This Request for Quote (RFQ) Amendment 1, issued by the Idaho Department of Labor on May 27, 2026, solicits janitorial services for the agency's Post Falls local office, a 17,837 square-foot facility located at 600 N. Thornton Street, Post Falls, Idaho 83877. The scope of work includes comprehensive janitorial services encompassing daily, weekly, monthly, bi-monthly, quarterly, and annual cleaning tasks such as vacuuming, trash removal, restroom cleaning, window cleaning, dusting, and related maintenance activities. Bidders must submit quotes via IPRO by 5:00 p.m. Mountain Time on Monday, June 8, 2026. An optional facility walkthrough is scheduled for Tuesday, June 2, 2026, from 8:30 a.m. to 9:30 a.m. Mountain Time, with RSVP required by 5:00 p.m. Mountain Time on Monday, June 1, 2026. The initial contract term is one year, with an anticipated total contract term of five years subject to mutual written agreement for renewal, extension, or amendment. Award will be made to the responsive, responsible bidder submitting the lowest one-year total cost.
Bidders must submit Submittal Form A (Background, Declarations, and Certifications), Submittal Form B (Bid Schedule), and Exhibit 8 (Reference Sheet) with a minimum of three references from companies or agencies for whom the bidder has performed similar services within the last five years. The contractor must supply all equipment, tools, materials, and supplies at its sole expense, including vacuums, mops, brooms, cleaning chemicals, and personal protective equipment; the Idaho Department of Labor will provide paper products, toilet paper, toilet seat covers, plastic bags, trash receptacles, light bulbs, and building access. All contractor personnel must be background checked and bonded prior to starting work. Services are to be performed between 5:00 p.m. and 11:00 p.m., Monday through Friday, unless otherwise approved by the agency. The contractor must submit a completed Cleaning Inspection Form monthly and invoice monthly with detailed information. Performance will be assessed beginning 30 calendar days after the contract effective date, with deficiency points assigned for incomplete duties; payment reductions of 0.5 percent of monthly compensation apply for each deficiency point exceeding ten points per week. No set-asides are identified in this procurement.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Idaho Request For Quote Amendment 1 – 5/27/2026
| RFQ Title: |
| Janitorial Services – Post Falls Local Office |
| RFQ Number: |
| 1300 |
1. Purpose: The Idaho Department of Labor (“Agency” or “IDOL”) is issuing this Request For Quote (“RFQ”) to solicit Quotes from qualified and experienced firms (“Bidders”), to provide janitorial services for its Post Falls local office, a 17,837 square foot facility located at 600 N. Thornton Street, Post Falls, Idaho 83877.
2. RFQ Lead: The individual listed below (referred to as “RFQ Lead”) is the sole point of contact for this solicitation. All questions, clarification, or other correspondence must be submitted in writing via email to the RFQ Lead. Bidders are prohibited from communicating with any State employee or Official regarding this RFQ or procurement.
| Name |
| Kevin Jarrett |
| Title & Agency |
| Purchasing Officer, Division of Purchasing |
| Phone |
| 208-332-1615 |
| Kevin.Jarrett@adm.idaho.gov |
3. Procurement Schedule: The State will make every effort to adhere to the schedule below, but reserves the right, at its sole discretion, to adjust the schedule. Quotes are due by 5:00 p.m. MT on: Monday, June 08, 2026.
Late Quotes will not be accepted or considered.
Optional Facility Walkthrough: An optional facility walkthrough is scheduled for bidders to visit the Post Falls office and review the areas requiring janitorial services. Failure to attend the optional facility walkthrough must not relieve the Bidder of meeting the requirements of this RFQ. A maximum of two (2) representatives per interested party will be allowed to attend in-person. Details are as follows:
3.1 Date and Time: Tuesday, June 2nd, 2026, from 8:30 am to 9:30 am MT PT
3.2 Location: 600 N. Thornton Street, Post Falls, Idaho 83877
3.3 Contact: Contact information will be provided upon RSVP.
3.4 RSVP: Parties interested in attending a walkthrough must notify the RFQ lead via email by 5:00 p.m. MT on Monday, June 1st.
