RFQ_Metering of Gravity Sewer.pdf
PDF 185 KB Posted
- Attached to
- RFQ - Metering of Gravity Sewer
- Solicitation number
- 345-06/23/2026-2
- Issued by
- Camden County, North Carolina
About this file
This Request for Qualifications is issued by the Cape Fear Public Utility Authority (CFPUA) in Wilmington, North Carolina, seeking qualified consulting engineering firms to provide design and permitting services for metering instrumentation installation in existing gravity sewer systems. The scope of work includes surveying, preliminary field investigations, preparation of a Basis of Design Report, detailed design and specifications, permit acquisition and encroachment agreements, sewer bypass plans for three separate gravity mains at the University of North Carolina Wilmington campus, and bidding assistance with certified bid tabulation and award recommendations. Construction administration services will be determined at a later date and are not included in this phase. Statements of Qualifications must be submitted in PDF format to bids@cfpua.org no later than 2:00 PM on July 21, 2026, with a maximum file size of 25MB. The CFPUA selection team will place emphasis on the firm's ability to meet the aggressive project schedule, with key milestones including firm selection by August 6, 2026, Basis of Design completion by October 29, 2026, 60% design documents by December 10, 2026, 90% design documents by December 29, 2026, and final contract documents with permits by January 15, 2026.
Evaluation of submissions will follow a qualifications-based selection process with four equally weighted criteria (25% each): project understanding and approach, relevant firm experience on similar-sized projects, overall staff experience with identified project managers and discipline specialists, and demonstrated record of success in managing design costs relative to construction bids. Selected firms must maintain Professional Liability insurance of not less than $2,000,000 per loss, General Liability coverage of $1,000,000 per occurrence/$2,000,000 aggregate, Workers Compensation of $500,000/$500,000/$500,000, and Auto Liability Insurance of $1,000,000 per occurrence, with the Authority named as additional insured. One firm will be selected, and detailed scope of work and fee schedules will be negotiated with the best-qualified firm. All SOQs are limited to 25 pages or less, excluding cover pages, tables of contents, tabs, resumes, and appendices. Questions regarding the RFQ must be submitted by 2:00 PM on July 9, 2026, to Ben Guerrieri, Procurement Manager, at bids@cfpua.org.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1_Metering of Gravity Sewer.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Qualifications Professional Engineering Consulting Services
Metering of Gravity Sewer
Cape Fear Public Utility Authority
Wilmington, North Carolina June 23, 2026
General Information
Cape Fear Public Utility Authority (CFPUA) requests Statements of Qualifications (SOQ) from consulting engineering firms for the design and permitting of metering instrumentation installed in existing gravity sewer located in the CFPUA system.
The project will generally consist of surveying, preparing detailed design plans and technical specifications, permitting, and bidding assistance. The outcome of this project will be final contract documents that are suitable for bidding and construction.
Construction based services by the Engineer not included at this time.
Submission of a Statement of Qualification (SOQ)
Consulting engineering firms are invited to submit a Statement of Qualification to the CFPUA to be received no later than 2:00 PM on July 21, 2026. Submittals received after this deadline will not be considered.
CFPUA will address questions regarding the RFQ until 2:00 PM on July 9, 2026.
Questions submitted after this time will not addressed. Questions concerning this advertisement should be directed to Ben Guerrieri, Procurement Manager, Cape Fear Public Utility Authority, at bids@cfpua.org.
SOQ’s shall be limited to 25-pages or less, excluding cover page, table of contents, tabs, resumes and appendices.
Firms shall submit their statement of qualifications for consideration in .pdf format to bids@cfpua.org. Maximum file size for .pdf submission is 25MB. A reply will be sent to the email address submitting the statement of qualifications to confirm receipt. It is the submitting firms’ responsibility to confirm that CFPUA has received statement of qualifications via email. If email reply is not received from bids@cfpua.org, please call 910-332-6472 or 910-332-6651 before deadline for submission.
Submitted information shall comply with N.C.G.S. 143-64.31 through 64.34 (aka Mini Brooks Act).
