electrification Master Report (P2S, 2024), evaluates how to move the campus off fossil-fuel steam heating and recommends heat pump systems and envelope upgrades for each building. The Eco District Engineering Assessment for Seattle City Light (Wood Harbinger, 2024), evaluates a carbon-neutral district serving Seattle Center and Climate Pledge Arena through a shared campus condenser loop, solar, and energy storage. Together these studies set the electrification strategy behind the Arup study’s mechanical and electrical scope.
Armory Concept Package. This study (Olson Kundig, 2025) explores concepts that renew the landmark Armory as an open civic hub, with a daylit atrium, a public rooftop, and expanded performance and food hall space. The concept defines the Armory scope and cost estimates (GLY Construction, 2025) carried in the Arup study.
Open Space Cost Estimates. Conceptual cost estimates (Sellen, 2026), schedule, and pedestrian routing plans for five campus open space improvement packages serve as the basis for the open space scope and phasing in the Arup study.
These studies identify the scale of deferred need and explore preliminary concepts. The master plan will provide a vision, a shape, a sequence, and further definition for the open space and landscape framework.
Seattle Center will share these studies with the selected Consultant. Respondents can prepare a complete response from the information in this RFQ.
Seattle Center staff are also advancing bond program planning. This work includes:
• Phasing and sequencing. Testing assumptions about project order, dependencies, and construction durations.
• Revenue impacts. Forecasting how closing buildings and spaces during construction will affect earned revenue.
• Program impacts. Working with Seattle Center departments to understand how construction will affect campus programs and where they can operate in the interim.
The City’s early planning work establishes a starting point for the master plan and informs the breadth of the bond measure. The selected Consultant will bring the specialized expertise to test and challenge these assumptions, offer new ideas and fresh perspectives, and develop the strongest ideas into detailed, implementable plans.
3. Performance Schedule
The City anticipates executing the contract in Q1 2027 following the consultant selection process.
The work is organized in two parts, described in Section 6.1. Part A, Master Planning Services, runs from Q1 2027 through Q4 2028. Part B, Implementation Services for selected public realm improvements, may begin as early as 2028 and could continue through approximately 2038. The City will define the bond package, including its final project list, and submit it for the Mayor’s approval by April 2027, before the master plan is complete.
The Consultant will prioritize the master plan, which the City intends to complete regardless of the bond outcome. Part A base services include the master plan, a campus design framework, and a bond readiness roadmap. The City has identified initial funding for Part A services. If the bond measure passes in November 2027, the City intends to add detailed design guidelines, bond readiness work streams, and other services by amendment.
During negotiations, the selected team will propose a detailed work plan and help the City determine what scope is feasible within available funding. The City anticipates the following general timeline.
Period Part A: Master Planning Bond Program Part B: Implementation
Q1 to Q2
Discover and synthesize: review existing plans and studies, document existing conditions, listen to partners and stakeholders, and begin bond readiness roadmap
Bond package defined by City departments and submitted to the
Mayor for approval
Q2 to Q4
Imagine: blue sky ideation, campus-wide concepts and alternatives, and complete bond readiness roadmap
Vote in November 2027
2028 Shape and adopt: preferred plan, phasing, campus design framework, and final master plan by Q4 2028. If the bond measure passes, detailed design guidelines and bond readiness work streams may be added by amendment.
If the bond measure passes, early bond projects begin
Public realm design services may be authorized as needed
2029 to
Design of the first major bond projects begins
Public realm design for selected areas may be authorized as needed
2031 to
Construction of bond projects in sequenced phases
Public realm design and construction administration for selected areas may be authorized as needed
Seattle Center anticipates that work before the November 2027 vote will focus on discovery, early ideas, and bond readiness work. Public information prepared before the vote will be factual and educational, consistent with RCW 42.17A.555.
3.1 Bond Schedule and Concurrent Planning Efforts
The master plan will be developed while several related efforts move forward. The selected team will coordinate with each and integrate their outcomes.