3.5 Instructions: Official questions about the walkthrough must be submitted in writing to the RFQ Lead; verbal questions may be answered during the walkthrough but are considered unofficial and will not be included in this document.
4. Required Submittals: The Quote must be submitted in accordance with the requirements set forth in this solicitation. Any Quote that does not adhere to the requirements may be rejected. Bidders must complete and submit the following Submittal Forms:
4.1 Submittal Form A – Background, Declarations, & Certifications
4.2 Submittal Form B – Bid Schedule
4.3 Exhibit 8 – Reference Sheet
5. Submission Instructions The Quote must be submitted via IPRO (IPRO POWERED BY LUMA) prior to the deadline. Upload all required Submittal Forms (including Submittal Form A, Submittal Form B, and any other Forms listed under Required Submittals). Enter your Total Cost in IPRO.
To respond to this RFQ, the Bidder must supply with their quote the following submittal documents, which will be assessed on a pass/fail basis. Any response from a Bidder that does not include all of the required documents may not be awarded a contract.
5.1 Provide a minimum of three (3) references from companies or agencies (See Exhibit 8, Reference Sheet) for whom your company has performed services that are similar in scope and size within the last five (5) years (IDOL must not be used as a reference).
5.1.1 IDOL reserves the right to call and verify each reference that is provided.
5.1.2 Bidders unable to provide at least three (3) references will no longer be considered for award.
6. Award: Award will be made to the responsive responsible Bidder with the lowest One (1) Year Total Cost, as provided on Submittal Form B.
7. Initial Term and Contract Renewal: The initial term of this Contract will be for one (1) year. Upon mutual, written agreement, the Contract may be renewed, extended or amended. The anticipated total Contract term is five (5) years.
8. Resulting Contract: If the State awards a Contract from this solicitation, it will do so by issuing a Contract Purchasing Order (CPO) from the State’s ERP system (Luma). The State anticipates issuing a single contract from this solicitation which will include the Terms and Conditions, Scope of Work, General Requirements, Insurance Requirements, and any additional documents from the solicitation.
9. Amendments: The State reserves the right to issue amendments to make changes to this RFQ. All amendments will be communicated in writing through LUMA IPRO. Bidders must acknowledge all issued amendments, as required in Submittal Form A.
10. Authority: This procurement is conducted in accordance with IDAPA 38.05.01 and pursuant to Title 67, Chapter 92 of the Idaho Code.
Table of Contents
| Exhibit 1 - Background Information |
| Page 4 |
| Exhibit 2 – Definitions |
| Page 5 |
| Exhibit 3 – General Requirements |
| Page 6 |
| Exhibit 4 – Scope Of Work |
| Page 7 |
| Exhibit 5 – Performance Metrics |
| Page 10 |
| Exhibit 6 – Cleaning Inspection Form Template |
| Page 11 |
| Exhibit 7 – Floor Plan |
| Page 12 |
| Exhibit 8 – Reference Sheet |
| Page 13 |
| Submittal Form A - Background, Declarations, and Certifications |
| Page 13 |
| Submittal Form B - Bid Schedule |
| Page 16 |
EXHIBIT 1
Background Information
1. Background Information Idaho Department of Labor (IDOL) is requesting quotes for Janitorial Services at the Post Falls local office. Services are required for a space that is 17,837 square feet (SF) including two (2) enclosed offices, one (1) lobby, four (4) restrooms, two (2) conference rooms and multiple cubicle office spaces.
2. Objectives and Expectations IDOL seeks to secure the services of a qualified Contractor to deliver consistent, high-quality janitorial services that meet IDOL’s standards for cleanliness, safety, and professionalism. Services shall begin on July 1, provided the State has received and approved the Contractor’s required Certificate of Insurance.
