About this file

This document is a Request for Quotations (RFQ) issued by the State of Maine Department of Administrative and Financial Services Office of State Procurement Services (OSPS) on behalf of the Department of Transportation (Requesting Department). The RFQ seeks quotations to provide a Trailer Mounted Boring and Subsurface Exploration Drill Machine. The expected purchase quantity is one unit, and quotations are due by 4:00 p.m. local time on Monday, November 18, 2024. The drill machine will be delivered to MaineDOT Fleet Services in Augusta, Maine. Bidders must submit their quotations through the State's electronic procurement system, and the contract will be awarded on a best value basis to the lowest price bidder whose specifications most closely meet the requirements.

The RFQ provides detailed technical specifications for the drill machine, including requirements for the rotary drive, vertical drive, power unit, hydraulic system, controls, safety features, and trailer assembly. Bidders must provide pricing, delivery timelines, warranty information, and details on their service and repair capabilities in Maine. The State will pay the selected vendor net 30 upon receipt of an acceptable invoice, and the manufacturer's standard warranty will apply starting from the in-service date.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF MAINE

DEPARTMENT OF ADMINISTRATIVE AND FINANCIAL SERVICES

OFFICE OF STATE PROCUREMENT SERVICES

RFQ # 17D 241104-106

Trailer Mounted Boring and Subsurface Exploration Drill Machine

Quotations/Responses Due: Monday, November 18, 2024 not later than 4:00 p.m. local time

Note: All questions and responses must be provided via the State of Maine’s e-Procurement system: AdvantageME / Vendor Self Service (VSS).

General Instructions on Bidder Questions It is the responsibility of each Bidder to examine the entire RFQ and to seek clarification by submitting questions through the Q & A List tab on the Solicitation page in the CGI Vendor Self Service (VSS). Any answers to questions will appear there as well. It is the vendor's responsibility to log in to view all questions and answers posted. Additional information obtained any other way will not be valid.

In the event that you must contact us for any other reasons than the Q & A previously mentioned, only the Buyer listed on the Solicitation page may be contacted from the time this RFQ is issued until award notification is made. No other person/State employee is empowered to make binding statements regarding this RFQ. Violation of this provision may lead to disqualification from the bidding process, at the State’s discretion.

Summary For this competitive Request for Quotations (RFQ) process, the State of Maine Office of State Procurement Services (“OSPS”) is acting on behalf of the Department of Transportation (“Requesting Department”). OSPS and the Requesting Department seek quotations (also referred to as “bids” or “responses” herein) to provide the goods/services listed above. This document provides instructions and descriptions of requirements for this competitive process.

RFQ REQUIREMENTS

1. Description of Requirements

The following is a description of the goods and/or services sought by the State of Maine under this RFQ.

· Please see Appendix B on page 11

2. Bid Contents Requirements

In addition to the cost, delivery, and other information required in VSS, all bids should contain the following information as attachments, in the Appendices listed below:

· Quote on Company Letterhead: This document will be used to evaluate your bid. Please make sure it contains the make, model and model year.

· Product Data/Information Sheets: PDF literature from the manufacture for all the items bid. Literature must include documentation that the items bid meet or exceed the posted specifications.

· Warranty Information

· Appendix A: Bid Cover Page and Debarment Form

· Appendix D: MaineDOT Certifications. NOTE: ALL Pages of this Appendix must be attached

· Appendix E: MaineDOT Terms and Conditions. NOTE: ALL Pages of this Appendix must be attached

3. Submitting a Quotation

a. Quotations Due: Quotations must be received no later than 4:00 p.m. Eastern Standard Time (EST), on the date listed in VSS. Quotations received after the 4:00 p.m. deadline will not be accepted.

b. Submission Instructions: Bidders must submit their bids in the State of Maine’s electronic procurement system: Advantage “Vendor Self Service” (VSS). More information on this system can be found at the following internet link: https://www.maine.gov/dafs/bbm/procurementservices/vendors/vendor-self-service-system

c. Multiple Quotations: Unless specifically prohibited in Section 1 of this RFQ, Bidders are permitted to submit multiple quotations for this RFQ, offering alternative items or pricing for the State of Maine to consider in its best value determination.

d. Withdrawal of a Quotation: Bidders are permitted to withdraw their own quotations up until the due date and time for receipt of quotations. To do so, a Bidder must enter the VSS system (as referenced above), identify and open their submitted quotation located in the Solicitation Responses tab, and click the “Withdraw” button found at the bottom of the screen. Quotations cannot be withdrawn after the due date and time for receipt of quotations.

e. Attachments: Any attachments provided with the Advantage VSS bid submission must be in MS Word, MS Excel, or Adobe (.pdf) format, unless otherwise specified in Section 1 of this RFQ. Vendors are encouraged to submit supporting documentation that aid the requesting department in understanding how the bid conforms to the requirements. The VSS attachment file size limit is 2Mb. Please contact the buyer for this RFQ if you must submit attachment files larger than this.

f. Vendor specifications: Unless otherwise stated in this RFQ document, limited specification information will be required upon submission of a bid in response to this RFQ. However, a Bidder’s response should include an affirmative statement that their bid complies with all requirements of this RFQ, unless the Bidder specifically addresses how its bid differs from the specifications, and why the differences should be deemed acceptable by the State.

