RFQ 2026-156 FMP-8A KPZE1 _ UST Replacement CMS.pdf

PDF 2 MB Posted

Attached to
RFSQ Construction Management FMP-8A Kasch Park Zero Emissions Phase 1 & Underground Storage Tanks Replacement
Solicitation number
2026-156
Issued by
Snohomish County, Washington

About this file

This Request for Qualifications (RFQ) is issued by Community Transit (CT) in Everett, Washington, seeking qualified Architectural and Engineering (A&E) firms to provide Construction Management Services (CMS) for two concurrent capital improvement projects at the Kasch Park Campus. The first project, Facilities Master Plan Phase 8A/Kasch Park Zero Emissions Phase 1 (FMP-8A/KPZE1), involves the installation of Battery Electric Bus (BEB) charging infrastructure and associated electrical improvements to support CT's transition from diesel-powered buses to battery electric vehicles. The second project, Underground Storage Tanks (UST) Replacement, entails the removal of aging underground storage tanks and installation of a new high-capacity aboveground storage tank (AST) system to modernize campus fueling infrastructure. The Construction Management Team will coordinate and oversee both projects concurrently while maintaining safe operations, minimizing disruptions to transit operations, ensuring access to critical facilities and fueling infrastructure, and facilitating coordination among CT, design teams, the General Contractor, utility providers, and other stakeholders.

The RFQ document does not specify pricing terms, response deadlines, due dates, site visit requirements, bidders' conferences, award dates, contract term, renewal options, set-asides, incumbent information, or funding sources within the available file content. Prospective firms should review the complete RFQ documentation for specific submission requirements, evaluation criteria, and contract terms related to this Construction Management Services engagement.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

All information, including forms, awards, and protest procedures are posted on Community Transit’s procurement web portal, at https://www.communitytransit.org/about/procurement.

If you a

Architectural & Engineering Request For Qualifications

Point of Contact:

Rhonda Wahlgren, CPPB Sr Procurement Specialist rhonda.wahlgren@commtrans.org

RFQ # 2026-156

Facilities Master Plan Phase 8A (FMP-8A)

Kasch Park Zero Emissions Phase 1 and Underground Storage Tanks

Replacement – Construction Managements Services

Qualified Architectural and Engineering (A&E) firms are invited to submit Statements of Qualifications (SOQ) based on the information provided in this RFQ. See the full Scope of Work in Section 3.

This RFQ will result in a Cost-Plus-Fixed-Fee (CPFF) contract beginning in approximately mid-April 2027. The term of the Agreement shall be through completion of project services.

TIMELINE

The following represents the tentative schedule for this solicitation. All times below are stated in Pacific Local Time. Dates preceded by an asterisk are estimates only and are subject to change. Any change in the scheduled dates will be issued in an Addendum to this RFQ. The award schedule may be adjusted without notice.

Event Date

Issue Date November 20, 2026

Pre-Proposal Conference December 4, 2026, at 11:00 – 11:30 am

Final Questions/Clarifications Deadline *December 11, 2026, at 3:00 pm

Statement of Qualifications Due *January 6, 2027, at 1:00 pm

Intent to Award Notice *January 25, 2026

Negotiations Completed by *February 22, 2026

Board Award April 1, 2027

Notice To Proceed *April 12, 2027

Pre-Proposal Conference:

Location: MS Teams

Join: https://teams.microsoft.com/meet/2742000109657101?p=g4uHeeFy7oMMMt6VlU

Meeting ID: 274 200 010 965 710 1

Passcode: K9Z9VT2U

Date/Time: Friday, December 4, 2026, at 11:00 – 11:30 am PDT

*All Vendors are strongly encouraged to attend the Pre-Proposal Conference. Refer to Section 1.02 for more details

Upload Proposals to: Community Transit’s web page: https://www.communitytransit.org/about/procurement https://www.communitytransit.org/about/procurement mailto:rhonda.wahlgren@commtrans.org https://teams.microsoft.com/meet/2742000109657101?p=g4uHeeFy7oMMMt6VlU https://www.communitytransit.org/about/procurement

VENDOR CHECKLIST

RFQ 2026-156

Facilities Master Plan Phase 8A / Kasch Park Zero Emissions Phase 1 (FMP8A/KPZE1) and

Underground Storage Tanks Replacement

Construction Management Services

Technical Proposals must be uploaded to Community Transit’s Procurement webpage https://www.communitytransit.org/about/procurement under the above solicitation number and title no later than the proposal due date and time to be considered responsive. Community Transit will be the final authority in determining the responsiveness of a proposal.

Signed Vendor Commitment and Information Form – Form 7.01

Certification Regarding Conflict of Interest – Form 7.02

Questionnaire – Form 7.03

Cost Proposal Guidelines – Form 7.04

Please ensure all required documents are properly completed and signed.

TABLE OF CONTENTS

SECTION 1 – INSTRUCTIONS

SECTION 2 – EVALUATION & AWARD

SECTION 3 – SCOPE OF WORK

SECTION 4 – SPECIAL TERMS & CONDITIONS

SECTION 5 – GENERAL TERMS & CONDITIONS

SECTION 5A – SUPPLEMENTAL TERMS & CONDITIONS

SECTION 6 – FEDERAL TERMS & CONDITIONS <NOT USED>

SECTION 7 – FORMS

SECTION 8 – SAMPLE CONTRACT

SECTION 9 – ACRONYMS & DEFINITIONS

Rev: 03/02/2026 SECTION 1 - INSTRUCTIONS 1

SECTION 1 – INSTRUCTIONS

1.01 PREPARATION OF PROPOSALS

A. Vendors must register at and utilize the Community Transit Procurement webpage https://www.communitytransit.org/about/procurement to participate in this procurement.