3. Reference Documents
3.1 Exhibit 1 – Background Information
3.2 Exhibit 2 – Definitions
3.3 Exhibit 3 - General Requirements
3.4 Exhibit 4 – Scope of Work (SOW)
3.5 Exhibit 5 – Performance Metrics
3.6 Exhibit 6 – Cleaning Inspection Form Template
3.7 Exhibit 7 – Floor Plan
3.8 Exhibit 8 – Reference Sheet
EXHIBIT 2
Definitions
Definitions. The following definitions must apply to the terms used in the RFQ.
“ANNUAL” means one calendar year beginning with the effective date of the contract.
“AS NEEDED” means intermittent cleaning as determined necessary by the Contractor or as scheduled by the Idaho Department of Labor.
“BI-MONTHLY” means every two months.
“CLEAN” means to make free from dirt or impurities and to disinfect with a disinfectant cleaner approved pursuant to the contract. A clean surface is a surface that is disinfected and free from dirt and impurities.
“DAILY” means between the hours of 5:00 p.m. and 11:00 p.m., Monday through Friday.
“DAMP MOP” means to clean floors with water that is free from impurities and dirt.
“DISINFECT” means to use a disinfectant cleaner approved pursuant to the contract to destroy or prevent the growth of disease-carrying microorganisms.
“DUST” means to clean all loose dust from a surface with a damp cloth or wand.
“EDGE CLEAN” Using edge or crevice tool to vacuum where carpet meets the walls or cubicle edges.
“MONTHLY” means a calendar month beginning at 12:00 a.m. on the first day of the month and ending at 12:00 a.m. on the first day of the succeeding month.
“MOP” means to clean floors with a disinfectant cleaner approved pursuant to the contract and to rinse with clean water.
“SEMI-WEEKLY” means two (2) times per week on a scheduled basis.
“SWEEP” means to clean or clear away dirt and debris with a broom, brush or dry mop device and to remove dirt and debris to a trash receptacle.
“WASH” means to scrub or otherwise clean with a cleaning product approved pursuant to the contract.
“WEEK” means a consecutive seven (7) calendar day period beginning at 12:00 a.m. Sunday morning and concluding at 12:00 a.m. the following Sunday morning.
“WEEKLY” means every week.
EXHIBIT 3
General Requirements
The following provisions establish the minimum mandatory performance requirements applicable to the resulting contract. These requirements are mandatory and will be incorporated into the contract upon award. Bidders should carefully review each provision and ensure their quote meets requirements as set forth herein.
Note: In the event of conflict with the State’s Standard Terms and Conditions, or other terms, conditions or requirements contained in this RFQ, the following provisions will take precedence:
1. Reporting Requirements The Contractor must submit a completed Cleaning Inspection Form (Exhibit 6) to the IDOL Office Manager or designee on the last scheduled cleaning day of each month.
2. Subcontractors The Contractor must not enter into any subcontract relating to the daily cleaning duties of this Contract or any part thereof. Specialized services (e.g., carpet and upholstery cleaning), may be subcontracted only with prior written approval from the State.
3. Price Adjustment Clause A price adjustment may be considered on an annual basis, if necessary, upon Contract renewal. The Contractor must notify the State at least thirty (30) calendar days prior to the renewal date and must provide supporting documentation demonstrating industry wide increases or other justification for the requested adjustment. Any approved increase will be limited to the Contractor’s actual, documented cost increases. If the total price increases exceed fifteen percent (15%) of the life of the Contract, the State may terminate the Contract. The State will notify the Contractor whether the request is approved within ten (10) calendar days of receipt of the request.
4. Billing Procedure Contractor must invoice monthly, preferably on or before the fifteenth (15th) day of each month, for work performed. Any invoices submitted without the below-listed information will be rejected until a corrected invoice is submitted.
The Contractor must provide the following information with each invoice:
4.1. Detailed form/checklist (must include at minimum: names of Contractor staff performing the work, and a description of the work performed).
4.2. Dates of Service
4.3. Total amount billed for the billing period.
4.4. Contractor name, address, phone number, and e-mail address.
4.5. Contract Number.
4.6. Invoice Date
Invoices must be submitted as an Adobe PDF e-mail attachment to:
4.7. Accounts.Payable@labor.idaho.gov and Facility.Requests@labor.idaho.gov
Or by United States Mail to:
4.8. Idaho Department of Labor
4.9. Attn: Accounts Payable
4.10. 317 W Main St.