Effort Lead Anticipated Timing Relationship to the Master
Plan
Seattle Center bond measure
City of Seattle and Seattle
Center
Bond package to Mayor for approval by April 2027, Vote in
November 2027
Master plan guides the design and sequencing of bond-funded projects
Monorail Station
Reconfiguration
(SIGNAL Architecture +
Research)
Seattle Center Construction Q3 2026 through Q4 2027
Gateway and arrival experience at the campus core
Memorial Stadium
Redevelopment
Seattle Public Schools Opening Q4 2027 Reshapes the campus center and event capacity
Thomas Street Redesign
(GGN)
Seattle Center Schematic design currently on hold
Key east-west connection to
South Lake Union
Armory Concept
Development (Olson
Kundig)
Seattle Center Q1 2027 Additional concept development for the armory and possible outdoor connections
Monorail Bridge Design
(SIGNAL Architecture +
Research)
Seattle Center Q1 2027 Pedestrian connection from
Monorail to the Armory
Fisher Pavilion
Decarbonization and
Revitalization
(BuildingWork)
Seattle Center Currently in design, Construction Q2 2028 through Q2 2029
Fisher Pavilion’s direct connection to open space and surrounding corridors
4. Solicitation Objectives
Through this RFQ, Seattle Center seeks a multidisciplinary team with the creativity, technical depth, and collaborative spirit to deliver a visionary and achievable master plan. We welcome teams led by planners, urban designers, landscape architects, and/or architects. Respondents may assemble a team that demonstrates the highest creativity, technical skill, and client management expertise.
The City expects the master plan to embody the following guiding principles:
• Uniquely Seattle. The plan should express what makes this place one of a kind: a World’s Fair legacy, a civic commons for every community, and a stage for the region’s culture.
• Welcoming to All. The plan should advance the City’s commitment to race and social equity, accessibility, and free and affordable public access; serving as a place for people to come together, celebrate differences, and strength through diversity.
• A Green Heart. Landscape and a generous public realm within the center of the city are the campus’s defining element. Open space should be preserved, expanded, and designed to support flexible programming while protecting the established sense of place that makes the campus beloved.
• Built for Events and Everyday Life. The campus must work as well for a quiet weekday as for a festival weekend that draws hundreds of thousands. Major event operational considerations such as staging, load-in and load-out, crowd flow, security, and back-of-house functions for a diverse range of partner organizations, vendors, and operators, should shape the plan from the start.
• Connected to the City. The campus should open outward to its neighbors with clear gateways, safe and inviting routes, and seamless wayfinding and links to light rail, the Monorail, King County Metro, streetcar, and major thoroughfares such as Denny Way, Mercer Street, and Thomas Street.
• Partners Thrive. More than 30 partner organizations depend on the campus. The plan should strengthen their ability to achieve their missions for the long term by supporting overall visitor experience. Some buildings will close temporarily during construction, and others may remain partly open through phased construction. The plan should sequence construction, relocation, and surge space to minimize disruption.
• Resilient and Carbon Neutral. The plan should chart a path to carbon-neutral operations, renew aging infrastructure, and strengthen the campus’s role to support the community in emergencies.
• Financially Sustainable. The plan should identify new or underleveraged revenue opportunities, real estate and partnership strategies, and investments that reduce long-term operating costs.
• Grounded and Buildable. Bold ideas must be paired with clear phasing, realistic costs, and a sequence the City can realistically deliver over time.
5. Minimum Qualifications
Minimum qualifications are required for a Consultant to be eligible to submit a response. Your response must show compliance with these minimum qualifications. Responses that do not meet these qualifications shall be rejected by the City without further consideration.
Minimum Qualifications
A. Prime consultant must have served as prime or lead design firm on at least one master plan, framework plan, or comparable long-range plan, adopted, approved, or delivered in final form within the past 15 years, for a public agency or a civic, cultural, or institutional client, for a multi-building campus, district, attraction, or large urban site of at least 15 acres that included public open space.
B. The proposed day-to-day planning lead or lead designer must have served in a lead role on at least two
(2) plans meeting the criteria in (a), including work completed at a previous firm.
C. Team must include a licensed landscape architect.
D. Team must include a public engagement lead, from the prime consultant’s staff or a subconsultant, with experience leading community engagement for at least one (1) public planning project in the Seattle area within the past 10 years.
E. Local affiliation: If the prime consultant is based outside the Seattle metropolitan area, the team must identify an affiliation with a local office.