4. General Instructions

a. The Bidder must submit a cost quotation response that covers the goods and term of the contract, including any optional renewal.

b. The cost quotation shall include the costs necessary for the Bidder to fully comply with the contract terms and conditions and RFQ requirements.

c. Failure to provide the requested information may result in the exclusion of the quotation from consideration, at the discretion of OSPS.

d. No costs related to the preparation of the quotation for this RFQ or to the negotiation of the contract with the Department may be included in the quotation.

e. The State is exempt from the payment of Federal, State and local Taxes on articles not for resale. Please provide quotations that do not include these taxes. Upon application, an exemption certificate can be furnished by the State at the point of contract finalization.

5. Quotation Evaluation and Selection

Evaluation of the submitted quotations shall be accomplished as detailed below:

a. State of Maine RFQ documents are evaluated on a Best Value basis. The term “Best Value” may take into consideration the qualities of the goods or services to be supplied, their conformity with the specifications listed in the RFQ, the purposes for which they are required, the date of delivery, and the best interest of the State. Once the goods or services have been determined to conform to the specifications then OSPS will make its award decision based on the lowest price among the Bidders. Delivery days can be a factor in awarding.

b. The State reserves the right to not make an award to the lowest price bidder when that bidder has had documented poor performance, and/or a contract terminated or not renewed within the last five years.

c. At the discretion of OSPS, if a Bidder’s submission is deemed to not conform to the specifications listed in the RFQ, or otherwise not conform to the requirements of the RFQ, then that Bidder’s submission may not be considered for contract award.

d. In the event that no Bidder submission conforms to the specifications of this RFQ, then OSPS may choose not to make any award. Alternatively, OSPS may make an award to the Best Value Bidder whose specifications most closely meet the specifications of this RFQ. For example, if there are five specification requirements, and two responses are received with one Bidder meeting four requirements, and one bidder meeting three requirements, then OSPS, at its discretion, may make a contract award to the Bidder meeting four requirements.

e. If the specifications provided with this RFQ are of a technical nature, then OSPS’s RFQ Coordinator, at his or her discretion, may seek to use an evaluation team comprised of subject matter experts, end-users from the Requesting Department, or other State Department representatives. In such a case, the evaluation team will judge the merits of the quotations received in accordance with the best value criteria defined in the RFQ.

6. Negotiations

a. No Best and Final Offers: The State of Maine will not seek a best and final offer (BAFO) from any Bidder in this procurement process. All Bidders are expected to provide their Best Value pricing with the submission of their quotation.

b. OSPS reserves the right to negotiate with the successful Bidder to finalize a contract at the same rate or cost of goods and services as presented in the selected quotation. Such negotiations may not significantly vary the content, nature or requirements of the quotation or the RFQ to an extent that may affect the price of goods or services requested. OSPS reserves the right to terminate contract negotiations with a selected Bidder who submits a proposed contract significantly different from the quotation submitted in response to the RFQ.

c. In the event that an acceptable contract cannot be negotiated with the highest ranked Bidder, OSPS may withdraw its award and negotiate with the next-highest ranked Bidder, and so on, until an acceptable contract has been finalized. Alternatively, OSPS may cancel the RFQ, at its sole discretion.

TERMS AND CONDITIONS FOR RFQ AND CONTRACT

PART I GENERAL INFORMATION ON RFQs

A. Purpose and Background

The State of Maine (“State”) Department of Administrative and Financial Services (“Department”), Office of State Procurement Services (“OSPS”) acts as the purchasing agent on behalf of all Executive Departments and other agencies within State Government. For this competitive Request for Quotations (RFQ) process, OSPS is acting on behalf of the Requesting Department listed on the cover page. OSPS and the Requesting Department seek quotations (also referred to as “bids” or “responses” herein) to provide the goods/services as defined above in Section 1 of this document. This document provides instructions for submitting quotations, the procedure and criteria by which the Bidder(s) will be selected, and the contractual terms which will govern the relationship between the State and the awarded Bidder(s). Following Bidder selection and upon reaching a mutual agreement, the State and the selected Bidder will enter into a contract – taking the form of a State of Maine Master Agreement or Buyer Purchase Order (all generally referred to as “contract” herein), as applicable.

B. General Provisions

1.Issuance of this RFQ does not commit OSPS or the Requesting Department to issue an award or to pay expenses incurred by a Bidder in the preparation of a response to this RFQ. This includes attendance at personal interviews or other meetings and software or system demonstrations, where applicable.
2.All responses to this RFQ should adhere to the instructions and format requirements outlined in this RFQ and all written supplements and amendments (such as OSPS’s answers to the Bidders’ questions submitted through the VSS), as issued by OSPS. Responses are to follow the format and respond to all questions and instructions specified above in the “Submitting a Quotation” section of this RFQ.
3.Bidders shall take careful note that in evaluating a quotation submitted in response to this RFQ, the Department may consider materials provided in the quotation, information obtained through interviews/presentations (if any), and internal information of previous contract history between OSPS and the Bidder (if any). OSPS also reserves the right to consider other reliable references and publicly available information available in evaluating a Bidder’s experience and capabilities, if needed. All responses to this RFQ shall be considered to be authorized to legally bind the Bidder, and if selected for award, shall contain or be considered to contain a statement that the quotation and the pricing contained therein will remain valid and binding for a period of at least 180 days from the date and time of the bid opening.
4.The RFQ and the selected Bidder’s quotation, including all appendices or attachments, may be incorporated in the final contract.
5.Following announcement of an award decision, all submissions in response to this RFQ will be considered public records available for public inspection pursuant to the State of Maine Freedom of Access Act (FOAA) (1 M.R.S. §§ 401 et seq.).

http://www.mainelegislature.org/legis/statutes/1/title1sec401.html

6.OSPS, at its sole discretion, reserves the right to recognize and waive minor informalities and irregularities found in quotations received in response to this RFQ.
7.OSPS reserves the right to authorize other State Departments to use the contract(s) resulting from this RFQ, if it is deemed to be beneficial for the State to do so.
8.All applicable laws, whether or not herein contained, shall be included by this reference. It shall be Bidder’s responsibility to determine the applicability and requirements of any such laws and to abide by them.