4.11. Boise, ID 83735-0610
EXHIBIT 4
Scope of Work
The following Scope of Work represents the minimum mandatory requirements for the contract. Bidders must comply with all requirements set forth herein.
1. Summary of Scope The Contractor must provide comprehensive janitorial services for IDOL’s Post Falls local office located at 600 N. Thornton Street, Post Falls, ID 83877, in accordance with the required daily, weekly, monthly, bi-monthly, quarterly, and annual cleaning schedules. Services include, but are not limited to, vacuuming, trash removal, restroom cleaning, window cleaning, dusting, and other tasks necessary to maintain a clean, safe, and professional environment. Agency contacts for coordination will be provided upon contract award.
2. Requirements The Contractor must provide all janitorial services as outlined below, adhering to IDOL’s standards and safety requirements. See Exhibit 2 for Definitions of terms used in this section.
2.1 Daily Services
The Contractor must perform the following services at least daily to remove trash or debris and to maintain clean surfaces:
2.1.1. Sweep all walk surfaces at all entries and exits;
2.1.2. Sweep, mop and disinfect all restroom floors;
2.1.3. Clean and disinfect fixtures in all restrooms and breakrooms including mirrors, counters, washbasins, faucets, urinals, toilets, toilet seats and lids, and supply dispensers;
2.1.4. Clean and disinfect all drinking fountains;
2.1.5. Fill all supply dispensers located in the restrooms and breakrooms including paper towels, hand soap, toilet paper and toilet seat covers;
2.1.6. Empty all waste receptacles in conference rooms, restrooms, employee desks, front desk, shredders and outside receptacles, and install new plastic liners daily or as needed;
2.1.7. Vacuum carpeted areas including floor mats, walkways and offices;
2.1.8. Clean and disinfect glass doors including removal of all smudges;
2.1.9. Clean both sides of all partitions and doors including interior/exterior glass;
2.1.10. Clean all doorknobs, pull and push plates;
2.1.11. Empty and clean all ashtrays and remove cigarette debris from building entrances;
2.1.12. Clean reception counter and computer kiosks including the top, side, working surfaces, and computer screens located in the lobby and Resource Center;
2.1.13. Restock and distribute IDOL supplied paper products and consumables to restroom and breakroom storage areas to maintain minimum stock levels, as defined by the IDOL Office Manager or designee; and
2.1.14. At the completion of each shift, replace soiled dust and wet mop heads, hang all long-handled tools (mops, brooms) on wall-mounted hangers, empty and rinse all mop buckets, and ensure the housekeeping closet is clean, organized, and locked.
2.2 Weekly Services
The Contractor must perform the following services at least weekly to remove visible dirt and debris:
2.2.1 Clean and mop custodial storage room;
2.2.2 Vacuum carpeted areas including conference rooms and cubicles;
2.2.3 Clean and disinfect restroom walls, doors, and partitions. Special attention must be given to corners, floor edges, and chrome leg caps; and
2.2.4 Dust the tops of all cubicle partitions and window ledges.
2.3 Monthly Services
The Contractor must perform the following as noted below and at least monthly:
2.3.1 Clean all windowsills;
2.3.2 Clean interior-facing glass surfaces, including interior partition glass and interior window glass;
2.3.3 Dust all cobwebs inside of the building and at all entrance and exit doors;
2.3.4 Dust all window blinds;
2.3.5 Clean legs of all chairs and tables located in the lobby, breakroom, and conference rooms;
2.3.6 Clean all door frames, removing all smudges;
2.3.7 Clean all cubicle fixtures and;
2.3.8 Inspect all interior office lighting, replacing all non-operating light bulbs within one (1) business day.
2.4 Bi-Monthly Services
The Contractor must perform the following as noted below and at least every two months:
