RFQ_26-02_Addendum_1.pdf

PDF 207 KB Posted

Attached to
Architectural & Engineering Design Services New Health & Human Performance Center
Solicitation number
26-02
Issued by
Jackson County, Florida

About this file

This is an addendum to a Request for Qualifications issued by the District Board of Trustees of Lake-Sumter State College in Florida for Architectural & Engineering Design Services. The addendum modifies the original RFQ_26-02 for the planning, design, and construction phases of a new Health and Human Performance Center to be located on the College's South Lake Campus. The College intends to award one agreement to a single qualified vendor capable of providing comprehensive architectural and engineering design services. Key procedural details regarding submission deadlines, site visit requirements, bidders' meetings, or other timeline-specific information should be referenced in conjunction with the original RFQ document, as addenda typically clarify or modify specific provisions from the base solicitation.

The addendum addresses modifications to the original solicitation terms, which may include adjustments to pricing structures, qualification requirements, evaluation criteria, or contract conditions. Specific details regarding pricing terms, any small business or minority-owned business set-asides, funding sources, project budget, and other financial parameters would be contained within this addendum and should be reviewed in conjunction with the original RFQ to understand the complete procurement requirements and any changes to the College's expectations for the architectural and engineering design services engagement.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM TO SOLICITATION/OFFER AND AWARD

PAGE 1 of 4 PAGE(S)

1. ADDENDUM

NO. 1

2. EFFECTIVE DATE

10/29/2025

3. SOLICITATION NUMBER

RFQ 26-02

4. SOLICITATION DESCRIPTION

A-E Services Health & Human Performance Center

5. ISSUED BY:

LAKE-SUMTER STATE COLLEGE

MICHELLE D. MATIS, VP OF FINANCE

9501 U.S. HWY 441

WILLIAMS-JOHNSON BLDG./ROOM 101

LEESBURG, FLORIDA 34788-3950

7. TYPE OF ACTION REQUESTED

Check one:

A. THE CHANGE ORDER IS ISSUED TO INCREASE/DECREASE FUNDING AMOUNT AS SET FORTH IN ITEM 8 BELOW:

B. THE ABOVE NUMBERED SOLICITATION IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 8 BELOW:

C. OTHER (Set forth in Item 8 below)

IMPORTANT: CONTRACTOR IS NOT REQUIRED TO SIGN THIS DOCUMENT AND RETURN 1 ORIGINAL SIGNED COPY (IES) TO THE ISSUING OFFICE.

IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 1 ORIGINAL SIGNED COPY (IES) TO THE ISSUING OFFICE.

8. DESCRIPTION OF ADDENDUM:

Question and Answer Addendum

9. AUTHORIZED SIGNATURES REQUIRED

Michelle D. Matis Vice President of Finance Name(Print) Title

10/29/2025 Signature Date Signed

Addendum to RFQ 26-02 – Submitted Questions and Answers to those Questions

1. Are the front and back covers, as well as the tabs, included in the 50-page count, or are they excluded?

Answer: The front and back covers as well as the tabs are excluded from the page count.

2. Does the 50-page count refer to single-sided pages, or does a double-sided page count as one?

Answer: A single-sided pages counts as 1-page.

3. Should the submitting Architect include suggested subcontractors (e.g., MEP, Structural, Civil, etc.)?

Answer: Yes, please.

4. If known, what is the anticipated schedule for bidding and construction of this project?

Answer: See below for tentative schedule. Subject to change

January 2026 Board of Trustees approve A&E firm at the Jan. 21, 2026 meeting February 2026 Visioning and Programming and RFQ for CMAR March 2026 Schematic Design and DBOT Approval of CMAR April 2026 Design Development May-June 2026 Construction Documents July 2026 Bidding and Permitting August 2026– July 2027 Construction July 2027 Substantial Completion Early August 2027 Punch List August 2027 Owner Move In – Furniture Late August Fall 2027 Classes Begin

5. The RFQ packet states “Due Date: 11/18/2025 2:00 PM Eastern”, however, Demandstar website shows Due Date as “Nov 18, 2025 4:00pm (EST)”. Please confirm this.

Answer: The due date is 11/18/25 at 2 pm Eastern as outlined in the packet.

Demandstar is incorrect and we are working to get it updated.

6. When do you anticipate construction will start and end?

Answer: See #4.

7. We would like to know if it would be possible to visit the campus to view the current health training facilities before we submit our proposal.

Answer: A site walkthrough is not scheduled prior to the submission of qualifications.

8. We wanted to confirm that we should include a full consultant team in our Stage 1 response Answer: Yes, please.

9. Please confirm that all pages, including required forms, count toward the 50-page limit. (With exception of Financial Statements under separate cover.)

Answer: Required forms, except Financial Statements provided under separate cover, count toward the 50-page limit.

10. There is a request for a certificate of insurance and W-9, please confirm this is for the AOR only, and that it is to be included in our 50 pages?

Answer: The certificate of insurance and W-9 should be included and count toward the 50-page limit.

11. One attachment F, the client reference forms, who is to complete the lower portion of the form (Narrative Description, Respective Dates, Relevant Data, and Project Similarities) the submitting firm, or do we leave blank for the client? | Is this form to be completed by the client prior to being included in our package? Or will LSSC send the forms to the named client requesting the reference?

Answer: You may have the client complete it or you may complete it for them. It should be included in the submission. LSSC does not send the forms out.

12. Can you please confirm that this will be a 35,000 SF NEW building (vs. renovation)?

Answer: Yes, this building is new construction.

13. Is there a building site identified on the South Lake Campus?

Answer: A general area on the South Lake Campus, but not an exact location.

14. Has any program been developed, if so, can you please share it?

Answer: The Health and Human Performance Center will house the Nursing department including at least four lecture rooms, skills labs, debriefing room, and simulation lab. The building will also be home to the Physical Therapist Assistant program with a lecture room and large lab spaces as well as Medical Assisting classrooms. There will be student collaboration spaces, faculty offices, Health Programs Administrative spaces, a conference room, an approximately 300 seat-auditorium, etc. Exact square footages for the building program have not been determined.

15. Do you have a schedule in place, can you offer us anticipated milestones and/or you desired occupancy date?

Answer: See #4.

16. Can you share who is on the selection committee?

Answer: The internal selection committee will be comprised of LSSC leadership, including Facilities Planning representation.

17. Will a site walkthrough be provided prior to submission of quals?

Answer: A site walkthrough is not scheduled prior to the submission of qualifications.

18. Does LSSC have a typical Owner/Architect agreement that they can provide for review?

Answer: LSSC typically uses a standard AIA document.