6. Scope of Work
6.1. Overview
The Consultant will lead the development of a new master plan for the Seattle Center campus, working in close partnership with Seattle Center staff, partner organizations, City departments, and the public. The plan will succeed the Century 21 Master Plan as the City’s long-range guide for the campus.
The Consultant will synthesize what is already known, generate new ideas to respond to current and future needs, test them rigorously, and deliver a plan that is both inspiring and implementable. The plan will address the campus as a whole and its relationship to the surrounding neighborhoods, including perimeter properties and the streets that frame the campus.
The scope is organized in two parts:
Part A: Master Planning Services Part B: Implementation Services
What Base services: master plan, campus design framework, and bond readiness roadmap. Additional services: detailed guidelines and bond readiness work streams (Section 6.3)
Public realm design and construction administration for selected areas of the campus (Section 6.4)
When Q1 2027 through Q4 2028 As early as 2028, through approximately 2038
Contract Status Base contract, with additional services added by amendment in accordance with Section 8.13
Anticipated additional services, added by amendment in accordance with
Section 8.13
Trigger Contract execution Bond funding approval, satisfactory
Part A performance, and City authorization, which may occur before master plan adoption
If the bond measure fails Complete the master plan, campus design framework, and bond readiness roadmap
Scaled to available funding or deferred
City team and decision-making. Seattle Center’s Planning and Capital Development team will manage this contract and coordinate with partner organizations and City departments. Seattle Center will lead all communications about the bond measure, and the Consultant will prepare factual planning materials to support the bond. Seattle Center leadership will set direction and approve the final master plan, in collaboration with the Seattle Center Advisory Commission and a steering committee composed of Seattle Center department directors.
6.2. Key Planning Topics
The master plan is expected to address the following topics. Their relative emphasis will be refined with the selected Consultant during negotiations.
A. Vision and Blue Sky Ideation. Lead a collaborative process with campus stakeholders and the public that fosters bold, unconstrained thinking about what Seattle Center could become. Explore big ideas, grounded in the guiding principles under Section 4, before narrowing to what is feasible, and carry the most compelling ideas forward into the plan.
B. Landscape, Public Realm, and Open Space. Treat landscape and the public realm as the organizing system of the campus. Preserve and maximize open space for flexible programming while protecting its character and sense of place. Address tree canopy, ecology, stormwater, shade, comfort in all seasons, and the “green heart” called for in the Strategic Vision and 10-Year Action Plan, and leverage the public realm to support climate and heat resilience and biodiversity.
C. Events, Programming, and Operations. Understand how the campus operates. Account for festivals, concerts, sporting events, and daily public life. Address event staging, load-in and service access, crowd movement, security perimeters, power and water at event sites, maintenance operations, and the needs of production staff. Plan waste, compost, and recycling collection, storage, and hauling that work reliably and out of public view, including during event surges, consistent with the City’s recycling and composting requirements.
D. Partners, Facilities, Relocation, and Surge Planning. Consider impacts to more than 30 partner organizations and their operations throughout the plan. Key questions the Consultant will help address include which programs remain, are relocated, or consolidated, whether functions are better centralized or distributed, which uses belong on or off campus, and how surge and swing space can minimize program disruptions during construction.
E. Infrastructure, Utility Corridors, and Sustainability. Integrate findings from prior facility condition and infrastructure studies. Identify utility corridors and opportunities for dual-use spaces, such as service routes that also serve as public promenades or event infrastructure. Chart a path to carbon-neutral operations in partnership with Seattle City Light and Seattle Public Utilities, and strengthen the campus’s resilience and emergency role.
F. Mobility, Transit, and Gateways. Consider connections to Waterfront Park, the future light rail station on the Ballard Link Extension (BLE), the Monorail, King County Metro, potential future streetcar connections, and existing and planned bicycle and pedestrian networks. Create clear, welcoming gateways and wayfinding. Address parking, rideshare, micromobility, curb management, and loading in a transit-rich future. Strengthen connections to major thoroughfares and edges.
G. Topography and Accessibility. Work with the campus’s hilly terrain, which shapes nearly every connection on site. Treat grade changes as both a constraint and an opportunity. Plan clear, accessible routes for people of all abilities, manage service and loading access across changing grades, reduce modal conflicts, and resolve how buildings meet the ground at their entries and edges. Explore how terraces, overlooks, and level changes can enrich the campus experience.