C. Eligibility to Submit Bids

Public agencies, private for-profit companies, and non-profit companies and institutions are invited to submit bids in response to State of Maine Requests for Quotations.

D. Delivery Terms

For the purchase of goods, OSPS and selected Bidder will decide upon a delivery date in accordance with the State’s requirements and the terms offered in the Bidder’s quotation. Unless stated otherwise in Section 1 of this RFQ, all deliveries are expected with shipping terms of “Free on Board (FOB) – Destination”. The State intends for this to mean that all goods shall be priced in the bid response to include shipping charges, if any, to the State’s desired location. The “FOB – Destination” shipping term is also intended to mean that the State shall not bear any responsibility for the goods in question until the State takes possession of them at the destination point of delivery.

E. Alternate Bids and Approved Equals

When, in bid forms and specifications, an article or material is identified by using a trade name and catalog number of a manufacturer or vendor, the term “or approved equal,” if not inserted with the identification, is implied. Any Bidder that seeks to propose an alternate item from what is specified in this RFQ should refer to State of Maine Statute 5 MRSA §1825-B, for “Bids, awards and contracts”, found here: http://www.mainelegislature.org/legis/statutes/5/title5sec1825-B.html

F. Appeal of Contract Awards

Any person aggrieved by the award decision that results from this RFQ may appeal the decision to the Director of the Bureau of General Services in the manner prescribed in 5 MRSA § 1825-E and 18-554 Code of Maine Rules, Chapter 120 (found here: Chapter 120). The appeal must be in writing and filed with the Director of the Bureau of General Services, 9 State House Station, Augusta, Maine, 04333-0009 within 15 calendar days of receipt of notification of contract award.

If this RFQ results in the creation of a pre-qualified or pre-approved list of vendors, then the appeal procedures mentioned above are available upon the original determination of that vendor list, but not during subsequent competitive procedures involving only the pre-qualified or pre-approved list participants.

PART II CONTRACT ADMINISTRATION AND CONDITIONS

A. Contract Document

The successful Bidder will be required to execute a contract in the form of a State of Maine Buyer Purchase Order, Contract Agreement to Purchase Services or State of Maine Master Agreement.

The Terms and Conditions used with the aforementioned contract types may be found on the Office of State Procurement Services’ website at the following links:

BPO and MA Terms and Conditions Service Contract Terms and Conditions IT Service Contract Terms and Conditions

In the event that the State of Maine’s Standard Terms and Conditions or RFQ provisions do not otherwise cover contractual scenarios that are specific to the goods or services being purchased under this RFQ, then the State is willing to consider a Bidder’s standard terms and conditions. Consideration or use of a Bidder’s standard terms and conditions shall only occur under the general agreement that in the event of a conflict, the State of Maine’s Standard Terms and Conditions and RFQ provisions shall take precedence.

Other forms and contract documents commonly used by the State can be found on the Office of State Procurement Services’ website at the following link: https://www.maine.gov/dafs/bbm/procurementservices/forms

B. Independent Capacity

In providing services and performing under the contract, the successful Bidder shall act independently and not as an agent of the State of Maine.

C. Payments and Other Provisions

The State anticipates paying the selected Bidder for goods and services received, on the basis of net 30 payment terms, upon the receipt of an accurate and acceptable invoice. An invoice will be considered accurate and acceptable if it contains a reference to the State of Maine contract number, contains correct pricing information relative to the contract, and provides any required supporting documents, as applicable, and any other specific and agreed-upon requirements listed within the contract that results from this RFQ.

The State of Maine reserves the right to pay for goods purchased through this solicitation by any of several available means, which include but may not be limited to check, EFT, and/or procurement card. Bidders are advised that state statute precludes sellers from imposing a surcharge on credit or debit card purchases (text follows):

“9-A MRSA §8-509 (1): A seller in a sales transaction may not impose a surcharge on a cardholder who elects to use a credit card or debit card in lieu of payment by cash, check or similar means.”

Appendix A

STATE OF MAINE

DEPARTMENT OF ADMINISTRATIVE AND FINANCIAL SERVICES

OFFICE OF STATE PROCUREMENT SERVICES

RFQ # 17D 241104-106

Trailer Mounted Boring and Subsurface Exploration Drill Machine

BID COVER PAGE and DEBARMENT FORM

Bidder’s Organization Name:

Chief Executive - Name/Title:

Tel:
Cell:
E-mail:

Headquarters Street Address:

Headquarters City/State/Zip:

(provide information requested below if different from above)

Lead Point of Contact for Bid - Name/Title:

Tel:
Cell:
E-mail:

Street Address:

City/State/Zip:

By signing below Bidder affirms:

· Their bid complies with all requirements of this RFQ;

· This bid and the pricing structure contained herein will remain firm for a period of 180 days from the date and time of the bid opening;

· That no personnel currently employed by the Department or any other State agency participated, either directly or indirectly, in any activities relating to the preparation of the Bidder’s proposal;

· That no attempt has been made or will be made by the Bidder to induce any other person or firm to submit or not to submit a proposal; and

· The undersigned is authorized to enter into contractual obligations on behalf of the above-named organization.