B. Vendors shall examine the solicitation’s Scope of Work, instructions, general/special/supplemental provisions, and any attachments (i.e., exhibits, appendices). Failure to do so shall be at Vendor's risk.

C. Vendors shall furnish the information required by the solicitation. Incomplete or missing forms may cause the proposal to be deemed non-responsive. Erasures or other changes shall be initialed by the person signing the proposal.

D. Price elements must not be provided or discussed at any time during the selection process for the “most qualified” Vendor, which is based on the evaluation of qualifications.

E. Proposals for goods and/or services other than those specified will not be considered unless authorized by the solicitation.

F. Community Transit is not responsible for any cost associated with the preparation of responses to this request or any other costs incurred by any Vendor prior to the execution of a contract. All materials submitted become the property of Community Transit.

G. Information will not be released by Community Transit prior to contract award to protect the integrity of the procurement process, unless otherwise required by law. All proposals will remain confidential until a contract is awarded and fully executed by all parties involved.

H. The prime Vendor need not be an engineering firm or hold an engineering Certificate of Authorization; however, all engineering services must be performed by appropriately licensed and authorized individuals or subconsultants to provide such services in WA State. The prime Vendor is responsible for assembling and managing a qualified multidisciplinary team and ensuring compliance with applicable licensing and authorization requirements. A Construction Management firm serving as the Owner's-representative may serve as the prime Vendor using qualified subconsultants, provided it does not improperly practice or offer engineering services.

1.02 SUBMITTAL

A. Statement of Qualifications (SOQ): This written response is limited to answering the questions on Form 7.03, Questionnaire regarding relevant qualifications and experience. SOQs should be no longer than fifteen (15) pages, excluding any cover page, letter of interest, or appendix for resumes per Form 7.03 Questionnaire, Part B.2. Resumes are limited to one single-sided page per individual.

B. Complete the forms identified in the ‘Vendor Checklist’ and upload electronic copies on Community Transit’s procurement portal at:

Rev: 03/02/2026 SECTION 1 - INSTRUCTIONS 2 https://commtrans.procureware.com/home to be considered responsive. Instructions for uploading all submittals are as follows:

1. Log in, navigate to ‘BIDS’ and select the solicitation number (found on the cover sheet of this solicitation)

2. Download documents from ‘DOCUMENTS’ tab

3. Questions can be submitted in the ‘CLARIFYING QUESTIONS’ tab by deadline specified.

4. Upload completed documents to ‘RESPONSE’ tab.

1.03 VENDOR PROPOSED EXCEPTIONS

By submitting a proposal, the Vendor has accepted without reservation the whole of the general requirements, the legal requirements, and contract provisions contained in this solicitation document. If no exceptions are noted in the Vendor's proposal, Community Transit expects complete conformance by the Vendor.

Vendor shall document any exceptions or additional provisions that it wishes Community Transit to consider. Vendor shall clearly identify any proposed deviations from the language contained herein. Each exception must be clearly defined and cross-referenced to the proper paragraph in this solicitation. The exception shall include, at a minimum, the Vendor's proposed substitute language and opinion as to why the suggested substitution will provide equivalent or better service and performance.

Note: Community Transit reserves the right to reject any or all Vendor-proposed exceptions or additional provisions to terms and conditions, and other requirements without comment. An excessive number of exceptions may cause the proposal to be viewed as non-responsive. Federal Transit Administration (FTA) terms are non-negotiable.

1.04 COMMUNICATIONS WITH COMMUNITY TRANSIT

This section only applies to communications regarding this solicitation. All other communications remain unrestricted.

A blackout period is established between the time a solicitation is issued by Community Transit and the time the Agency awards the Contract. After the issuance of any solicitation, all Vendors or individuals acting on their behalf are hereby prohibited from contacting any Community Transit employee, official, or representative at any time during the blackout period. Communications concerning this solicitation with other than the listed Procurement Staff may cause the Vendor to be disqualified.

All communications during the blackout period shall be e-mailed to the following address: procurement@commtrans.org

1.05 REVISIONS OF PROPOSALS

All revisions shall be made in writing, executed, and submitted in the same form and manner as the original proposal.

https://commtrans.procureware.com/home mailto:procurement@commtrans.org

Rev: 03/02/2026 SECTION 1 - INSTRUCTIONS 3

1.06 WITHDRAWAL OF PROPOSALS

Proposals may be officially withdrawn from consideration only by submitting a written request to Community Transit’s point-of-contact identified on the cover sheet prior to the proposal due date.

1.07 REQUEST FOR DUE DATE EXTENSION

Prior to the deadline for questions due, Vendors may request an extension of the proposal due date. Such requests must be accompanied by documentation to justify an extension. Vendor also agrees to supply any additional information that may be required by Community Transit to make a decision on any request for extension. Community Transit shall examine the request and any documents and shall determine if the Contractor is entitled to an extension and the duration of such extension. Any approved extension will be issued as an Addendum.

1.08 LATE PROPOSALS

The time of receipt at Community Transit is the date-time stamp of the offer upload per Community Transit’s solicitation portal. Submittals will not be accepted by the portal after the due time of the solicitation.

1.09 REJECTION OF PROPOSALS

Community Transit may waive informalities and minor irregularities in proposals received.

Community Transit reserves the right to reject any or all proposals.