2.4.1 Clean all exterior-facing window glass, both interior and exterior surfaces;
2.4.2 Edge clean all carpets and;
2.4.3 Clean and disinfect all waste receptacles.
2.5 Quarterly Services
The Contractor must perform the following as noted below and at least four times per year:
2.5.1 Dust and clean all light fixtures;
2.5.2 Dust and clean heating and air system vents and;
2.5.3 Mop and disinfect all plastic chair mats located in cubicle and office areas.
2.6 Annual Services
The Contractor must perform the following as noted below and at least once per year:
2.6.1 Clean all upholstered chairs annually using hot water extraction or an equivalent method approved in writing by IDOL. Spot cleaning must be performed as needed throughout the year and;
2.6.2 Perform deep carpet cleaning for the entire office using hot water extraction or steam cleaning. Spot cleaning must be performed as needed.
2.7 Supplies and Equipment
2.7.1 The Contractor must supply, at its sole expense, all equipment, tools, materials, and supplies. Such supplies include, but are not limited to vacuums, mops, brooms, cleaning chemicals, floor stripper, floor sealer, floor wax, and personal protective equipment for staff, including latex gloves, aprons, goggles and filter masks.
2.7.2 The Contractor must submit specifications for all products and supplies to the IDOL Office Manager or designee for approval prior to use.
2.7.3 The Contractor must provide copies of Safety Data Sheet (SDS) documents for chemical supplies provided to IDOL pursuant to the contract. These documents must be supplied to and approved by the IDOL Office Manager or designee prior to using the chemicals.
2.7.4 IDOL will supply the following:
2.7.4.1 Paper towels;
2.7.4.2 Toilet paper;
2.7.4.3 Toilet seat covers;
2.7.4.4 Plastic bags;
2.7.4.5 Trash receptacles;
2.7.4.6 Light bulbs;
2.7.4.7 Keys and/or building entry codes as necessary; and
2.7.4.8 Storage not to exceed what is currently used by housekeeping.
2.8 Maintenance and Use of Supplies and Equipment
2.8.1 All Contractor equipment, supplies, and chemicals must be maintained in a manner that prevents unauthorized persons from gaining access to such items.
2.8.2 The Contractor must ensure that all Contractor’s equipment and supplies comply with applicable state and federal safety requirements.
2.8.3 The Contractor must ensure that all equipment is maintained in proper operating condition. The Contractor must, at its sole cost and expense, furnish all parts, tools, and qualified personnel required to service or repair its equipment
2.8.4 The Contractor’s equipment must be operated in a manner that maintains reasonable noise levels during regular business hours and prevents disruption to business activities
2.8.4.1 Contractor must only perform services during business hours when approved by IDOL, per Section 2.10, Hours of Operation.
2.8.5 The Contractor must mix, manage, store, secure, label and distribute all chemicals used by the Contractor in a safe manner that complies with all applicable state and federal safety requirements.
2.8.6 The Contractor must maintain Safety Data Sheet (SDS) information at the location where chemicals are used, stored, mixed and distributed, and maintain a master inventory of SDS for all chemicals used in conjunction with this contract.
2.8.7 Housekeeping closets and equipment must be kept in a clean and orderly fashion. Closets must be locked at all times. Materials must be placed on shelves with labels facing out, paper supplies and clean mop heads on upper shelves, liquid and caustic material on lower shelves.
2.9 Staff and Training
2.9.1 All personnel must be background checked and bonded by the Contractor prior to starting work.
2.9.2 The Contractor must ensure that Contractor’s staff is trained in the following:
2.9.2.1 The proper use of chemicals used under the Contract;
2.9.2.2 The handling of infectious waste; and
2.9.2.3 The conduct of all activities required under the Contract.
2.9.2.4 IDOL reserves the right to request additional documentation from Contractor to prove that their staff has completed the above training.
2.9.3 The Contractor must take all necessary steps to ensure the health and safety protection of persons and real and personal property during the performance of the Contract including:
2.9.3.1 Providing all training necessary for Contractor employees who are limited in English proficiency to conduct all activities under the Contract in a manner that does not put any person, including the Contractor employee, or any real or personal property at risk of injury, death or damage.
