RFQ Scope- Potable WTP Residuals Monofil Siting Study.pdf

PDF 172 KB Posted

Attached to
Potable Water Treatment Plant Residuals Monofil Siting Study
Solicitation number
CIZ-DWU-27 001E
Issued by
Tarrant County, Texas

About this file

This is a Request for Qualifications (RFQ) issued by the City of Dallas Water Utilities Department for a Potable Water Treatment Plant Residuals Monofil Siting Study (Contract No. 27-001E). The city seeks qualified engineering firms to conduct a comprehensive facility siting study to evaluate potential locations for one or more monofil sites for disposal of drinking water treatment plant residuals from three facilities: Bachman Water Treatment Plant (150 million gallons per day capacity), Elm Fork Water Treatment Plant (310 MGD capacity), and East Side Water Treatment Plant (440 MGD capacity). The combined daily dry solids production estimate across all three plants ranges from 118 tons per day at average flow to 186 tons per day at 95th percentile flow. The consultant shall be prepared to assist with property acquisition, preliminary design, and permitting for one monofil site as determined by the owner based on funding availability and priority. The project is expected to be completed within 24 months of notice to proceed, with deliverables including a detailed siting study report, site analysis, recommendations, and all necessary supporting documentation.

The scope of work encompasses conducting a comprehensive siting study that includes defining purpose and objectives, reviewing available information and operations data, compiling and validating residuals data, establishing site criteria, performing preliminary and detailed site screening, conducting life cycle cost assessments, and providing final site selection recommendations with documented rationale. Following site selection, the consultant shall provide assistance with property acquisition including survey preparation in conformance with City of Dallas Survey Standards, preliminary site assessment, environmental and archeological investigations, and appraisals if requested. The consultant shall also develop preliminary engineering design documents to facilitate permitting, provide geotechnical assessments, identify required utilities and infrastructure, and prepare all necessary federal, state, and local permit applications while coordinating with relevant agencies throughout the review process. The RFQ specifies that a qualified team must demonstrate experience with water treatment plant residuals facilities, solid waste and monofil site selection, permitting, and design. No specific pricing information, set-asides, incumbent contractor information, or funding source details are provided in this qualifications-based procurement document.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF DALLAS

WATER UTILITIES DEPARTMENT

POTABLE WATER TREATMENT PLANT RESIDUALS MONOFIL SITING STUDY

REQUEST FOR QUALIFICATIONS

CONTRACT NO. 27-001E

Dallas Water Utilities invites qualified engineering firms to submit Statements of Qualifications (SOQs) for conducting a Facility Siting Study. The purpose of the study is to evaluate potential locations for one or more monofil sites for disposal of drinking Water Treatment Plant (WTP) residuals. The consultant shall have the ability to further assist with property acquisition, preliminary design, and permitting assistance for one monofil site as determined by owner based on funding availability and priority. A qualified team is expected to have experience with water treatment plant residuals facilities including relevant solid waste and monofil site selection, permitting and design.

CONTENTS

• Overview and Background

• Preliminary Scope of Work and Project Requirements o Specific Requirements – Basic and Special Services o General Requirements – Administrative Guidelines for the Project o Deliverables and Schedule

• Requirements for Organization of the Statement of Qualifications (attached document)

• Consultant Selection Guidelines and Requirements (attached document)

OVERVIEW AND BACKGROUND

The City of Dallas Water Utilities (DWU) provides water, wastewater, storm water and flood control services to over 2.6 million people in the City of Dallas and 27 neighboring communities.

Its operations are funded through water, wastewater, and storm water rates paid by customers as part of DWU′s service delivery. DWU has water rights to seven (7) reservoirs and operates large raw water conveyance infrastructure and three (3) potable WTPs: Bachman, Elm Fork, and East Side. The combined treatment capacity rating of the facilities is nearly 900 million gallons per day (MGD).

The Bachman Water Treatment Plant was constructed in the late 1920s and underwent expansions in 1936, 1948, and 2006. The most recent expansion brought the plant to its current capacity of 150 MGD. The plant was converted from Partial Softening to Enhanced Coagulation (EC) and Biologically Active Filtration (BAF) in April 2017. The Bachman Water Treatment Plant is Dallas' only water treatment plant located within the Dallas city limits and can serve areas to the north, south, and east of the site. Bachman has two offsite residual lagoons that have been periodically cleaned by contract dewatering and hauling services.

The Elm Fork Water Treatment Plant is located in Carrollton, Texas and is DWU’s second largest plant. Originally constructed in the 1950s, the plant underwent an expansion and renovation to its current capacity of 310 MGD in the early 1990s. The plant recently implemented a variety of water quality improvements including the recently completed construction of an off-site residuals complex and a residuals-thickening facility to address EC residuals and facilitate separated waste-streams.

The East Side Water Treatment Plant, located in Sunnyvale, Texas is DWU’s largest plant.

Originally constructed in the 1960s, the plant was expanded to a 440 MGD capacity over the course of three construction stages. In 2010, the plant began designing water quality improvement projects including filter-to-waste, basin improvements, a non-chlorinated backwash pump station and separate waste-stream improvements. The plant converted to EC in 2011 and converted to BAF in 2019. The plant has five on-site lagoons, two peaking lagoons located near Berry Road, and three older off-site lagoons.