1.10 JOINT VENTURE

Joint venture proposals will not be accepted by Community Transit. Vendors shall structure submitted proposals, so the Vendor is the Primary Vendor. Firms associated with the Primary Vendor providing goods and/or services to Community Transit under this Contract shall be as a subcontractor to the primary Vendor and not to Community Transit.

1.11 SINGLE PROPOSER

If only one proposal is received, Community Transit may request an extension of the proposal due date or evaluate the single proposal (See Section 2.02).

1.12 ADDENDA

If at any time Community Transit changes, revises, deletes, clarifies, increases, or otherwise modifies the solicitation, a written Addendum to the solicitation will be issued.

Some routine or non-critical clarifications (items that don’t change the Scope) may be provided under “Clarifying Questions” on our website for this solicitation without issuance of Addenda. Vendors must register for this solicitation to be notified of any Addenda and/or new documents. It is the Vendor’s responsibility to check for addenda and other new documents on-line.

No oral interpretations of the solicitation will be made to any Vendor. All questions and any explanations must be requested in writing and directed to the Point of Contact no later than the deadline specified on the cover sheet or as extended per addendum. Oral explanations or instructions are not binding. Any information modifying a solicitation will be furnished to all Vendors by addendum.

Rev: 03/02/2026 SECTION 1 - INSTRUCTIONS 4

1.13 ACKNOWLEDGMENT OF ADDENDA

By submitting a proposal on our web portal, Vendor acknowledges receipt and understanding of any and all Addenda issued for this solicitation.

--END SECTION 1--

SECTION 2 – EVALUATION & AWARD 1

SECTION 2 – EVALUATION & AWARD

2.01 METHOD OF PROCURMENT

Following the Qualifications Based Selection (QBS) process of the federal Brooks Act or RCW 39.80, as applicable, Community Transit will identify the most qualified Vendor based on demonstrated competence and qualifications for the type of engineering and design services being procured, and at a fair and reasonable price. After the evaluation of Statements of Qualifications or Technical Proposals to select the “most qualified” Vendor, Community Transit and the selected Vendor will enter negotiations of scope and cost.

If the Parties are unable to negotiate a satisfactory agreement, or Vendor does not execute an agreement within 30 days after the final award notice, negotiations with the Vendor will terminate and Community Transit will enter negotiations with the second highest ranking firm. This process will repeat until a contract has been fully executed.

No work will be undertaken by any Vendor without a mutually agreed upon Scope of Work, Schedule, and price contract executed by the Parties.

2.02 EVALUATION PROCESS

A Community Transit evaluation team will review and score each response in accordance with the requirements stated in this solicitation.

A. Selection Criteria

1. Evaluations for the “most qualified” Vendor will be based on the following weighted criteria regarding the firm and the individuals assigned to perform the work.

Community Transit may obtain relevant information through other means (i.e., references, past performance, etc.)

B. The purpose of interviews, if held, will be to further review the finalists in specific areas to determine the best fit for Community Transit. Finalists shall have key employees available for these interviews. Community Transit will notify finalists as to the time, date, and location for an interview.

C. Final Selection: Will be based on the total of the scores achieved for each Criterion.

Community Transit may enter negotiations with the highest ranked Vendor for purposes of awarding a contract to the “most qualified” Vendor.

# Criteria Points Description

1. Firm Qualifications & Relevant Experience

50 Evaluate responses from Questionnaire.

2. Key Personnel Qualifications, Experience & Availability

40 Evaluate responses from Questionnaire.

3.

Subconsultants, Small Business & Equity Commitment

10 Evaluate responses from Questionnaire.

Total 100

SECTION 2 – EVALUATION & AWARD 2

D. Contract Negotiations: A cost or price proposal will be requested of the “most qualified” Vendor prior to negotiations, which shall account for all costs necessary to perform the services to completion and shall form the basis for payment. Vendor’s detailed cost or firm-fixed price proposal submittal shall follow the instructions outlined in Form 7.04, Cost Proposal Guidelines or Price Sheet, as applicable, and shall be inclusive of Washington State Sales Tax and any other applicable governmental charges, unless otherwise specified.

2.03 AWARD

A. Community Transit will award to the Vendor whose response conforms to the solicitation instructions and proposed team is deemed “most qualified” to perform the work. Award will depend on successful negotiations with the selected Vendor.

B. Intent to Award: The intent to award notification will be posted on Community Transit’s website as shown on the cover sheet. Only the selected Vendor will be sent an Intent to Award letter and a Contract.

C. Notice to Proceed: Upon submission of all required documents, Community Transit will execute the Contract and issue a Notice To Proceed (NTP). A Purchase Order (PO) will be issued for invoicing purposes and may also serve as the official NTP.

--END SECTION 2--

SECTION 3 – SCOPE OF WORK 1

SECTION 3 – SCOPE OF WORK

3.01 PURPOSE

Community Transit (CT) requires Construction Management Services (CMS) and oversight for two capital improvement projects at the Kasch Park Campus (KPC) in Everett, WA that are anticipated to be constructed concurrently:

1. Facilities Master Plan Phase 8A, Kasch Park Zero Emission Phase 1 (FMP-8A/KPZE1)

This Battery Electric Bus (BEB) Charging Infrastructure project will support CT’s transition of its Fixed Route fleet from diesel-powered buses to BEBs through the installation of new BEB charging infrastructure and associated electrical improvements.