All SOQ’s will be evaluated by a CFPUA selection team.
One firm will be selected from this request for qualifications.
mailto:bids@cfpua.org
Background
CFPUA is pursuing professional engineering consultant services to assist in the design and bidding for the installation of monitoring devices for metering gravity sewers to provide billing services. CFPUA has identified the UNCW campus for this project. The area has 3 separate gravity mains leaving the campus that require metering.
Description of Services
The scope of work is expected to include the services described below.
Overall objectives of this project are outlined below:
1. Gather and evaluate available information provided by CFPUA and perform preliminary field investigations as needed for cost estimation
2. Prepare a Basis of Design Report
3. Prepare detailed design and specifications for bidding
4. Obtain all necessary permits and encroachment agreements
5. Prepare sewer bypass plans for each location
6. Provide bidding assistance, certified bid tabulation and letter of recommendation to award
7. Construction administration and observation-based services to be determined at a later date.
Schedule
The CFPUA selection team will place strong emphasis on a firm’s ability to meet the schedule of deliverables outlined below. The selected consultant will be expected to complete final plans and specification in accordance with the project schedule shown below, or sooner. CFPUA will provide comments on all design submittals generally within 2 weeks from the date received.
o CFPUA Selects Firm(s) August 6, 2026 o Complete Scope and Contract September 3, 2026 o Basis of Design October 29, 2026 o 60% design documents December 10, 2026 o 90% design documents December 29, 2026 o Final contract documents and permits January 15, 2026
Consultant Selection
CFPUA will follow a qualifications-based selection process. Consultants must demonstrate their level of competence and qualification, and each sub-consultant's level of competence and qualification, with respect to the listed evaluation factors for the needed services.
SOQ’s will be evaluated based on the following four (4) considerations and the level of importance for each consideration. The SOQ shall be formatted consistent with the evaluation consideration. Criteria shown under each of the four (4) considerations are to be addressed in the SOQ. Consultant’s may provide additional information, as necessary.
1. Project understanding and approach (25%)
a. Understanding of project drivers and scope of work to be performed
b. Approach to keep the project on schedule
c. Description of the design team’s quality control program
2. Relevant firm experience (25%)
a. Projects of similar size and scope
b. References and descriptions of similar projects
3. Overall staff experience proposed for this project (25%)
a. Project Manager to lead the design aspect of the project
b. Individual team members for each discipline and relevant experience
4. Record of success by the consultant (25%)
a. Managing design and construction costs within project budgets and design estimates. Provide 5 previous projects indicating the engineer’s opinion of probably cost estimate compared to construction low bid.
A more detailed scope of work and fee schedule will be negotiated with the best qualified firm. If negotiations are not successful with any selected firm, CFPUA will terminate negotiations with that firm and initiate negotiations with the next best qualified firm.
When a fair and reasonable fee is established, a contract award recommendation will be made to the CFPUA Board for its consideration.
Insurance Requirements
The following criteria will be deemed necessary for selection:
• The firm must meet the following insurance requirements. Workers Compensation may be waived if firm has no employees.
• General Liability $1,000,000 per occurrence/$2,000,000 aggregate. Authority must be additional insured and endorsement required.
• Workers Compensation $500,000/$500,000/$500,000. Waiver of Subrogation against the Authority and endorsement required.
• Auto Liability Insurance $1,000,000 per occurrence combined single limits applicable to claims due to bodily injury and/or property damage. Authority must be additional insured and endorsement required.
• Professional Liability not less than $2,000,000 per loss.
Any firm wishing to be considered must be properly registered with the Office of the Secretary of State.
Notification
The selected firms will be notified by telephone and/or email.
The CFPUA reserves the right to reject any and all Proposals.
CFPUA will address questions regarding the RFQ until 2:00PM on July 9, 2026. Questions submitted after this time will not addressed. Any questions concerning this advertisement should be directed to Ben Guerrieri, Procurement Manager, Cape Fear Public Utility Authority, at bids@cfpua.org by July 9, 2026, at 2:00PM.
File details come from the government source that posted it. Updated .