H. Real Estate, Revenue, and Perimeter Properties. Identify real estate development opportunities, public and private partnership models, and density transfer potential. Consider perimeter properties and opportunities for compatible uses that activate campus edges. Explore revenue-generating opportunities that support Seattle Center’s role as a social enterprise and the long-term operation of the campus.
I. Heritage, Landmarks, and Design Review. Respect the campus’s designated landmarks and World’s Fair legacy. Plan for early and ongoing engagement with the Landmarks Preservation Board, the Seattle
Design Commission, and other review bodies. Historic Resource Assessments and landmark nominations are not part of this scope.
J. Phasing and Implementation. Propose a plan that is buildable over time. Key questions include how projects should be sequenced, how their cost, dependencies, and operational impacts compare, and which investments belong in the near-term bond program and which in the long-range vision.
6.3. Part A: Master Planning Services
Services may include, but are not limited to:
1. Review and synthesize the Century 21 Master Plan, the Strategic Vision and 10-Year Action Plan, facility condition assessments, bond planning studies, and the related plans listed in Section 6.8.
2. Document existing conditions, including land use, open space, public realm, circulation, utilities, building conditions, topography and grade changes, event operations, service and waste operations, and the regulatory framework.
3. Facilitate visioning and blue sky ideation sessions with Seattle Center leadership, partners, and the community.
4. Develop and evaluate campus-wide alternatives against agreed criteria.
5. Prepare a preferred master plan, including an open space and landscape framework, mobility and access framework, land use and facilities framework, infrastructure and utility framework, and event operations framework.
6. Prepare campus-level , relocation, consolidation, highest and best use, and surge planning strategies, with test-to-fit studies for priority facilities.
7. Prepare real estate, revenue, partnership, and density transfer analyses, supported by market and financial expertise.
8. Prepare phasing and implementation strategies with order-of-magnitude cost estimates.
9. Coordinate with Sound Transit, King County Metro, Seattle Public Schools (SPS), and City of Seattle departments, such as Seattle Department of Transportation (SDOT), Seattle City Light (SCL), Seattle Public Utilities (SPU), Department of Neighborhoods (DON), etc.
10. Assist in presentations to elected officials, City leadership, the Seattle Center Advisory Commission, the Seattle Design Commission, the Landmarks Preservation Board, partner organizations, and community groups, at the direction of the City.
11. Support environmental review under the State Environmental Policy Act (SEPA) as needed.
12. Prepare a campus design framework that carries the master plan into individual projects, with design principles for the public realm, frontages, buildings, and utility corridors.
13. Prepare a bond readiness roadmap that identifies the work streams, sequence, and estimated level of effort needed to prepare bond-funded project to proceed quickly after the vote.
14. Produce a clear, highly visual master plan document, along with factual summary materials suitable for public education.
15. Prepare factual public information about the master plan and its relationship to the bond program.
Additional Services. The City may add the following services by amendment, in 2027 or after bond approval, as funding becomes available. The bond readiness roadmap will help the City define their scope, sequence, and fee.
1. Bond project briefs for each anticipated project or package, defining scope, limits of work between building and public realm, dependencies, and preliminary cost.
2. Validation of the relocation and surge sequence for partner organizations and Seattle Center functions, through test-to-fit studies of potential swing spaces.
3. An interim utility strategy so early projects align with the long-term campus utility and energy plan.
4. Detailed campus design guidelines for the public realm, buildings, and infrastructure, including frontages, materials, planting, lighting, and signage.
6.4. Part B: Implementation Services
The City may retain the selected Consultant to design and implement selected public realm improvements of the campus through construction. The City currently anticipates that the first area will be the gathering spaces in the southeast quadrant of the campus. Final selections for individual public realm improvement projects remain at the City’s discretion, based on the Consultant’s performance during Part A, program needs, and available funding, and the City may assign more, fewer, or different areas. Part B services may be authorized after bond funding is approved, including before the master plan is adopted, and are anticipated to continue through approximately 2038. Part B services may include:
• Public realm design and construction administration for the selected areas, from design through construction completion.
• Design guidelines stewardship. Maintain and update the campus design guidelines as projects move forward, at the City’s direction.