2. Underground Storage Tanks (UST) Replacement

This project will modernize the campus fueling infrastructure through the removal of aging USTs and installation of a new, high-capacity Aboveground Storage Tank (AST) system. The intent is to reduce environmental risks associated with subsurface storage while providing reliable fueling infrastructure capable of supporting simultaneous vehicle fueling.

The Construction Management Team (CMT) will be responsible for coordinating and overseeing construction activities across both projects to promote safe and efficient project delivery, minimize disruptions to ongoing transit operations, maintain access to critical facilities and fueling infrastructure, and facilitate effective coordination among CT, the respective Design Teams, the General Contractor (GC), utility providers, and other project stakeholders.

CT anticipates delivering both projects under a single construction contract; however, since the projects are funded through separate accounts to facilitate the tracking and documentation of grant-eligible expenses, project costs must remain separately identifiable and accounted for. The CMT will maintain separate cost records and submit individual invoice packages for each project, including a CT-approved allocation of shared services and costs. The CMT will also review construction pay applications and supporting documentation to verify that construction costs are appropriately identified, allocated, and charged to the corresponding project and CT account.

3.02 BACKGROUND

A. FMP-8A/KPZE1 BEB Chargers

The new battery electric chargers are planned to be installed on the west side of the KPC. The design and construction of the charging infrastructure will be coordinated with the procurement and delivery schedule for the new BEBs.

CT has coordinated with the Snohomish County Public Utility District (SnoPUD), which has confirmed that the existing electrical circuit has sufficient capacity to support this load. An existing underground primary electrical line currently serves the site from the southwest corner of the property. SnoPUD plans to intercept and utilize this existing line and does not anticipate impacts to the adjacent green space or wetlands. SnoPUD estimates that the design and installation of the required electrical infrastructure will take approximately six months.

SECTION 3 – SCOPE OF WORK 2

B. Underground Storage Tank Replacement

The new AST system will utilize a consolidated tank configuration on the west side of the fuel island to optimize space. The system is anticipated to include diesel and gasoline storage, maintenance fluid storage, and high-volume dispensers capable of fueling multiple buses simultaneously.

The project will require removal of the existing USTs, including environmental testing of the surrounding soil due to the site's history of previous fuel and fluid releases.

Excavation and sitework activities must be carefully planned and coordinated to account for the proximity of existing stormwater vaults and subsurface utilities, eliminating potential impacts to existing infrastructure.

Maintaining continuous fueling operations throughout construction is critical to CT operations. Construction will therefore be phased so that the new AST and fueling systems are installed, tested, and commissioned prior to decommissioning and removing the existing UST system.

C. Since the UST Replacement and KPZE1 projects are anticipated to be constructed concurrently within the active KPC, the CMT will be responsible to help coordinate construction sequencing, contractor activities, site access and staging, utility work, safety requirements, and minimize any impacts to CT operations across both projects.

3.03 CONSTRUCTION MANAGEMENT SERVICES SUMMARY

A. The CMT shall provide construction management services and work directly with the Community Transit Project Manager (CTPM). The CMT will monitor the Work for compliance with the Construction Documents, contract requirements, permit conditions, and jurisdictional approvals; identify defects and deficiencies; help coordinate project activities among stakeholders; and help ensure the successful delivery of the project in accordance with applicable codes, industry standards, and best management practices.

B. The CMT will provide two (2) positions:

1. Construction Manager (CM): Will also serve as the Resident Engineer (RE) and have relevant experience in reviewing and assessing engineering Drawings, Specifications, Submittals, RFIs, field condition problem solving, and experience coordinating with local jurisdictions.

2. On-Site Inspector: Will have experience evaluating on-site progress and labor in the field for alignment with the construction schedule, conformed Construction Documents, preparing proposed Field Directives (for CT authorization when needed), monitoring concrete pours, and observing and promptly reporting apparent safety concerns. One full-time, on-site Inspector will be required to provide construction oversight for both the UST and KPZE1 projects. This individual will be shared between the two projects rather than having a dedicated Inspector assigned to each project.

C. The CM/RE and Inspector are preferred to have experience with both BEB charging infrastructure and replacement of USTs as it relates to construction, equipment start-up and commissioning. The GC retains responsibility for construction means, methods, and contractor safety. The CMT shall follow CT-approved procedures for

SECTION 3 – SCOPE OF WORK 3

escalating immediate hazards; authority to suspend work shall be established in the Construction Documents. Directives affecting scope, cost, or time require CT authorization.

3.04 ESTIMATED SCHEDULE

• April 2027 – Notice To Proceed / Kickoff

• September 2027 – Construction Design Bid Documents Finalized

• October 2027 – Construction Begins

• October 2028 – Anticipated Construction Complete; CMT Closeout and Task Completion to follow within the agreed closeout period.

3.05 DELIVERABLE STANDARDS

A. Unless a task states otherwise, the CMT shall comply with the following requirements for all Deliverables:

1. Deliverables shall be complete, internally coordinated, and reviewed through the Consultant's Quality Assurance and Quality Control (QA/QC) process. Each submittal shall identify the responsible preparer and reviewer and include evidence of the completed review when requested.

2. Unless otherwise specified, apply CT standards and the requirements of the applicable Construction Documents, laws, codes, regulations, design criteria, manuals, and industry standards in effect on the date of Notice to Proceed.

Promptly identify conflicts or proposed deviations for CT direction.

3. Clearly identify assumptions, unresolved issues, deviations from prior direction, and decisions needed from CT in each draft Deliverable.

