RFQ 2021-62 Clarifying Questions 1.pdf
PDF 220 KB Posted
- Solicitation number
- S-C01010-00000131
- Issued by
- Clackamas County, Mission CDP, Oregon
About this file
This document is a clarification response to Request for Quotes #2021-62 for On-Call Bridge Consulting Services issued by an Oregon state or local government entity. The RFQ solicitation requires interested firms to submit quotes addressing qualifications, project team capabilities, project examples, and fee schedules within a 20-page limit, with all pages including forms, cover sheets, and tables of contents counting toward this maximum. The response clarifies that evaluation will focus primarily on the first four items listed in Section 4 of the RFQ, though no formal point-based scoring system is employed in this informal solicitation process. Fee schedules must be submitted for both the prime consultant and all subconsultants representing the full project team.
The document addresses three key questions submitted by prospective bidders regarding submission requirements and evaluation methodology. Notably, the clarification confirms that all supporting documentation counts against page limits and that comprehensive fee information from the entire team is mandatory for consideration. While specific contract terms, award dates, and pricing thresholds are not detailed in this clarification document, the response indicates that the review committee will emphasize technical qualifications and demonstrated project experience when evaluating competing quotes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 2021-53 Calibration of Laboratory Equipment - final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTES #2021-62
ON-CALL BRIDGE CONSULTING SERVICES
RESPONSE TO CLARIFYING QUESTIONS #1
July 15, 2021
Note that these are questions submitted by interested firms to the above referenced solicitation. The below answers are for clarification purposes only and in no way alter or amend the RFQ as published.
1. Do the forms, coversheet, table of contents, etc. count towards the 20-page limit?
Answer: Yes, all pages count towards the 20-page limit.
2. Is there a point’s distribution for each section?
Answer: This is an RFQ (informal) solicitation, so there is no formal evaluation using “points”.
However, generally when the review committee reviews the quotes, they generally review:
qualifications, project team capabilities, project examples, fee schedules and other information.
When look at Item 4 Quotes, of the RFQ document, the first four items in the list are typically reviewed heavier.
3. Are fee schedules for subconsultants required?
Answer: Yes. Fee schedules are needed for the prime and subconsultant representing the entirety of the team.
End of Clarifying Questions #1