- PRECAST CONCRETE TRAFFIC CONTROL BARRIERS
- Solicitation number
- 925
- Issued by
- Adams County, Idaho
About this file
This file is a Request for Quotation (RFQ) 925 issued by the Idaho Transportation Department for the procurement of precast concrete traffic control barriers. The RFQ solicits quotations from vendors for new precast concrete traffic control barriers that meet specified design and structural requirements for use in Idaho's transportation infrastructure. Vendors may submit quotations electronically through IPRO Powered by LUMA or via email to the solicitation contact, Denise Cooley, at denise.cooley@ITD.IDAHO.GOV. Required submittals include a completed Price Sheet (Attachment 2) and Signature Page (Attachment 3). Delivery of all barriers is required no later than July 1, 2025, FOB Destination with freight prepaid and allowed, to ITD District 5 located at 5151 South 5th Avenue, Pocatello, ID 83204. Delivery must occur Monday through Friday between 8:00 a.m. and 4:00 p.m. local time, excluding Idaho state-recognized holidays. Award will be made to the responsive and responsible vendor with the lowest total cost for all groups, and ITD reserves the right to make multiple awards per manufacturer if determined to be in the state's best interest.
The file does not explicitly identify specific pricing terms, quantities, or budget amounts within this attachment. No set-asides for small businesses, women-owned businesses, or other special categories are indicated. Vendors must establish an account in the IPRO system, provide proof of insurance as specified in a separate RFQ 863 attachment, and warrant that all barriers will be free from substantial defects in materials, manufacturing, and design when used in accordance with design limits and structural and environmental specifications. Invoicing is permitted within thirty calendar days of written acceptance by ITD's Contract Monitor, who will document acceptance using the Deliverable Acceptance Form (Exhibit 1) or non-compliance using the Contract Discrepancy Notice (Exhibit 2). Contractors have thirty calendar days to correct any identified discrepancies. Communication regarding the RFQ is restricted to the designated RFQ Lead; unauthorized communications with other ITD staff may result in the vendor being found non-responsible and non-responsive.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Instructions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IDAHO TRANSPORTATION DEPARTMENT
RFQ 925
PRECAST CONCRETE TRAFFIC CONTROL BARRIERS
GENERAL INFORMATION
1. Purpose The Idaho Transportation Department (ITD) is requesting Quotations from Vendors for precast concrete traffic control barriers (Barriers), as further detailed below.
2. Solicitation Contact The contact for this RFQ is:
Name: Denise Cooley, PPS-CPPB Email: denise.cooley@ITD.IDAHO.GOV (preferred method of contact)
3. Restrictions on Communications From the issue date of this RFQ, until a contract/purchase order is awarded or the RFQ is cancelled, vendors and their representatives are prohibited from communications (written or verbal) regarding this RFQ with the ITD staff, other than the ITD RFQ Lead. Any communications (written or verbal) with ITD staff other than the RFQ Lead may result in the submitting vendor being found Non-Responsible and Non-Responsive.
4. Requirements and Specifications See Section 1 (below)– Requirements & Specifications See Attachment 2 – Price Sheet See Attachment 3 – Signature Page
5. Quote
5.1. Your Quote may be submitted electronically via IPRO Powered by LUMA or email (see below for additional details). ITD will not be accepting manual submissions for this solicitation. Your Quote must include the Required Submittals listed below and be received prior to the deadline established in IPRO Powered by LUMA.
Electronic Submission: IPRO – Enter your pricing in IPRO (https://purchasing.idaho.gov/information-for-vendors/) and upload all Required Submittals.
5.2. Email:
Send an email to the Solicitation Contact (see Section 2-above) and attach all Required Submittals.
6. Required Submittals:
Attachment 2 – Price Sheet;
Attachment 3 – Signature Page;
7. Award
| 7.1 | Award will be made to the responsive responsible vendor(s) with the lowest total cost for all Groups. |
| 7.2 | The State reserves the right not to evaluate or make an award in the best interest of the State. The State also reserves the right to make multiple awards per manufacturer, in accordance with Section 67-9211 of Idaho Code in the best interest of the State. |
Though it is not mandatory to submit your Quotation electronically via IPRO, all vendors participating in a solicitation issued through IPRO must establish an account in the IPRO system (even if submitting a quote outside of IPRO). It is free to establish an account and only takes a few minutes of your time.
ATTACHMENT 1 – REQUIREMENTS AND SPECIFICATIONS
Section 1 - Requirements
1. Warranty
1.1 Vendor must warrant, to the original purchaser only, that Barriers will be free from substantial defects in materials, manufacturing, and design, and when used in accordance with the design limits and the structural, technical, and environmental specifications.
2. Acceptance
2.1. Documenting Acceptance - ITD’s Contract Monitor will be responsible for documenting Acceptance, in writing, using Exhibit 1 - Deliverable Acceptance Form. This document will be emailed to the Contractor’s Contract Manager as proof of Acceptance and approval to proceed with the invoicing procedures as required in Section 6, Invoicing.
2.2. Documenting Non-Compliance - ITD’s Contract Monitor will be responsible for documenting non-compliance, in writing, using Exhibit 2 - Contract Discrepancy Notice. This document will be emailed to the Contractor’s Contract Manager, providing details for each discrepancy that require corrective action. Invoicing shall not occur until non-compliance has been corrected.
2.3. Correcting Non-Compliance - After receipt of the Contract Discrepancy Notice, the Contractor’s Contract Manager must respond, using the document, explaining how and when each discrepancy will be corrected. All discrepancies must be corrected and brought back into compliance with the Contract within thirty (30) calendar days after receipt of the notice from ITD. If the Contractor does not correct the discrepancies within this timeframe, ITD reserves the right to take further Cure actions.