4. Provide draft and final versions of reports, estimates, and other Deliverables identified in this Scope of Work. With each revised or final submittal, provide a comment-response matrix or redlined copy that identifies each review comment, the Consultant response, and where the comment was addressed. Clearly identify comments that were not incorporated and the reason. Routine logs, daily inspection reports, invoices, and other recurring administrative records do not require separate draft and final versions or comment-response matrices unless specifically requested by CT.

5. Provide electronic copies of all Deliverables in searchable PDF and in the native, editable format used to develop the Deliverable, unless otherwise specified.

Provide supporting calculations, models, data files, linked files, and other source materials necessary for CT to use and update the Deliverable.

6. Provide draft meeting and workshop agendas, including objectives and required decisions, at least two (2) business days before the scheduled event.

7. Provide draft meeting or workshop notes, including decisions, action items, responsible parties, and due dates, within two (2) business days after the event.

8. Update action-item and decision logs within five (5) business days after each project team meeting, or more frequently when needed to support timely decisions.

SECTION 3 – SCOPE OF WORK 4

9. Incorporate review periods into the Project Schedule. Unless otherwise specified, allow three (3) business days for CT review of meeting notes and routine administrative documents and 10 business days for review of technical Deliverables. Consultant shall not assume approval due to the passage of time and shall coordinate any schedule impacts associated with consolidated comments or additional review cycles.

3.06 SCOPE OF WORK SUMMARY

Task 1 Project Management & Administration

Task 2 Preconstruction & Mobilization

Task 3 Construction Administration

Task 4 Schedule, Cost, Change, Risk & Contract Compliance

Task 5 Field Inspection & Construction Quality Documentation

Task 6 Special Testing & Inspection

Task 7 Project Closeout

A. TASK 1 - PROJECT MANAGEMENT AND ADMINISTRATION

1. Activities

a. Plan, coordinate, and manage the Consultant team, including subconsultants, and third-party inspectors to complete the Services in accordance with the approved scope, schedule, budget, and quality requirements.

b. Prepare and maintain a project risk register appropriate to the Services.

Identify each risk, potential effects, probability, impact, owner, response strategy, mitigation action, and status. Review the risk register with CT at agreed intervals.

c. Organize and facilitate weekly consultant project management meetings with CT staff using a CT-approved virtual collaboration tool (e.g. Microsoft Teams);

prepare agendas, maintain meeting notes, and relevant action items.

Coordinate these meetings with Task 3 check-ins to avoid duplicative meetings. Use recordings and transcription tools only as approved by CT.

d. Provide two monthly contract administration reports with associated project invoices (one invoice package for the UST project and one invoice package for KPZE1 project) including, but not limited to, individual hours worked, labor rates, overhead and profit calculations for staff and consultants, tasks accomplished, budget status, and explanation of comparison between percent complete and actual hours spent versus percent proposed and hours scheduled for the past month, 3-month billable outlook, etc.

1) Track all labor hours, subconsultant charges, testing costs, reimbursable expenses, and other billable costs separately by project and task. Submit one separate monthly invoice and supporting report package for each project, identifying the applicable CT-provided project and account codes.

Maintain supporting time and cost records that substantiate the charges to each project. Allocate shared services and costs using a CT-approved

SECTION 3 – SCOPE OF WORK 5

method, identify the allocation in each invoice package, and ensure that the combined charges do not exceed the actual billable hours or costs incurred.

2) Submit invoices monthly for services performed during the prior month, along with monthly status reports (contract budget, contract schedule, project schedule, project risk register). Notify CT in writing before including charges for work performed more than sixty (60) days before the invoice date.

3) Submit year-end invoices to CT by a mutually agreed upon date in January of the following year. In no case should work performed in the prior year be invoiced after this date.

4) Submit a monthly schedule update showing actual progress through the data date, forecast start and finish dates, changes to the critical path and available float, activities or milestones at risk, corrective actions, and the current forecast completion date.

e. Use the CT-designated document management and collaboration system to store, transmit, and control project records and Deliverables. Comply with CT file-naming, version-control, access, retention, and information-security requirements. Do not establish a separate system without prior written approval from CT.

2. Deliverables

a. Risk Register

b. Kick-Off Meeting agenda, presentation, and notes

c. Project Team meeting agendas and notes

d. Separate monthly invoices and supporting progress report packages for KPZE1 and UST, including project and account codes and documented shared-cost allocations.

e. Monthly project schedule updates

f. Project correspondence, transmittals, agendas, meeting notes, and action-item logs

3. Assumptions

a. The Project Management and Administration budget shall be based on a sixteen-month period of performance, beginning at Notice to Proceed and ending at completion of the Services. The negotiated scope and fee shall identify the assumed preconstruction, active construction, and closeout durations. Services beyond the agreed duration or staffing assumptions require CT authorization in accordance with the Agreement.

b. Attendance at weekly scheduled project team meetings during the period of performance.

