RFQ_250440__Procurement_Plan.docx

DOCX document 41 KB Posted

Attached to
Request for Quote (RFQ) Synchro 12 Upgrade with Support and Maintenance
Solicitation number
250440
Issued by
Orange County, California

About this file

This is a Procurement Plan memorandum prepared by the Contracts and Procurement Management (CAMM) department for the Orange County Transportation Authority (OCTA) regarding Request for Quote (RFQ) 250440 for Synchro 12 Upgrade with Support and Maintenance. The procurement seeks quotes from authorized Synchro 12 resellers to provide software upgrades and support services for a three-year contract term effective September 1, 2026 through August 31, 2029. All responding firms must be authorized resellers; unauthorized quotes will be deemed non-responsive and rejected. Delivery shall be by electronic download only, with no tangible items accepted. Questions or clarifications must be submitted in writing no later than 11:00 a.m. on July 9, 2026, with written addenda responses due by July 17, 2026. Award will be made to the lowest responsive and responsible firm on a lump sum basis, with prices remaining firm for the entire contract term.

The total budget for this procurement is $13,642.65, funded through local sources as identified in Requisition No. R002279. An independent cost estimate has been received and approved. The procurement employs a Firm Fixed Price contract type, with cost serving as the sole evaluation criterion at 100 percent weight, as no specific firm qualifications, staffing expertise, or detailed work plan are required for award. No retention, prevailing wage, liquidated damages, or DBE goals apply to this procurement. The memo requires concurrence from both the IS Project Manager and the CAMM Section Manager before execution.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTEROFFICE MEMO

Procurement Plan – RFQ 250440

Date: June 17, 2026

To: Kristina Jenkins, IS Project Manager, Information Systems

From: Desiree Fernandez, Associate Contract Administrator, CAMM

Subject: Procurement Plan – RFQ 250440 “Synchro 12 Upgrade with Support and Maintenance"

Please review the procurement plan for the subject RFQ and advise your concurrence with the evaluation criteria and contract elements.

Procurement Type: |_| RFP |_| IFB |X| RFQ

Justification:

Request for Quotes (RFQ) is issued as the nature of the requirements allows the lowest responsive, responsible firm to be selected for award.

Evaluation Criteria:

PROPOSAL
WEIGHT
Qualifications of the Firm
0%
Staffing/Project Organization
0%
Work Plan
0%
Cost
100%

Justification:

There are no required skills, firm qualifications, or detailed work plan necessary to complete this scope of work. Therefore, cost is the only determining factor for the evaluation of this project.

Contract Type: |_| Time & Expense |_| CTO-Based |X| Firm Fixed Price

Justification (Explain the rationale for using the particular contract type):

A one-time purchase order will be issued to the lowest responsive, responsible firm.

Retention:
|_| Yes
%
|X| No
|_| N/A
Prevailing Wages:
|_| Yes
$
|_| No
|X| N/A
Liquidated Damages:
|_| Yes
$
|_| No
|X| N/A
Procurement Schedule:
|X| Attached

Contract Term: Three (3)-year term, effective 9/1/2026 through August 31, 2029

Funding Source: |X| Local |_| Measure M |_| FTA |_| FHWA

Dollar Amount: |X| $13,642.65.

Independent Cost Estimate Received: |X| Yes |_| No

Requisition Received: |X| Yes, Req No. R002279

DBE Goal: |_| Yes |X| No

Project Manager Concurrence:

________________________________________________
Kristina Jenkins, IS Project Manager, Information SystemsDate

CAMM Section/Department Manager Concurrence:

________________________________________________
Rebecca Abeyta, Section Manager III, Contracts and ProcurementDate

Revised: 05/09/2018 Revised: 05/09/2018 image1.png

File details come from the government source that posted it. Updated .