Relationship to building projects. Seattle Center will hire architects for building improvements through separate solicitations. The City anticipates two types of building projects:
• Buildings with open space connections. The building architect designs the building improvements and the building’s immediate site connections, consistent with the campus design framework and any design guidelines. Where the building adjoins public realm improvements assigned to the master plan Consultant, the two firms will work together under separate City contracts to coordinate their designs and bid documents.
• Buildings with major outdoor spaces. Where a building and a significant outdoor space are best designed and built together, those public realm space improvements will be included in the building solicitation and designed by the selected building team.
For either type, each contract will define the limits of the work, the firm that assembles and issues the bid documents, shared document standards, and construction-phase responsibilities.
Competing for other work. The Consultant and their subconsultants may compete for other bond-funded work, including as the prime building architect or as a subconsultant on a building team whose scope includes adjoining public realm, subject to the safeguards in Section 6.9. All public realm improvements not selected for the Consultant, along with buildings, will be procured competitively through separate solicitations.
Part B services will be authorized by amendment in accordance with Section 8.13, in phases matched to available funding. The City is not obligated to authorize these services or to assign any minimum amount of campus public realm to the Consultant.
6.5. Community and Stakeholder Engagement
Public engagement is essential to a plan that belongs to all of Seattle. The Consultant team must include a public engagement lead, as required in Section 10, who will work with Seattle Center to design and carry out an inclusive engagement program. The program should reach residents across the city, the surrounding neighborhoods, partner organizations, event producers, the business community, and communities that have historically been underrepresented in civic planning. The City will lead engagement with Tribal Nations, with support from the public engagement lead. The engagement program should also include urban Native and other Indigenous communities. Engagement should use both in-person and digital methods and should make the planning process itself visible and inviting on campus.
6.6. Team Composition and Subconsultant Participation
The City anticipates a multidisciplinary team that may include expertise in urban design and master planning, campus planning, landscape architecture (including design and construction administration of public realm improvements), architecture and facility planning, transportation and mobility, structural, mechanical, electrical, and plumbing engineering, civil and utility engineering, solid waste and recycling logistics, accessibility, sustainability and energy, event and venue operations planning, real estate and economic analysis, cost estimating, historic preservation, public engagement, and graphic communication and wayfinding. Teams may add other specialties or propose a team composition they believe will strengthen the plan.
Seattle Center’s programs and events staff manage the logistics of campus events and will work closely with the Consultant. The City may also engage an events programming consultant to help imagine new uses and events for the campus and plan their logistics. Respondents are not required to include this expertise on their team. The City may later ask the Consultant to add an events programming consultant as a subconsultant or may contract with one directly.
Subconsultants may be listed on more than one Respondent’s team. By submitting, each Respondent certifies that any agreement with a listed subconsultant does not prevent that subconsultant from contracting with another Respondent selected under this RFQ. The City reserves the right, during negotiations or at any time during the contract term, to request that the selected Consultant engage a specialty subconsultant identified in any Respondent’s submittal, or to request substitution of a listed subconsultant.
6.7. City Policies
Sustainability is a core value of the City of Seattle. The plan should advance the City’s climate goals, including the Green New Deal for Seattle and the City’s Sustainable Buildings Policy, and the Strategic Vision goal of a carbon-neutral campus. The master plan will define the path and phasing toward the Action Plan’s goal of a net-zero cultural campus. The plan should also advance the City’s Race and Social Justice Initiative, inclusive design, and universal accessibility. The Seattle Design Commission will review the master plan and make recommendations before City adoption.
6.8. Related Planning Documents
The following documents provide essential context. Items marked with an asterisk will be provided in
Attachment E or on the Procurement Portal.
Available site information includes base maps, topographic survey, utility mapping, and partial as-built drawings. These records are not a complete account of campus conditions.
Document Lead Relevance
Century 21 Master Plan (2008)* Seattle Center Current governing plan for the campus
Seattle Center Strategic Vision and
10-Year Action Plan (2025)*
Seattle Center and Seattle Center
Foundation
Vision, goals, and Big Moves the plan will implement
Seattle Center Economic Impact
Analysis (2026) and 2025
Community Impact Report*
Seattle Center Visitation, economic role, and community programs
6.9. Organizational Conflicts of Interest
The selected Consultant and its subconsultants may compete for other design contracts for bond-funded buildings and public realm improvements, subject to the following safeguards:
A. Bond project briefs, design guidelines, and other Part A work products the City uses to define a solicitation will be made available to all respondents to that solicitation.