2.4. In addition to any remedies available to the State under law or equity, the State may at its sole discretion require one (1) or more of the following Cure actions if any of the service does not conform to the Contract requirements: 1) require the Contractor to take corrective action to ensure that performance conforms to the Contract requirements, 2) require the Contractor to subcontract all or part of the Contract at no additional cost to the State, 3) withhold payment or require payment of actual damages caused by the Discrepancy, 4) terminate the Contract pursuant to Section 3, Termination and Cure, in addition to any remedies imposed by the State.
2.5. If ITD must perform or hire a separate contractor to perform any of the Contract’s requirements, which is the responsibility of the Contractor under the terms of the Contract, ITD may withhold the actual cost to ITD from the Contractor’s payment(s).
3. Termination and Cure
3.1. See State of Idaho Contract Terms and Conditions in the Terms Tab in IPRO Powered by Luma.
4. Delivery
4.1. Delivery is required no later than July 1, 2025, FOB Destination, freight prepaid and allowed. ITD reserves the right to accept delivery dates outside of the desired delivery date if in the best interest of the State of Idaho. The Contractor must deliver the Barriers to the location listed below by the delivery date or the date provided on Attachment 2 – Price Sheet if determined to be in the best interest of the State of Idaho. ITD will be responsible for the unloading of the Barriers.
4.2. Delivery must be made Monday through Friday, 8:00 am to 4:00 pm local time excluding state of Idaho recognized holidays (https://www.idaho.gov/government/holidays.html), unless otherwise approved in writing by ITD.
4.3. Delivery Location:
ITD District 5 5151 south 5th Ave Pocatello, ID 83204
5. Insurance
5.1. See Insurance Requirements on the Attachment tab of RFQ863 IPRO powered by LUMA.
6. Invoicing
6.1. The Contractor must submit its invoice within thirty (30) calendar days of acceptance to the billing contact identified (below) on the Contract. Invoices submitted prior to acceptance, or without the required information listed below, will be returned to the Contractor for correction and resubmission. The following information must be included with each invoice:
6.2. Purchase Order Number;
6.3. Invoice Number and Date;
6.4. Contractor Contact Information and;
6.5. Itemization of Property delivered and accepted – description, quantity, unit of measure, unit price, and total invoice amount.
6.6. Invoices must be submitted electronically to:
D5AP@ITD.IDAHO.GOV
PRECAST CONCRETE TRAFFIC CONTROL BARRIERS
Section 2 – Specifications
The Barriers must meet the minimum specifications provided in the drawings and must be new, not used.
https://itd.idaho.gov/business/?target=construction-resources#standard-specifications-for-highway-construction
EXHBIT 1 – DELIVERABLE ACCEPTANCE FORM
| Contract No: |
| TBD |
Contract Name:
Deliverable Information: The Deliverable Acceptance form signifies sign-off of the specified deliverable(s) below. This will verify what has been delivered to ITD, per the Contract, and that ITD has accepted and approved the deliverable(s).
Deliverable Description
Contract Reference
Acceptance Criteria
Item #1
Item #2
Attachments:
· Bill of Lading/Ship Tickets
Deliverable Acceptance:
ITD Printed Name:
Title:
ITD Signature:
Date:
ITD Comments
EXHIBIT 2 – CONTRACT DISCREPANCY NOTICE
| Contract No: |
| TBD |
| Contract Name: |
| PRECAST CONCRETE TRAFFIC CONTROL BARRIERS |
Discrepancy Information: This Contract Discrepancy Notice identifies the Discrepancy(ies) found by ITD while monitoring the Contractor’s performance required per the referenced contract. Items identified as “Discrepancy” require a response from the Contractor. Items identified as “Observation” are areas of concern that may lead to a future Discrepancy if not addressed. Observations do not require a response unless otherwise noted in this notice.
ITD has identified the following Discrepancy(ies):
(Add additional tables for multiple discrepancies)
| Description of Discrepancy: |
| Describe the discrepancy in detail and explain how the contractor is out of compliance. Attach photos or other supporting documents and reference here. |
| Contract Reference: |
| Site the document name, attachment #, and section # of the requirement out of compliance. |
| Required Action: |
| Site the required corrective action from the contract. |
| Contractor’s Resolution: |
| Contractor to describe action that will be taken to correct the discrepancy in order to become compliant with the contract. |
| Estimated Resolution Date: |
| Contractor to provide estimated date it anticipates resolving the discrepancy by. |
ITD Contract Monitor - Check appropriate box with regard to Contractor’s resolution
| Accept ☐ |
| Partially Accept ☐ |
| Reject ☐ |
Reason for Rejection or Partially Accepted
Anticipated Follow Up Date on Resolution
ITD Contract Monitor Signature
Date
Contractor - Sign below to indicate your understanding of the Discrepancy(ies) and your responsibility for resolution.
Contractor Printed Name
Title
Contractor Signature
Date
Resolution
ITD Contract Monitor – Sign below to indicate that each Discrepancy has been resolved based on the actions detailed in the Contractor’s Resolution for each Discrepancy.
ITD Contract Monitor Signature
Date
ITD has identified the following Observations (no response required):
| Description of Observation: |
| Describe the observation in detail and explain how it may lead to a non-compliance issue in the future. Attach photos or other supporting documents and reference here. |
| Contractor’s Response (optional): |
| Contractor to describe action that will be taken to correct the discrepancy in order to become compliant with the contract. |
2 | Page dcc