RFQ # AE27-003 Assessment, Design & Adminstration for HVAC Replacement - Addendum 1.pdf
PDF 231 KB Posted
- Solicitation number
- 323-A/E27-003
- Issued by
- Hertford County, Charlotte City, North Carolina
About this file
This addendum to Request for Qualifications (RFQ) AE27-003 issued by the Town of Chapel Hill, North Carolina on November 6, 2026 provides clarifications and responses to questions submitted by prospective engineering firms regarding assessment, design, and administration services for HVAC system replacement across the Public Works and Transit Campuses. The scope encompasses seven buildings across two campuses: five Public Works buildings located at 6850, 6830, 6840, 6842, and 6838 Millhouse Road (Administration, Operations, Fleet, Surplus Storage, and Wash Bay facilities), and two Transit buildings at 6900 and 6924 Millhouse Road (Operations/Fleet and Gas Island facilities). The Town clarified that Public Works and Transit will be bid as separate projects with potentially different timeframes while buildings remain occupied, and that the estimated construction budgets are design deliverables to be determined during the project. The RFQ response limit is eight single-sided pages including all forms and resumes, with proposals due November 19, 2026 and anticipated selection and notification scheduled for December 15, 2026. The contract term commences January 1, 2027 and runs for three years.
The Town indicated that no predetermined construction budgets exist for either campus or the Alternate #1 option for cooling system additions to Fleet Repair Facilities. Limited digital records are available from Public Works, though mechanics possess institutional maintenance knowledge; two mini-split units have been replaced since 2008. The current Building Automation System (BAS) uses Champion Systems with Delta Control enteliWEB platform, with physical hardware components to be replaced as part of this project. The Town is flexible on commissioning approach, accepting either design team or third-party commissioning authority services. This qualifications-based selection under North Carolina General Statute 143-64.31 will negotiate fees following evaluation rather than compete on price. The Town encourages participation from small, minority, and women-owned businesses but does not establish a set-aside or participation goal.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ # AE27-003 Assessment, Design & Administration for HVAC Replacement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Assessment, Design, and Administration Services for HVAC System Replacement for Public Works and Transit Campuses RFQ: AE27-003, Town of Chapel Hill, NC 1 November 6, 2026
ADDENDUM 1
FOR
ASSESSMENT, DESIGN, AND ADMINISTRATION SERVICES FOR HVAC SYSTEM REPLACEMENT FOR
PUBLIC WORKS AND TRANSIT CAMPUSES
TOWN OF CHAPEL HILL, NORTH CAROLINA
RFQ: A/E27-003
TO: All Prospective Companies
FROM: Lenore Bishop, Purchasing & Contracts Manager
SUBJECT: Addendum # 1
DATE: November 6, 2026
This Addendum is being issued to provide additional information and answer the questions received from prospective Companies regarding the above-referenced Request for Qualifications. All other terms and conditions remain unchanged.
Question:
Listed below are the questions received and our responses:
1. What are the five Public Works buildings with addresses and the Transit buildings in scope? Are the Fuel and Wash buildings included?
A. The buildings listed below are the sites in scope.
1. Public Works Sites.
Building Address Administration - Building #1 6850 Millhouse Road Operation Building - Building #2 6830 Millhouse Road Fleet - Building #3 6840 Millhouse Road Surplus Storage Building 6842 Millhouse Road Wash Bay 6838 Millhouse Road
Assessment, Design, and Administration Services for HVAC System Replacement for Public Works and Transit Campuses RFQ: AE27-003, Town of Chapel Hill, NC 2 November 6, 2026
2. Transit Sites.
Building Address
Operations and Fleet Building 6900 Millhouse Road Gas Island 6924 Millhouse Road
2. Has equipment been replaced or added since 2008? Are O&M, service, and energy records available?
A. Public works has had two Mini splits replaced. There are limited digital records. Mechanics with institutional repair and maintenance knowledge are available.
3. Who is the Town's current controls vendor and platform? Is the BAS staying or being replaced?
A. The current vendor is Champion Systems. The platform is Delta Control – enteliWEB. The
BAS physical hardware components will be replaced as part of this project.
4. Is there a construction budget for each campus and for Alternate #1?
A. No for either one, on either campus. The estimated construction budgets are one of the Design Deliverables.
5. Will Public Works and Transit be bid as separate packages, or in phases while buildings remain occupied?
A. Public Works and Transit will be bid as separate projects with likely separate timeframes while the buildings are occupied.
6. Is commissioning to be done by the design team (as written) or by a third-party CxA?
A. The Town is open to either approach with the goal to be the verification of the new systems working as designed and properly conditioning and dehumidifying the spaces.
7. Does the 8-page limit include the forms and resumes?
A. Yes, the Town would like firms submitting RFQ’s for this project to be precise, on-point and economical with their information presentations.
8. Are the 8 pages for the RFQ response allowed to be double-sided?
A. No, they are to be single sided.
File details come from the government source that posted it. Updated .