Name:

Title:

Authorized Signature:

Date:

State of Maine RFQ# RFQ 17D 241104-106 Rev. 9/12/2024 Debarment, Performance, and Non-Collusion Certification

By signing this document, I certify to the best of my knowledge and belief that the aforementioned organization, its principals, and any subcontractors named in this proposal:

1. Are not presently debarred, suspended, proposed for debarment, and declared ineligible or voluntarily excluded from bidding or working on contracts issued by any governmental agency.

1. Have not within three years of submitting the proposal for this contract been convicted of or had a civil judgment rendered against them for:

0. fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a federal, state or local government transaction or contract.

0. violating Federal or State antitrust statutes or committing embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property;

0. are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or Local) with commission of any of the offenses enumerated in paragraph (b) of this certification; and

0. have not within a three (3) year period preceding this proposal had one or more federal, state or local government transactions terminated for cause or default.

1. Have not entered into a prior understanding, agreement, or connection with any corporation, firm, or person submitting a response for the same materials, supplies, equipment, or services and this proposal is in all respects fair and without collusion or fraud. The above-mentioned entities understand and agree that collusive bidding is a violation of state and federal law and can result in fines, prison sentences, and civil damage awards.

· Failure to provide this certification may result in the disqualification of the Bidder’s proposal, at the discretion of the Department.

To the best of my knowledge all information provided in the enclosed proposal, both programmatic and financial, is complete and accurate at the time of submission.

Name:

Title:

Authorized Signature:

Date:

Appendix B

DEPARTMENT OF ADMINISTRATIVE AND FINANCIAL SERVICES

OFFICE OF STATE PROCUREMENT SERVICES

DETAILED SPECIFICATIONS

Prices: Bid Price must be with shipping terms of “Free on Board (FOB) – Destination”. The State intends for this to mean that all goods shall be priced in the bid response to include shipping charges, if any, to the State’s desired location. The “FOB – Destination” shipping term is also intended to mean that the State shall not bear any responsibility for the goods in question until the State takes possession of them at the destination point of delivery.

Quantity: The expected purchase quantity is one (1) unit. There is no guaranteed award associated with this bid opportunity. All purchases will depend on the bid results and departmental budget. The State of Maine reserves the right to negotiate the purchase of additional units at the bid price for six months after the award is officially made.

Delivery Location: MaineDOT Fleet Services, 66 Industrial Drive, Augusta ME

Delivery and Inspection: The requested items will be inspected after delivery. If shipment is deemed unacceptable the delivery will be refused and will be returned at the risk and expense of the selling vendor.

Delivery Date: This item is needed immediately, delivery date After Receipt of Order (ARO) may be factored into the bid award decision.

Intent: The purpose and intent of these minimum specifications is to describe a One relatively lightweight combination auger, core, rotary type boring machine. The drill shall be mounted on a trailer that can be towed by a heavy-duty pickup truck. It must be of heavy-duty design to deliver dependable service under severe operating conditions. Unit bid shall be currently produced with all the latest standard features whether or not called for in these specifications.

Purpose: This equipment shall be used for soil sampling, foundation testing, monitoring well installation and subsurface exploration work. The drill machine shall be capable of performing auger borings in unconsolidated formations with hollow-stem augers. The drill shall have the capability of productively using currently popular geo-exploration methods and techniques that include shelby tube or continuous tube sampling and standard penetration testing. The drill shall be capable of coring or rotary drilling applications.

Completeness: The price quoted in any proposal submitted shall include all items of labor, materials, and other costs necessary to fully complete the manufacture and delivery of the Sub-surface Exploration Drill Machine pursuant to these specifications.

Any part or detail which makes the Sub-surface Exploration Drill Machine pursuant complete and ready for service shall not be omitted, even though such part is not mentioned in these specifications.

Conformity: All parts not specified shall be manufacturer’s best quality and shall conform in materials, design, or workmanship to the best practice known in the Sub-surface Exploration Drill Machine pursuant industry. All parts shall be new and in no case will used, reconditioned or obsolete parts be accepted. The parts on the Sub-surface Exploration Drill Machine pursuant provided by the manufacturer should be interchangeable.

INSTRUCTIONS FOR COMPLETING TECHNICAL SPECIFICATION SHEET

Please complete the checklist for technical specifications set forth below. Electronically enter responses directly into the text-enabled fields next to each specification, including actual dimensions when applicable. Each Bidder must indicate whether it can meet the technical specifications by inserting an “X” next to each specification. The “X” will demonstrate that the Bidder’s offering meets the technical specification. If a Bidder cannot meet a technical specification, then the Bidder must give an explanation for each exception and for equipment that is not available or that will be dealer installed. All explanations must be provided in detail on separate pages along with the justification as to why the alternative equipment or deliverables will be as good as the equipment or deliverables described in the detailed specifications for desired items. A copy of the vendor specification proposal must be provided. Following these instructions is essential for proper bid evaluation.

If a Bidder fails to provide requested information or if information on a quote is found to be false or misleading, the quote will be rejected as unresponsive.

The award will be made on a best value basis to the vendor that either meets or most closely meets the specifications, while taking price and delivery into consideration.

It is understood that all specifications are minimums. Equivalent bid specifications may be considered. To have an “Equivalent Bid Specification” evaluated, the bidder must provide specifications and details for all specifications bid as “Equivalent Bid Specification.” Bids missing this information may be rejected.