B. TASK 2 - PRECONSTRUCTION AND MOBILIZATION

1. Activities

SECTION 3 – SCOPE OF WORK 6

a. Review the 90% and final Issued for Bid design documents at the identified design milestones for constructability, completeness, consistency, coordination, sequencing, access, and potential construction risks.

b. Review anticipated construction phasing, staging, site access, temporary facilities, traffic control, temporary transit operations, passenger access, contractor work areas, material storage, equipment access, utility outages, shutdowns, and maintenance of existing operations.

c. Participate in interdisciplinary constructability-review meetings with CT, Engineer of Record, and other stakeholders.

d. Meet with CT and Engineer of Record to review significant findings and resolve comments. Engineer of Record to retain responsibility for evaluating and incorporating design revisions.

e. Back-check design documents to determine whether accepted constructability comments have been incorporated or resolved. Document unresolved and/or partially resolved items.

f. Attend Pre-Bid Meeting/Site Visit when requested by CT.

g. Compile Bidder questions and draft recommended responses for review by CT and the Engineer of Record. CT retains sole authority to issue procurement communications and Addenda.

h. Assist the CT Procurement Specialist with Bid Schedule reviews, as necessary.

i. Plan, facilitate, and document one formal Preconstruction Meeting with the GC, design team, environmental consultant, CTPM, and CT internal stakeholders, as directed by CT. Address roles and authority, schedule constraints, notices to proceed, permits, review procedures, temporary erosion and sediment control (TESC), Stormwater Pollution Prevention Plan (SWPPP), concrete cleanup, cultural-resource and inadvertent-discovery procedures, contaminated-soil procedures, payment processing, Schedule of Values and cost codes, public and worker safety interfaces, and protection of transit operations.

j. Review and comment (if needed) on all pre-construction Submittals, including but not limited to, Baseline Schedule, Staging Plans, Safety Plans, SWPPP, Submittal Log, Inspection and Test Plan, List of Long Lead Materials, etc., for contractual completeness and readiness. Confirm receipt and contractual completeness of the GC's safety plan without approving its adequacy. Route technical questions and design matters to the authorized reviewer. Task 4 shall perform substantive analysis of the GC baseline schedule.

k. Review the GC’s proposed Schedule of Values (SOV) and allocation of shared construction costs with CT before the first pay application to confirm that the two projects are separately identified and the breakdown supports payment from the respective CT accounts.

SECTION 3 – SCOPE OF WORK 7

l. Review and track receipt of the GC’s required Apprentice Utilization Plan (AUP) before construction Notice To Proceed, where applicable to the Construction Documents, and report outstanding requirements to CT.

m. Maintain a permit-condition matrix and open-issue list and coordinate clarifications through CT and the design team. The Consultant shall not prepare permit applications, redesign the Project, or commit CT to agency requirements without written authority.

n. Observe and document installation of initial TESC and SWPPP measures before construction begins at each authorized work location and coordinate observed deficiencies through the established process. Ongoing construction-phase SWPPP and TESC observation is included in Task 5.

o. Coordinate readiness of the CM field office and verify that the facilities, utilities, communications, equipment, access, security, and records-management provisions assigned in the field-office responsibility matrix are operational before field staffing begins.

2. Deliverables

a. Constructability Review Plan identifying the approach, disciplines, reviewers, design milestones, focus areas, schedule, and comment-resolution process.

b. Constructability Review Comment Log to include but not limited to drawing, document reference, description, potential cost, schedule, quality, construction impact, recommended action, and updates to document final resolution.

c. Procurement question-and-recommended-response log, as requested.

d. Pre-solicitation and preconstruction meeting agendas, attendance records, minutes, and action items.

e. Pre-construction submittal review for completeness comments and disposition tracking.

f. Permit-condition matrix and open-issue list.

g. Initial SWPPP and TESC installation observation record.

h. Completed field-office readiness checklist and responsibility matrix.

3. Assumptions

a. Constructability reviews to be 10 business days for each milestone unless otherwise agreed to in writing.

b. Engineer of Record retains responsibility for design adequacy, design coordination, code compliance, calculations, and revisions to the Contract Documents. CT retains authority for changes to the Contract Documents, and communications with CT Procurement.

c. The GC will provide timely and complete pre-construction submittal submissions and install required temporary controls before beginning work.

d. Field-office responsibility shall be documented in a CT-approved responsibility matrix before fee negotiation. The fee basis assumes the GC will provide the

SECTION 3 – SCOPE OF WORK 8

trailer, utilities, internet, furniture, IT equipment, printers, physical security, maintenance, relocation, and demobilization as required by the Construction Documents.

C. TASK 3 – CONSTRUCTION ADMINISTRATION

1. Activities

a. Facilitate weekly construction progress meetings as listed below. Prepare and distribute meeting agendas and minutes and maintain applicable action-item and decision logs. Construction Progress meetings shall be held in person during active construction unless CT approves virtual participation.

b. Owner, Architect, and Contractor (OAC) Meetings: Facilitate weekly OAC meetings with CT staff, the Architect, and the GC.

c. Project Cost Review Meetings: Facilitate weekly meetings with the GC to review and negotiate all outstanding project cost items, including pending change orders and other cost-related issues.

d. CTPM and RE/ Inspector Check-In Meetings: Facilitate weekly individual check-in meetings with the CTPM to discuss field issues, installation deficiencies, RFIs, submittals, and other items that may have schedule or cost impacts. These check-ins may also satisfy the Task 1 consultant project management meeting requirement when the necessary topics are covered.

e. Facilitate pre-installation meetings when required by the Contract Documents or when material coordination decisions are needed and document decisions and action items.

f. Provide routine Construction Administration coordination among CT, the GC, design team, environmental consultant, authorities having jurisdiction, testing agencies, and other Project participants.

g. Administer the CT-designated Document Control System (DCS). Coordinate authorized access and licenses, configure standard workflows, and provide user guidance and training. Do not establish a separate DCS without written CT approval.

h. Administer RFI and submittal workflows, including completeness screening, routing to the authorized reviewer, due-date monitoring, consolidation of reviewer input, distribution of CT-authorized responses, status logging, and escalation of overdue items. Consultant shall not issue design interpretations unless expressly delegated by CT and the Engineer of Record.

i. Maintain current electronic logs for correspondence, RFIs, submittals, review status, responses, inspections, photographs, meetings, changes, tests, deficiencies, and other Project records. Task-specific personnel shall create their records and file them in the DCS in accordance with this task.

j. Maintain a field set of Contract Documents marked to show reported construction progress. Maintain only the hard-copy records expressly identified by CT; otherwise, the electronic DCS is the official working record.