2.10 Hours of Operation
2.10.1 The Contractor must perform all services between the hours of 5:00 PM through 11:00 PM, Monday through Friday, unless such other hours of operation are approved by IDOL. No work is expected to be performed during State-recognized holidays (https://idaho.gov/about-idaho/state-holidays/#gsc.tab=0).
EXHIBIT 5
Performance Metrics
Contractor Performance
IDOL will commence formal assessment of the Contractor’s performance thirty (30) calendar days after the effective date of the contract. A designated representative of IDOL will assess the Contractor’s performance. The IDOL representative will inspect all services under this RFQ on a random basis. The Contractor will be given a copy of inspection reports as they are done.
IDOL may inspect Contractor’s work at any time. Any deficiencies will be documented by IDOL and immediately corrected by the Contractor. IDOL may withhold payment on monthly invoices until deficiencies are corrected to IDOL’s satisfaction.
The Contractor will be assigned one (1) deficiency point based on the Contractor's failure to complete a duty or any part of a duty unless IDOL requested the Contractor not perform the duty.
If the Contractor corrects any noted deficiencies to the satisfaction of IDOL within forty-eight (48) hours, any charges will be credited back.
IDOL will furnish a monthly Quality Assurance Report to the Contractor. The report will include a total number of deficiency points assigned to the Contractor during inspections for the month and a general description of the deficiencies that need to be corrected. The Contractor must correct deficiencies as soon as practicable or reasonably directed by IDOL.
Payment pursuant to the contract will be reduced in the following manner:
RANGE
ACTION
| 0 TO 10 Deficiency points per week |
| No deductions from payments |
| 11+ Deficiency points per week |
| Deduct one-half percent (0.5%) of the Contractor's monthly payment for each deficiency point over ten (10) points in any week. Deductions will be taken from the Contractor's next monthly invoice unless corrections have been made in accordance with IDOL approval and timeframe as listed above. |
Notwithstanding any provision of this Section to the contrary, the above specified assessment and deficiency process must in no way limit the rights and remedies of IDOL as set forth in the contract or as otherwise allowed by applicable law.
EXHIBIT 6
Cleaning Inspection Form Template
| Inspector: |
| Date: |
(O) Satisfactory (X) Requires Action
| Daily: |
| Condition |
| Comments |
Sweep all walk surfaces at all entries and exits.
Sweep, mop and disinfect all restroom floors.
Clean and disinfect all fixtures in restrooms and breakrooms.
Clean and disinfect all drinking fountains.
Fill all supply dispensers in restrooms and breakroom.
Empty all waste receptacles in the conference rooms, restrooms, desks, front desk, shredders, and outside.
Vacuum carpeted areas including floor mats, walkways and offices.
Clean and disinfect glass doors including removal of all smudges.
Clean both sides of all partitions and doors.
Clean all doorknobs, pull and push plates.
Empty and clean all ashtrays and remove cigarette debris.
Clean reception counter and computer kiosks.
Restock and distribute supplied paper products and consumables to restroom and breakroom storage areas.
Replace soiled dust and wet mop heads, hang all long-handled tools, empty and rinse mop buckets, ensure housekeeping closet is clean, organized, and locked.
Weekly
Clean and mop custodial storage room.
Vacuum carpeted areas including conference rooms and cubicles.
Clean and disinfect restroom walls, doors and partitions. Special attention must be given to corners, floor edges, and chrome leg caps.
Dust the tops of all cubicle partitions and window ledges.
Monthly
Clean all window sills.
Clean interior facing glass surfaces.
Dust all cobwebs inside of the building and at all entrances and exit doors.
Dust all window blinds.
Clean legs of chairs and tables in lobbies, breakroom and conference room.
Clean all door frames removing all smudges.
Clean all cubicle fixtures.
Inspect all interior office lighting, replacing all non-operating light bulbs.
Bi-Monthly
Clean all exterior windows, inside and outside.
Edge clean all carpets.
Clean and disinfect all waste receptacles.
Quarterly
Dust and clean light fixtures.