The following abbreviations must be used:
X
Standard or as specified
N/A
Not Available
DI
Dealer Installed
EQ
Equivalent Bid Specification
1.0 General Specifications
Abbreviation
Actual Dimension
Notes
1.1
The drill shall be a self-contained unit having a single engine power source.
1.2
The power shall be appropriately directed to the hydraulic system and mechanically driven drill head.
1.3
A hydraulically actuated folding upright drill frame with twin hydraulic feed cylinders shall be supplied.
1.4
The assembled drill with its complement of auxiliary equipment shall be so arranged that work may be carried on with optimum efficiency and a minimum of manual labor.
1.5
All parts, materials and workmanship shall be of the highest quality recognized by the trade.
1.6
The drill unit shall be thoroughly field tested and ready for immediate and continuous operation at time of delivery.
1.7
The equipment proposed must be a current model under standard production, being produced in quantity for national distribution.
1.8
The manufacturer must have a minimum of three years’ production experience designing and manufacturing this type of equipment.
1.9
The drill shall have been in production for at least two years.
1.10
Dealer or vendor modifications to a non-conforming model for the express purpose of meeting minimum specification requirements will not be acceptable.
1.11
Parts and accessories shall be stocked and readily available from the successful vendor.
1.12
The drill unit shall be furnished with all standard equipment advertised whether or not specifically called for here, except where optional or conflicting equipment is specified. The drill shall meet the following specifications.
2.0 ROTARY DRIVE
Abbreviation
Actual Dimension
Notes
2.1
The drill transmission shall have at least four speeds forward and one speed reverse.
2.2
The transmission shall be mounted stationary on the drill main base frame with a heavy-duty clutch immediately adjacent to the transmission power input.
2.3
The maximum drill spindle torque shall exceed 3,530 foot-pounds in first gear.
2.4
Rotational speeds of the drill spindle shall range from at least 120 RPM in first gear to more than 760 RPM in fourth gear at 2,500 engine RPM.
2.5
The output of the transmission shall power a single speed right angle drive.
2.6
The right-angle drive output shall turn a drive shaft connected to the rotary box.
2.7
The rotary box shall be stationary with respect to the drive head travel.
2.8
The rotary box shall be grease packed and not run in oil.
2.9
The minimum rotary box chain size shall be double 80 series.
2.10
The rotary box shall turn a rotary drive bar that has a square cross section of at least 1.75 inches a side and shall be made of heat-treated alloy steel.
2.11
The drill shall be equipped with a heavy-duty auger drive universal joint and 1-5/8-inch hexagon drive socket.
3.0 VERTICAL DRIVE
Abbreviation
Actual Dimension
Notes
3.1
The vertical drive shall consist of two double-acting hydraulic feed cylinders with an overall stroke or travel of at least 68 inches.
3.2
The feed cylinders shall have a point of thrust centered upon the axis of the drill spindle.
3.3
The vertical drive shall have a maximum downward thrust of not less than 13,650 pounds and an upward or retract force of not less than 19,600 pounds.
3.4
The feed cylinders shall have a minimum piston rod diameter of 1.375 inches to withstand compressive forces when retracting augers from the ground without rotation
3.5
Hydraulic gauges shall be provided on the control panel at the left rear of the drill to indicate in pounds per square inch the hydraulic feed pressure and system pressure.
3.6
Hydraulic controls shall be furnished for varying the feed rate and down pressure.
3.7
The maximum rate of feed shall not be less than 79 feet per minute down and 55 feet per minute up.
3.8
Two feed levers shall be provided. One feed lever shall be of the spring return type permitting standard rates of feed and retract.

1. The first feed lever shall not be affected by the dial control settings used with the second feed lever.

2. The second feed lever shall have a detent position and be used for drilling when a controlled rate of feed is required.

3.9
A feed rate control shall be furnished for changing the rate of feed
3.10
Feed rate, once set, shall not be affected by changes in engine RPM nor by changes in formation resistance unless the adjusted pressure setting is reached.
3.11
A pressure control shall be furnished for changing the maximum bit pressure.
3.12
The feed rate and pressure controls shall be operated by rotary type valves located on the front of the control panel within easy reach of the operator.
4.0 DRILL POWER UNIT
Abbreviation
Actual Dimension
Notes
4.1
The power unit shall be a self-contained electric starting, liquid-cooled, heavy-duty turbocharged 4-cylinder industrial type diesel engine, having not less than 171 cubic inch displacement and a minimum 65 gross intermittent horsepower. The engine shall meet U.S. EPA Tier 4 final emission certification.
4.2
The unit shall be equipped with a heavy-duty two-stage replaceable element air cleaner, electronic governor and a replaceable full flow oil filter.
4.3
The unit shall have a 12-volt electric starting system consisting of a starter, alternator, battery as well as cold weather starting aid and engine protection shutdown systems.
4.1
The unit shall have a keyed ignition switch on the drill control panel and an electrically controlled engine throttle.
4.2
The power unit shall be equipped with a dry disc clutch not less than 11 inches in diameter and a transmission having not less than four speeds forward and one reverse.

When coupled with the drill unit, the engine shall have sufficient power to meet all requirements listed elsewhere in this specification.

The fuel tank shall have a capacity of not less than 12 gallons and shall have level indicator sights.

5.0 UPRIGHT DRILL FRAME WITH PERMANENTLY COUPLED DRIVELIN
Abbreviation
Actual Dimension
Notes
5.1
The upright drill frame shall be hydraulically actuated permitting 90-degree fold over for traveling.
5.2
The depth of the upright part of the base frame shall be at least 8 inches for rigidity.
5.3
Two 2.5-inch ID double-acting hydraulic cylinders that have a minimum of 1.375-inch diameter rods shall control the drill frame movement.
5.1
The direct-coupled mechanical drive train to the rotary shall not have to be disconnected when folding the upright drill frame over to a horizontal travel position.
6.0 HYDRAULIC SYSTEM
Abbreviation
Actual Dimension
Notes
6.1
This system shall have a heavy-duty engine driven hydraulic pump run independently of the gear train with a capacity of not less than 24.9 GPM at 2,000 PSI.