B. The Consultant will not advise on, evaluate, or participate in the selection of firms for any solicitation in which it or any of its subconsultants is a respondent.
C. The City retains final authority over design guideline conformance for all bond-funded projects, and makes all decisions on how building and public realm work is packaged.
D. The City may limit the Consultant’s participation in a specific solicitation where it determines that a conflict of interest cannot be mitigated.
7. Contract Modifications
The City consultant contract is attached (See Attachments Section).
Consultants submit proposals understanding all Contract terms and conditions are mandatory. Response submittal is agreement to the Contract without exception. The City reserves the right to negotiate changes to submitted proposals and to change the City's otherwise mandatory Contract form during negotiations. If the
Consultant is awarded a contract and refuses to sign the attached Contract form, the City may reject the
Consultant from this and future solicitations for the same work. Under no circumstances shall Consultant submit its own boilerplate of terms and conditions.
8. Procedures and Requirements
This section details City instructions and requirements for your submittal. The City reserves the right in its sole discretion to reject any Consultant response that fails to comply with the instructions.
8.1. Registration into the City's Procurement Portal
If you have not previously done so, register at: https://procurement.opengov.com/portal/seattle, then subscribe to the City’s Procurement Portal. The Procurement Portal is used by City staff to identify companies for future solicitation lists and check certifications. Women- and minority-owned firms are asked to self-identify their business as such in OpenGov. Registration in the City's Procurement Portal is required to submit a response to this solicitation.
8.2. Pre-Submittal Conference
The City offers an optional pre-submittal conference at the time, date and location on the Timeline. Respondents are highly encouraged to attend but not required to attend to be eligible to submit their qualifications. The meeting answers questions about the solicitation and clarifies issues. This also allows Respondents to raise concerns. Failure to raise concerns over any issues at this opportunity will be a consideration in any protest filed regarding such items known as of this pre-submittal conference.
8.3. Questions
Respondents may submit their questions through the Procurement Portal. Respondents may also email questions to the Procurement Contact until the deadline stated in the Timeline. Failure to request clarification of any inadequacy, omission, or conflict will not relieve the Consultant of responsibilities under any subsequent contract. It is the responsibility of the interested Consultant to assure they receive responses to questions if any are issued.
8.4. Changes to the RFQ
The City may make changes to this RFQ if, in the sole judgment of the City, the change will not compromise the
City’s objectives in this solicitation. Any change to this RFQ will be made by formal addendum issued by the City, through the Procurement Portal at https://procurement.opengov.com/portal/seattle and shall become part of this RFQ.
8.5. Receiving Addenda and/or Question and Answers
It is the obligation and responsibility of the Consultant to learn of addenda, responses, or notices issued by the
City, through the Procurement Portal. Some third-party services independently post City of Seattle solicitations on their websites. The City does not guarantee that such services have accurately provided all the information published by the City.
All submittals sent to the City may be considered compliant with or without specific confirmation from the
Consultant that any and all addenda was received and incorporated into your response. However, the Project
Manager reserves the right to reject any submittal that does not fully incorporate Addenda that is critical to the project.
8.6. Qualifications Submittal
Responses must be received by the City no later than the date and time in the Timeline, except as revised by
Addenda. The submitter has full responsibility to ensure the response is submitted to the City's Procurement
Portal within the deadline. The Procurement Portal will not allow vendors to upload submissions past the deadline.
8.7. Respondent Responsibility to Provide Full Response
It is the Respondent's responsibility to respond in a manner that does not require interpretation or clarification by the City. The Respondent is to provide all requested materials, forms and information. The Respondent is to ensure the materials are submitted properly and accurately reflect the Respondent’s qualifications. During scoring and evaluation (prior to interviews if any), the City will rely upon the submitted materials and shall not accept materials from the Respondent after the RFQ deadline; this does not limit the City’s right to consider additional information (such as references that are not provided by the Respondent but are known to the City, or past City experience with the consultant), or to seek clarifications as needed.