Dust and clean heating and air system vents.
Mop and disinfect all computer mats.
Annually
Clean all upholstered chairs.
Carpet heavy cleaning and spot cleaning as needed for the whole office.
EXHIBIT 7
Floor Plan
Exhibit 8 Reference Sheet
Reference #1
Project Length (EX: April 2024- Oct 2025)
Contact Information:
Name:
Telephone:
Email:
Postal Address:
Reference #2
Project Length (EX: April 2024- Oct 2025)
Contact Information
Name:
Telephone:
Email:
Postal Address:
Reference #3
Project Length (EX: April 2024- Oct 2025)
Contact Information
Name:
Telephone:
Email:
Postal Address:
SUBMITTAL FORM A
Background, Declarations, & Certifications
All information requested in Submittal Form A is mandatory. Failure to complete or respond to each question, failure to sign this Form A, or failure to submit this Form A may result in your quote not being considered for award.
PROJECT INFORMATION
| RFQ Number: |
| 1300 |
| Project Name: |
| Janitorial Services – Post Falls local office |
BIDDER INFORMATION
Company Name:
Company Address:
Tax Identification Number (EIN):
| Legal Status: |
| ☐ Corporation |
☐ Limited Liability Corporation (LLC) ☐ Limited Liability Partnership ☐ Sole Proprietorship ☐ Other (specify)
CONTACT INFORMATION
Individual responsible for preparing this Bid, and who can be contacted for clarification on this Bid
Contact Name:
Title:
Email:
Telephone:
CONFLICT OF INTEREST
The Bidder must select an option below:
| ☐ |
| The Bidder declares that there is no potential, perceived, or actual conflict of interest that may arise as a result of their response to this RFQ and/or subsequent award of Contract. |
| ☐ |
| The Bidder declares that there are potential, perceived, or actual conflicts of interest that may arise as a result of their response to this RFQ and/or subsequent award of Contract. The Bidder must attach additional information to explain the conflicts. |
CERTIFICATIONS
| QUESTION |
| RESPONSE* |
1) Is Bidder a legal entity with the legal right to contract?
☐ Yes ☐ No
2) Is Bidder in compliance with applicable equal employment regulations?
☐ Yes ☐ No
3) Does Bidder affirm that it is not currently suspended, debarred, or otherwise excluded from federal or state procurement and non-procurement programs? (Vendor information available at sam.gov)
☐ Yes ☐ No
4) Does Bidder warrant that it does not knowingly and willfully employ persons who cannot legally work in this country; and that Bidder takes steps to verify that it does not hire persons who have entered our nation illegally or cannot legally work in the United States; and that any misrepresentation in this regard or any employment of such persons constitutes a material breach and will be cause for the imposition of monetary penalties up to five percent (5%) of the Contract price, per violation, and/or termination of the Contract?
☐ Yes ☐ No
5) Does the Bidder affirm and acknowledge that the State manages all vendor profiles and payment preferences exclusively through PaymentWorks, and that organizations selected for award must register or update their PaymentWorks account to avoid delays in contract awards and payments?
☐ Yes ☐ No
* Failure to answer, or answering “No” may be grounds for disqualification. Attach additional information on any subject where the Bidder responded “No” to a question above.
ATTESTATION AND SIGNATURE
This Submittal must be dated and signed by an officer or agent (“Representative”) duly authorized to execute contracts for the Bidder. By my signature I accept the terms, conditions and requirements contained in the solicitation, including, but not limited to, the State of Idaho Standard Contract Terms and Conditions, and the solicitation instructions in effect at the time this RFQ was issued, as incorporated by reference into this solicitation; as well as any special terms and conditions incorporated in the solicitation documents. As the undersigned, I certify I am authorized to sign and submit this response for the named Bidder. I further acknowledge I am responsible for reviewing and acknowledging any addendums that have been issued for this solicitation.
Printed Name of Representative
Signature
Date
SUBMITTAL FORM B
Bid Schedule
Submittal Form B is provided as an Excel document in the Questions tab of the event in IPRO.
image2.png image1.png