· The hydraulic pump shall be driven from a point in the line of power transmission so that hydraulic power will be available whenever the engine is running. Biodegradable hydraulic fluid (Chevron Clarity or equal) shall be used.

6.2
The system shall be equipped with a full-flow replaceable element hydraulic oil filter in the low pressure return line.
6.3
A hydraulic oil cooler shall be furnished.
6.1
The hydraulic oil reservoir shall have adequate capacity and shall be equipped with

· level indicator sight eyes,

· A vented filler cap

· a magnetic drain plug

6.1
The hydraulic pump shall be driven from a point in the line of power transmission so that hydraulic power will be available whenever the engine is running.

· Biodegradable hydraulic fluid (Chevron Clarity or equal) shall be used.

7.0 DRILLER CONTROL PANEL
Abbreviation
Actual Dimension
Notes
7.1
All controls and gauges needed for the various drilling operations shall be placed in such a manner as to be easily accessible and convenient for the drill operator while permitting a view of the drilling operation at all times. The driller's control panel shall be mounted on the left rear of the drill and shall include the following instrumentation and controls:

· Keyed ignition switch and starter switch.

· Push-button emergency engine shut-off switch.

· Electric engine throttle switch.

· Transmission gear selector, lock-out clutch handle and auxiliary spindle brake set valve.

· Engine ECM diagnostic module to monitor engine parameters (engine speed, oil pressure, coolant temperature, system voltage, machine hours). Diagnostic module shall be in a sealed enclosure with locking cover.

· Hydraulic gauges for systems pressure and pull-down pressure.

· Feed rate, feed pull-down pressure controls.

· Feed and detented feed levers.

· Hydraulic controls for all standard and provided optional components.

7.1
The drill controls shall be arranged in groups and situated for convenience according to frequency of use.

· For safety and convenience, the hydraulic levers shall have directional control that corresponds with cylinder movement. For example, moving the feed lever up shall extend the feed cylinders.

8.0 SAFETY AND EMERGENCY SHUT-DOWN SYSTEM
Abbreviation
Actual Dimension
Notes
8.1
Push-button emergency shut-off switches shall be located on the control panel and on the right side of the main drill frame.

· A neutral start switch is to be included that only allows the engine to start when the clutch is disengaged.

8.2
Two emergency multi-directional wobble shut-off switches with extended levers shall be located near the bottom of and parallel to the feed cylinders
8.3
One emergency multi-directional wobble shut-off switch shall be located above and parallel to the axis of the cathead. When any emergency shut-off switch is activated, a drive line brake is engaged to stop the spindle rotation in less than one revolution, the clutch is released, the cathead rotation instantly stops, and the engine is shut down.
8.4
The system shall also include a lock-out type clutch handle that positively locks the clutch handle in the down or disengaged position and an auxiliary spindle brake set valve.
8.5
A mast-raising alarm shall be included to alert the drill crew to look for overhead obstructions.
9.0 MAST
Abbreviation
Actual Dimension
Notes
9.1
The mast shall be secured by bolts to the upright drill frame and shall be removable from the drill when not needed.
9.2
With the mast in a vertical position, the sheaves shall be not less than 15 feet from the base of the drill main frame.
9.3
The maximum line pull of the draw works shall be evenly distributed on four cross-braced tubular members with an adequate margin of safety
9.4
Pairs of 8-inch diameter sheaves shall be aligned with the rope or wire rope they carry.
9.5.
Two hydraulic cylinders shall be provided to raise and lower the upright drill frame and mast.
10.0 DRAW WORKS
Abbreviation
Actual Dimension
Notes
10.1
The draw works shall include:

· a cathead,

· two hydraulic hoists

· a hydraulic wireline hoist.

10.2
The cathead shall be hydraulically powered and have a pulling capacity of not less than 1,370 pounds.

B. The cathead shall be located at the right rear corner of the drill at right angles to the long axis of the drill frame.

C. The diameter of the drum shall be 8 inches and the length 7.5 inches.

D. Maximum peripheral speed shall not be less than 710 feet per minute.

10.3
The first hydraulic hoist shall have a maximum pulling capacity of not less than 3,200 pounds. The maximum line speed shall be not less than 100 feet per minute.

D. One hydraulic lever shall be furnished for controlling hoisting or lowering and rotation speed.

E. The hoist shall include 3/8-inch diameter wire rope and a safety Shur-Lok hook.

10.4
The second hydraulic hoist shall have a maximum pulling capacity of not less than 1,800 pounds. Maximum line speed shall be not less than 200 feet per minute.

· One hydraulic lever shall be furnished for controlling hoisting or lowering and rotation speed.

· The hoist shall include 3/8 inch diameter wire rope and a safety Shur-Lok hook.

10.5
The hydraulic wireline hoist shall have a maximum pulling capacity of not less than 1800 pounds. Maximum line speed shall be not less than 200 feet per minute.

· One hydraulic lever shall be furnished for controlling hoisting or lowering and rotation speed.

· The hoist shall be capable of holding up to 900 feet of 3/16 inch diameter wireline cable; 300 feet of wireline cable shall be included.