Historically, residuals dewatering, hauling, and disposal services at Bachman, Elm Fork, and East Side WTPs were managed through capital projects. In recent years, DWU has transitioned these activities to plant operations because they are recurring operating expenses rather than capital assets. Operations now manage these contracts directly through the operating fund, allowing for recovery of operating costs associated with residuals handling.

PRELIMINARY SCOPE OF WORK AND PROJECT REQUIREMENTS

DWU recently completed a comprehensive Water Production Facilities Strategic Plan (WPFSP) project which evaluated the performance limiting factors (PLFs) related to condition and reliability. The WPFSP identified the availability and cost of final disposal options for the residuals streams at all three plants was an important PLF to address. The recommendation is to plan for the development of one or more monofil sites to address the long-term cost, reliability and capacity for managing residuals disposal. The solids production estimate (2024) for all three plants as per the WPFSP is provided in Table 1. This project is for the identification, evaluation and recommendations for purchase of candidate property(ies) to serve all three plants. The project may also include future property acquisition, design and permitting determined by owner based on funding availability and priority.

Table 1: Solids production estimate

Facility

Raw Water Flow (MGD) – Average

Raw Water Flow (MGD) – 95th Percentile

Dry Solids Production Estimate

(tons/day) – Average

Dry Solids Production Estimate

(tons/day) – 95th Percentile

Eastside WTP 171.9 259.7 45 68 Elm Fork WTP 153.6 224.3 49 82 Bachman WTP 87.2 118.9 24 36

Conduct a siting study to identify a monofil site(s) to serve all three WTPs. Multiple sites may be a part of the recommended solution for economic reasons or if a single site does not meet the capacity needs or have transport limitations. Assist in acquiring the property by providing survey support, appraisal and other due diligence. Following acquisition, the consultant shall develop preliminary design documents of sufficient detail to facilitate permitting, and the consultant shall assist the owner in obtaining necessary permits.

Specific Requirements

I. Siting Study

A. Define the Purpose and Objectives

a. Clarify the need for the property(ies).

b. Define goals such as improving reliability, minimizing cost, maximizing flexibility and accessibility, environmental compliance, etc.

c. Identify key criteria and constraints for site selection.

B. Review of Available Information

a. Pertinent Reports and Recent Projects

i. Water Production Facilities Strategic Plan

ii. Water Quality Study (Malcolm-Pirnie, 2010)

iii. Water Quality Projects at each plant

iv. Long Range Water Supply Plan

b. Operations Data

c. History of DWU Residuals Management

d. Staff Input

C. Compile and Validate Residuals Data

a. Recent disposal projects

b. Solids in existing lagoons

i. Estimate of solids currently stored in existing lagoons

ii. Current residuals chemical and physical characteristics

iii. Percent solids and expected dewatered solids concentrations.

iv. Convert projected solids production into annual disposal volume

c. Expected future residuals

i. Evaluate constituents that may affect permitting or long-term management. (PFAS, etc)

ii. Estimate solids production volumes from all DWU Potable Water

Treatment Plants based on demand projections from strategic plans.

D. Establish Site Criteria

E. Preliminary Screening of Sites

a. Conduct an initial review to eliminate sites that do not meet critical criteria (e.g., zoning restrictions, protected areas).

b. Narrow down to a manageable list of candidate sites.

F. Detailed Site Analysis

Develop detailed criteria with DWU.

G. Site Comparison and Ranking

a. Use quantitative and qualitative methods (scoring, weighted factors, multi-criteria decision analysis) to rank the candidate sites.

b. Identify trade-offs and sensitivities in criteria weighting.

H. Life Cycle Cost Assessment and comparison

a. For each Monofil site including Site Purchase, Maintenance, O&M, etc.

b. Residuals Management for each plant without monofil

I. Field Visits and Stakeholder Consultations

a. Conduct site visits to verify data and assess real-world conditions.

b. Engage with stakeholders (local communities, government authorities, environmental groups) to gather input.

J. Final Site Selection

a. Integrate all data, analyses, and feedback.

b. Choose the site that best meets the overall objectives.

c. Document the rationale behind the selection.

K. Reporting and Recommendations

a. Prepare a detailed report summarizing the study process, data, analyses, final recommendations and cost.

II. Assistance with Property Acquisition

A. Prepare metes and bounds survey in conformance with City of Dallas Survey Standards of the property intended to be acquired.

B. Conduct preliminary site assessment and due diligence, including necessary environmental and archeological investigations.

C. Conduct appraisal(s) of the intended property to be acquired, if requested by owner.

III. Design Services

A. Develop engineering concepts and design documents to a sufficient level to facilitate permitting.

B. Provide geotechnical assessments and stability evaluations C. Identify required utilities and infrastructure improvements

IV. Permitting Support

A. Prepare all required federal, state, and local permit applications.

B. Conduct environmental impact analysis as required.

C. Coordinate with relevant agencies throughout review processes.

D. Support public meetings and stakeholder engagement

Deliverables and Schedule

This project is expected to be completed within 24 months of notice to proceed. The deliverables are as needed to deliver the project as described in the description of basic services in addition to the final report of the project.