8.8. Prohibited Contacts
Respondents shall not interfere in any way to discourage other potential and/or prospective consultants from submitting or considering participation in the submittal process. Prohibited contacts includes but is not limited to any contact, whether direct or indirect (i.e. in writing, by phone, email or other, and by the Respondent or another person acting on behalf of the Respondent) to a likely firm or individual that may discourage or limit competition. If such activity is evidenced to the satisfaction and in sole discretion of the City department, the
Respondent that initiates such contacts may be rejected from the process.
8.9. License and Business Tax Requirements
The Consultant must meet all applicable licensing requirements immediately after contract award or the City may reject the Consultant. Companies must license, report and pay revenue taxes for the Washington State business License (UBI#) and Seattle Business License, if required by law. Carefully consider those costs before submitting an offer, as the City will not separately pay or reimburse such costs.
Seattle Business Licensing and associated taxes
A. If you have a “physical nexus” in the city, you must obtain a Seattle Business license and pay all taxes due before the Contract can be signed.
B. A “physical nexus” means you have physical presence, such as: a building/facility/employee(s) in
Seattle, you make sales trips into Seattle, your own company drives into Seattle for product deliveries, and/or you conduct service work in Seattle (repair, installation, service, maintenance work, on-site consulting, etc).
C. We provide a Consultant Questionnaire Form in our submittal package items later in this RFP/RFQ, and it will ask you to specify if you have “physical nexus”.
D. All costs for any licenses, permits and Seattle Business License taxes owed shall be borne by the
Consultant and not charged separately to the City.
E. The apparent successful Consultant(s) must immediately obtain the license and ensure all City taxes are current, unless exempted by City Code due to reasons such as no physical nexus. Failure to do so will cause rejection of the submittal.
F. The City of Seattle Application for a Business License and additional licensing information can be found this page here: https://www.seattle.gov/city-finance/business-taxes-and-licenses/business-licenses https://www.seattle.gov/city-finance/business-taxes-and-licenses/business-licenses
G. For Questions and Assistance, call the Revenue and Consumer Protection (RCP) office which issues business licenses and enforces licensing requirements. The general e-mail is tax@seattle.gov. The main phone is 206-684-8484.
H. Self-Filing You can pay your license and taxes on-line https://www.filelocal-wa.gov/Default_FileLocal.aspx
I. If a business has extraordinary balances due on their account that would cause undue hardship to the business, the business can contact the License and Tax Administration office at tax@seattle.gov or 206-
684-8484 to request additional assistance.
J. Those holding a City of Seattle Business license may be required to report and pay revenue taxes to the
City. Such costs should be carefully considered by the Consultant prior to submitting your offer. When allowed by City ordinance, the City will have the right to retain amounts due at the conclusion of a contract by withholding from final invoice payments.
8.10. State Business Licensing
Before the contract is signed, you must have a State of Washington business license (a “Unified Business
Identifier” known as a UBI#). If the State of Washington has exempted your business from State licensing (some foreign companies are exempt and sometimes, the State waives licensing because the company has no physical presence in the State), then submit proof of that exemption to the City. All costs for any licenses, permits and associated tax payments due to the State because of licensing shall be borne by the Consultant and not charged separately to the City. Instructions to apply for a business license can be found at https://dor.wa.gov/open-business/apply-business-license and the State of Washington Department of Revenue contact help page at https://dor.wa.gov/contact.
8.11. Federal Excise Tax
The City is exempt from Federal Excise Tax.
8.12. No Guaranteed Utilization
The City does not guarantee utilization of any contract(s) awarded through this RFQ process. The solicitation may provide estimates of utilization; such information is for Consultant convenience and not a usage guarantee. The City reserves the right to issue multiple or partial awards, and/or to order work based on City needs. The City may turn to other appropriate contract sources or supplemental contracts to obtain these same or similar services. The City may re-solicit for new additions to the Consultant pool. Use of such supplemental contracts does not limit the right of the City to terminate existing contracts for convenience or cause.
8.13. Expansion Clause
The contract limits expansion of scope and new work not expressly provided for within the RFQ.
Expansion for New Work (work not specified within the original Scope of Work Section of this Agreement,…