SECTION 3 – SCOPE OF WORK 9

k. Tag and categorize all RFIs, Submittals, field directives, design clarifications, and OAC meeting items in the DCS by specific project identification (KPZE1/FMP8 vs. UST Replacement). For items affecting shared infrastructure, campus access, or concurrent work areas, designate the entry as Shared Campus Coordination to ensure clear audit trails and supporting records for separate project account allocations.

2. Deliverables

a. Weekly OAC construction meeting agendas, minutes, action items, and project status summary.

b. Weekly RFI, Submittal, change order log, testing, inspection, deficiency, and permit tracking logs.

c. Current electronic project filing system and marked field set of Contract Documents.

3. Assumptions

a. The DCS will initially be SharePoint transitioning in Q2 2027 into ProCore. The fee assumes no additional user licenses will be required and one training/overview session.

b. CT will provide DCS standards for naming, workflow, information security, applicable state grant compliance, retention, public records, and final archiving.

c. The GC, design team, testing agencies, and other reviewers will use the DCS and follow the established routing and response procedures.

4. Exclusions and Optional Services

a. Enterprise software purchase, custom software development, integrations beyond standard configuration, cybersecurity certification, migration of unrelated legacy records, and long-term records hosting are excluded.

D. TASK 4 – SCHEDULE, COST, CHANGE, RISK, AND CONTRACT COMPLIANCE

1. Activities

a. Review the GC baseline schedule and monthly GC CPM updates for compliance with the Contract Documents, logic, sequencing, constraints, calendars, progress, percent complete, milestones, float, critical and near-critical paths, and completion-date forecast.

b. Compare each GC’s CPM update with the accepted baseline and prior update and identify variance, delayed or driving activities, potential milestone impacts, and proposed corrective actions. Review GC three-week look-ahead schedules against actual progress and observed field conditions.

c. Prepare schedule review comments and recommendations. Acceptance of a schedule, time extension, recovery plan, or contractual interpretation remains with CT.

SECTION 3 – SCOPE OF WORK 10

d. Review project costs and budget status and document material concerns.

Weekly status information may be incorporated into Task 3 construction-meeting records rather than issued as a duplicate standalone report.

e. Review monthly Pay Applications, supporting quantities, SOV, cost codes, materials and stored-material documentation, certified payroll and prevailing wage Intents and Affidavits status, and the current GC schedule.

1) Conduct completeness conferences when useful, but do not prepare or certify the GC's pay application. Use Task 5 quantity records and provide a payment recommendation to CT.

2) Verify that the GC’s SOV and each pay application separately identify costs for the KPZE1 and UST projects using CT-approved project and account codes. Review the allocation of shared construction costs against a CT-approved allocation method.

3) Confirm that current and cumulative payment amounts, stored materials, approved changes, and retainage are correctly attributed to each Project and reconcile to the total pay application.

4) Identify discrepancies and coordinate corrections with the GC before recommending payment. Provide the recommended payment amount separately for each Project.

f. Administer the change-management process, including field authorizations, change requests and proposals, entitlement review, coordination with the design team to confirm design intent, independent evaluation of cost and schedule impacts, maintenance of the change log, negotiation support within the agreed scope and fee assumptions, and recommendations to CT. Identify the applicable project and CT account for each proposed change, including a documented allocation when a change affects both projects. Track proposed and approved change amounts separately for each Project.

g. Provide construction-contract risk and issue information for inclusion in the master Project Risk and Issue Register maintained under Task 1. Do not maintain a duplicate risk register.

h. Receive and review GC certified payrolls for apparent compliance with applicable Washington State prevailing wage requirements identified in the Construction Documents; conduct field wage interviews; track deficiencies; and report exceptions to CT. This service is not a financial statement or fraud audit.

i. Collect and review L&I approved prevailing wage Intents and Affidavits (I&A) from the GC and every subcontractor and send to CT’s Procurement Specialist with a log identifying outstanding I&A and subcontractor status. The log will include, as applicable to the subcontractors, their UBI number, license/registration number, Industrial Insurance account number, Intent ID, Intent Approved Date, Affidavit ID, Affidavit Approved Date, and any SBE number.

j. Provide day-to-day oversight of Apprenticeship Utilization Requirements (AUR), including but not limited to, collecting and auditing monthly utilization reports from the GC with the payroll data to verify and track apprentice hours, SECTION 3 – SCOPE OF WORK 11 monitoring the GC’s utilization percentage, reporting metrics to the CTPM, flagging any shortfalls early so the project team can make corrections before penalties accrue, and maintaining compliance records for the project files. CT has sole authority to approve or deny the GC’s request to reduce AUR percentages.

k. Review RFIs and Submittals for construction coordination and potential cost or schedule impacts; coordinate technical review with the authorized reviewer through Task 3. Monitor GC updates to redline drawings to document modifications incorporated through Change Orders and Construction Change

Directives.

l. When requested by the CTPM, review Change Order Requests (CORs) for completeness within three (3) business days of receipt, identify any additional information needed, and establish the analysis deadline with the CTPM.