11.0 SLIDING BASE, IN-OUT
Abbreviation
Actual Dimension
Notes
11.1
A sliding base shall be furnished for moving the drill in and out so that the drill spindle can be positioned to facilitate alignment of augers and drill rods and to provide clearance from the hole for handling augers, casing and other down-hole tools. With the slide base extended, the center of the auger drive shall be at least 15 inches from the rear of the trailer to provide ample working room.
11.2
The in-out slide base shall have at least 15 inches of travel and shall be hydraulically operated.
11.3
The in-out slide base shall have a replaceable nylatron (or approved equal) wear plate between the metal slide surfaces.
12.0 SLIDING BASE, SIDEWAYS
Abbreviation
Actual Dimension
Notes
12.1
A sliding base shall be furnished for moving the drill to either side so that the drill spindle can be positioned to facilitate alignment of augers and drill rods when starting or drilling a hole.

1. The sideways slide base shall have at least 8 inches of travel and shall be hydraulically operated.

1. The sideways slide base shall have nylatron (or approved equal) wear plate between the metal slide surface.

13.0 MUD PUMP ASSEMBLY:
Abbreviation
Actual Dimension
Notes
13.1
The mud or water pump shall be a progressive cavity type pump (Moyno 3L6 or equal) and shall have an infinitely adjustable output of 0 to 36 gallons per minute and a maximum pressure of 225 PSI..
13.2
Pump output shall not be affected by changes in engine RPM.
13.3
Power for the mud pump shall be supplied by a hydraulic motor operated from the drill hydraulic system. The assembly shall include:

· pressure gauge,

· 1-1/2-inch pressure port with sufficient1-1/2-inch-high pressure hose to connect to the control panel

· a 2-inch suction port.

· Provisions shall be made for drainage of the mud pump and lines

14.0 WATER SWIVEL
Abbreviation
Actual Dimension
Notes
14.1
A side-feed type water swivel shall be provided having 1-5/8-inch hex connection on top and AW drill rod box connection on bottom.
14.2
A means for stabilizing the water swivel body shall be provided to minimize water hose movement during rotation.
14.3
No plumbing or hose will be provided from the control panel standpipe to the water swivel.
15.0 HYDRAULIC HAMMER
Abbreviation
Actual Dimension
Notes
15.1
A hydraulic hammer system shall be furnished that will lift a 140-pound drive weight and completely release the weight for a 30-inch free fall.

· No rope or cable shall be attached to the weight that might impede free fall.

· The system shall have a minimum rate of at least 50 blows per minute.

· The hammer shall be preset at the factory for a consistent weight fall height through the use of adjustable priority hydraulic control valves.

· Once the valves are set, the fall height of the hammer weight shall not be affected by engine throttle adjustments.

· The fall height shall have a tolerance of plus or minus 1/2 inch.

· A method for visual verification of the fall height of the weight while the hammer is in operation shall be provided.

· The hammer shall be mounted on one single-acting hydraulic cylinder which is dedicated to the operation of the hammer device and shall be attached to the upright drill frame opposite of the control panel.

· The hammer device shall be hydraulically raised or lowered by this hydraulic cylinder through 60 inches of vertical travel.

· A 140-pound drive weight shall be furnished. A safety feature shall be furnished that will prevent the hammer from operating if the anvil is not in place.

16.0 HYDRAULIC ROD HOLDER AND BREAKOUT DEVICE
Abbreviation
Actual Dimension
Notes
16.1
· A hydraulic rod holder having two opposed hydraulic cylinders that clamp up to 4.5-inch OD drill rod or pipe between two replaceable jaws shall be furnished.

· These jaws shall have a minimum of 3.75 inches of vertical height engagement evenly distributed over a minimum of 45 percent of the drill rod circumference.

· The device shall swing on and off the hole from a pivot point near the right rear leveling jack and shall hydraulically move in and out.

· The hydraulic extension or retraction of the rod holder shall permit centering of the rod holder jaws on tools that are aligned with the vertical axis of the drill spindle.

· The rod holder shall store flush with the rear of the trailer and out of the way when drilling with auger tools.

· The rod holder shall be capable of pivoting away from the carrier so that the jaws are a minimum of 55 inches from the platform.

· A hydraulic breakout wrench shall be mounted on the rod holder. Three sets of drill rod jaws shall be supplied.

17.0 HYDRAULIC LEVELING JACKS:
Abbreviation
Actual Dimension
Notes
17.1
Heavy-duty hydraulic leveling jacks shall be furnished that are operated from the control panel at the left rear of the drill.

· The jacks shall provide adequate leveling capability and shall be strong and rigid enough to easily support the total weight of the machine plus the loads generated when retracting drilling tools. Check valves shall be furnished in the hydraulic lines to prevent leakage or slippage of the jacks while the drill is set up on a site.

· The chrome-plated jack piston rods shall be completely enclosed to safeguard them from damage.

17.2
Two jacks shall be mounted at the rear of the platform, one on each corner.

· The maximum cylinder travel shall not be less than 36 inches.

· The minimum outside diameter of the jack cylinders shall be 4.5 inches with a 4 inch bore and 2.5-inch diameter piston rod.

· Rear jacks shall have independent control valves.

17.3
Two jacks shall be mounted at the front of the trailer.

· The maximum cylinder travel shall not be less than 36 inches.

· The minimum outside diameter of the jack cylinders shall be 4.5 inches with a 4 inch bore and 2.5-inch diameter piston rod.

· Front jacks shall be controlled by a single valve

18.0 TRAILER ASSEMBLY
Abbreviation
Actual Dimension
Notes
18.1
The trailer shall be constructed of steel box tubing and 12-gauge safety tread plate.