Submit the Independent Governmental Cost Estimate (IGCE) and recommendation addressing contractual entitlement, cost, and schedule impacts within the agreed deadline.

m. Use the RFI and Submittal logs maintained under Task 3 to identify and track items with potential cost or schedule impacts. Do not maintain duplicate logs.

n. Coordinate planned fueling and power interruptions, access restrictions, utility outages, changes to bus circulation, and other construction impacts with the

CTPM and CT-designated Operations contact. Provide at least 14 Calendar

Days’ advance notice and obtain required CT approval before work affecting operations proceeds. Immediately report unplanned or emergency impacts and document notices, approvals, and unresolved items in the Operations coordination log.

o. Review GC traffic control plans, staging layouts, and temporary lane shift configurations against fixed-route bus swept-path requirements. Ensure proposed temporary work zones preserve required turning radii and operational clearances prior to issuing operational concurrence to CT.

2. Deliverables

a. GC baseline schedule review memorandum and comment log.

b. Monthly GC CPM schedule analyses and three-week look-ahead review comments.

c. Cost, budget, schedule, quality, safety-reporting, and issue summaries incorporated into meeting records or monthly reports.

d. Provide budget review and analysis every two weeks for overall project costs, identifying costs separately for each project. This analysis may be incorporated into the required cost-review meeting records or monthly reports rather than issued as a duplicate standalone report.

SECTION 3 – SCOPE OF WORK 12

e. Reviewed GC pay applications with quantity support, verified project cost breakdowns, documented shared-cost allocations, and payment recommendations identifying the amount payable from each project account.

f. Current change log, change analyses, independent cost or schedule reviews within stated assumptions, negotiation records, and change-order recommendations.

g. Construction risk and issue updates for the master register.

h. Field wage interview records, Intents and Affidavits review records, and AUR records.

i. Operations coordination log documenting planned impacts to transit operations, advance notices, CT approvals, and unresolved coordination items.

j. Current RFI and Submittal logs are maintained under Task 3, with cost and schedule impacts identified.

E. TASK 5 – FIELD INSPECTION AND CONSTRUCTION QUALITY DOCUMENTATION

1. Activities

a. Provide full-time on-site inspection during active GC work using competent personnel and coordinate coverage with the accepted GC schedule and approved CMT staffing plan. The staffing plan will identify coverage for concurrent work locations, critical activities, absences, overtime, and any night or weekend work, including specialist support and additional inspection coverage when needed and authorized by CT.

b. Provide field observation and coordination during subsurface excavation, soil testing, and UST decommissioning activities. Coordinate directly with CT’s third-party Environmental Consultant and the GC during the discovery, handling, stockpiling, and disposal of contaminated soils or groundwater. Verify and record contaminated soil haul-off volumes, soil disposal manifests, and chain-of-custody documentation to support environmental compliance and Task 4 payment verification.

c. Observe work for conformance with the Contract Documents and permits and promptly communicate observed deficiencies or nonconforming work through the established process.

d. Document observed deficiencies; notify the CTPM and GC; track corrective action; and verify documented correction or disposition approved by the authorized party. The Consultant shall not independently accept a nonconforming condition unless expressly authorized.

e. Prepare daily inspection reports and photographs. Organize source photographs by date, work location, and activity for efficient retrieval and CT review.

f. Collect, measure, and document materials and quantities needed to support payment review. Provide the records to Task 4. Task 4 remains responsible for the payment recommendation. Identify the applicable project and SOV

SECTION 3 – SCOPE OF WORK 13

items in quantity and payment support records, including documentation supporting allocations of work shared by both Projects.

g. Maintain material-acceptance logs and field construction records documenting labor, equipment, work in progress and work completed, working and nonworking days, discrepancies, discussions, test results, weather, and other pertinent conditions.

h. Observe and document ongoing SWPPP and TESC compliance during construction and escalate observed deficiencies through the contract-administration process. Initial SWPPP and TESC installation observation are included in Task 2.

i. Coordinate field questions and technical issues with the RE, CTPM, GC, design team, and testing personnel.

j. Inspect temporary traffic control measures, work zone barriers, and temporary lane shifts daily to verify that physical field layouts maintain required bus turning clearances and do not impede active transit vehicle circulation or fuel island access

k. Coordinate and document equipment startup, testing, commissioning, operator training, and operational turnover for the BEB charging and AST fueling systems in collaboration with the GC, equipment suppliers, utility provider, design team, and CT. Verify that required testing and commissioning activities are completed by the parties designated in the Construction Documents, including coordinating and observing the required testing and obtaining CT authorization before taking the existing fueling system out of service. Track deficiencies, monitor their resolution, and recommend readiness for CT acceptance.

2. Deliverables

a. Daily inspection reports for each active workday and assigned inspector. Daily reports to be provided to CT within 24 hours after the reported field work.

b. Dated and indexed inspection photographs.

c. Field construction reports and quantity records supporting Task 4 payment review.

d. Current material acceptance log and supporting documentation.

e. Deficiency and nonconformance records with corrective action and disposition tracking.

f. Construction-phase SWPPP and TESC observation and escalation records.

g. Startup, commissioning, operator-training, and operational-turnover coordination records, including outstanding deficiencies and recommendations regarding readiness for CT acceptance.

3. Assumptions

a. Inspection does not relieve the GC of responsibility for quality control, Contract Document compliance, safety, or correction of defective work.

SECTION 3 – SCOPE OF WORK 14

b. SWPPP and TESC services are limited to routine observation and escalation unless the fee identifies required certifications, monitoring frequencies, sampling, or agency reporting.

c. The CM/RE and…