· Watertight toolboxes with a single shelf and locking hasp shall be located on both sides of the trailer.

· A license plate bracket, folding driller’s step plus auger and drill rod racks shall be supplied.

18.2
The trailer shall have:

· two axles rated at 8,000 pounds each four 245/70R17.5 (H) tires and a 16,000-pound capacity.

· Breaks shall be electric type. LED Stop, turn signals, running, and license plate lights meeting DOT requirements shall be provided.

· The trailer shall be undercoated and equipped with an extended tongue and pintle hook hitch that is adjustable from 18-25 inches.

· One spare tire and wheel shall be supplied loose, not mounted.

19.0 COLOR
Abbreviation
Actual Dimension
Notes
19.1
The drill unit, trailer and all parts normally painted shall be primed and painted a color complying with specifications. A color sample shall be furnished to the successful bidder.
19.2
All exposed hydraulic cylinder piston rods shall be covered to prevent over spray during painting.
20.0 MISCELLANEOUS
Abbreviation
Actual Dimension
Notes

20.1 All equipment cataloged as standards shall be furnished and shall be included in the purchase price of the unit.

· The component parts of the unit shall be of proper size and design to safely withstand maximum stress imposed by a capacity load, and the manufacturer's rated loads for chains, bearings and universal joints shall not be exceeded when the unit is loaded with such loads.

· The torque capacity of each driven part shall be equal to or exceed the torque capacity of its driving member.

7. This machine is to be delivered in first-class operating conditions with acceptance subject to inspection and approval. The successful bidder, at a time designated, shall provide two days of training to familiarize personnel with the correct operation and servicing procedures for the equipment delivered.

8. No deviations from the specifications will be accepted.

9. All items which require periodic lubrication shall be provided with a suitable lubrication fitting.

10. All pressure systems shall be provided with suitable pressure relief valves. With the exception of the drill rotary box, cathead, spindle and drilling tools, all moving parts which are so located as to be a hazard to operating or maintenance personnel shall be fully enclosed or properly guarded. Protective devices shall not impair the operating functions.

11. The equipment to be furnished under these specifications shall be warranted against defective design, materials and workmanship as standard with the manufacturer.

21.0 MANUALS & SOFTWARE
Abbreviation
Actual Dimension
Notes
21.1
There shall be two (2) operators manuals per unit.
21.2
There shall be two (2) shop repair manuals or thumb drives.
21.3
There shall be two (2) parts manuals or thumb drives.
21.4
There shall be two (2) Engine shop manuals or thumb drives.
22.0 PAINT
Abbreviation
Actual Dimension
Notes
22.2
All metal shall be free of rust and mill scale and prepared for primer and finish paint coat.
22.3
All paint and primers must be lead-free.
23.0 TRAINING
Abbreviation
Actual Dimension
Notes
23.1
Vendor may be asked to provide training at a later date, but within eight (8) weeks of delivery.
23.3
Any and all training shall be performed by a factory certified trainer.
23.4
All manufacture training programs being offered need to be defined in detail and a written proposal of what those programs will entail and submitted with bid packet. Include Cost Details with bid.
24.0 WARRANTY
Abbreviation
Actual Dimension
Notes
24.1
Manufacturer’s standard warranty shall apply.
24.2
Terms and conditions of warranty shall be provided with a bid proposal, (Warranty must be clearly defined and all components covered shall be clearly listed and identified).
24.3
The manufacturer’s warranty will start with MaineDOT in-service date.
24.4
In-Service Date: Warranty on Sub-surface Exploration Drill Machine (not placed in service immediately because of time lag due to installation of components, special equipment, seasonal usage, or other delays) shall be warranted from the date the units are actually placed in service. MaineDOT Fleet Services Augusta shall notify the vendor in writing of “in-service” date.
24.5
During the term of the manufacturer’s warranty Fleet Services reserves the right to perform any and or all warranty “in house” work to meet operational needs or demands with the pre-authorization of the vendor. Fleet Services will recover all parts and labor costs as allowed by manufacturer’s flat rate manual. O.E.M. parts may be supplied at no cost by the manufacturer, and or dealer, or may be purchased by Fleet Services on the open market to meet operational demands. Any and all defective parts shall be returned to the manufacturer or dealer upon request.
24.6
Vendor shall be 100% responsible for all repair costs to include parts, and labor during the warranty period.
25.0 GENERAL
Abbreviation
Actual Dimension
Notes
25.1
All pinch points and danger areas shall be clearly marked.
25.2
Two (2) sets of keys shall be furnished with each unit.
25.3
Successful bidder shall provide Sub-surface Exploration Drill Machine line sheets
25.4
Equipment shall be fully inspected, serviced, fully assembled, and ready to operate upon delivery.`
25.5
Be it known that these specifications are a minimum and that the bid will be evaluated based on price, warranty, manufacturer’s performance data, delivery schedule, parts availability, and other items deemed appropriate.
25.6
Bidders shall supply a detailed specification sheet with their proposals listing exactly what is being offered (not a reference to a web site) and to certify that they have service facilities in Maine, staffed with trained service technicians, and stocked with repair parts for the equipment which is being bid on. Failure to provide this information may cause the bid to be rejected. MaineDOT reserves the right to reject any and or all bids.
25.7
All hardware installed shall not obstruct any lubrication points. In addition, all components and systems shall be easily accessible to the operator.
25.8
All hardware installed shall not obstruct or interfere with any Sub-surface Exploration Drill Machine component or system
25.9
All safety, warning, and instructional decals shall be properly displayed and appropriate for the Sub-surface Exploration Drill Machine application.
25.10

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .