RFQ # 1135 Addendum No. 1.pdf

PDF 749 KB Posted

Attached to
RFQ # 1135 Stone Robinson Water Resource Recovery Facility Tank Repair and Rehabilitation
Solicitation number
QQ-118620
Issued by
Albemarle County, Chesapeake City, Virginia

About this file

This is Addendum No. 1 to a Request for Quote (RFQ) issued by the Rivanna Water & Sewer Authority (RWSA) for tank repair and rehabilitation services at the Stone Robinson Water Resource Recovery Facility (SRWRRF) in Charlottesville, Virginia. The scope of work encompasses temporary wastewater pumping and hauling, removal and reinstallation of existing process equipment, sandblasting of interior and exterior metal surfaces extending 6 inches below grade, installation of metal fabrications for deteriorated steel, application of protective coatings to interior and exterior surfaces, a 7-day operational performance review of reinstalled equipment, and site restoration. The addendum, dated May 8, 2026, revises the quote opening date to May 18, 2026, at 3:00 p.m. Eastern Time. Quotes may be submitted via mail, hand delivery, email, or the eVA Procurement Website. Substantial completion is required by July 15, 2026, with work anticipated to occur during June and July when the associated school is not in full session. Short Elliott Hendrickson Inc. (SEH) will serve as the project engineer and third-party inspector. The addendum includes requirements for contractor qualifications, insurance, safety certifications (minimum OSHA 10), and a pre-construction safety meeting.

Quotes are submitted on a lump-sum basis with no bid bond required if the bid is below the authority's threshold. The project carries no liquidated damages or retainage provisions. A two-year warranty from the date of substantial completion is required for all coating systems, with the contractor responsible for repairs of any coating failures at no cost to the authority. No wage rate requirements apply to this project, and tax exemption will be requested upon award. The facility was constructed in 1988, and lead paint is not anticipated to be present. Section 09 97 20 of the specifications details coating system requirements, including surface preparation standards, acceptable manufacturers (BASF, CIM Industries, General Polymers, L&M Construction, Sherwin Williams, and Tnemec), environmental compliance standards, and quality control procedures. All products must be lead, chromate, mercury, and heavy metals free, with VOC compliance required under the Clean Air Act.

View the file

Other files

File Type Posted
RFQ # 1135 Stone Robinson WRRF Repair.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum

RIVAN 190497 00 00 11 - 1

DOCUMENT 00 00 11

ADDENDUM NO. 1

May 8, 2026

Stone Robinson Water Resource Recovery Facility Tank Repair and Rehabilitation Rivanna Water & Sewer Authority

SEH No. RIVAN 190497

RFQ 1135

From: Short Elliott Hendrickson Inc.

400 Locust Drive, Suite 2 Charlottesville, VA 22901 651.490.2000

To: Document Holders

DOCUMENT HOLDERS on the above-named project are hereby notified that this document shall be appended to, take precedence over and become part of the original bidding documents dated April 21, 2026 for this work.

Bids submitted for the construction of this work shall conform to this document.

This addendum consists of two (2) page, plus the following:

• Bidding Requirements Specifications: Request for Quote Cover (2 pages), 00 41 00 – Quote Form (5 pages), 09 97 20 – Coating Systems for Wastewater Facilities (12 pages).

o Revise quote opening date to May 18th, 2026 at 3 p.m. ET.

Changes to Specifications:

1. INCLUDE the following documents in their entirety.

a. Request for Quote Cover

b. 00 41 00 – Quote Form

c. 09 97 20 – Coating Systems for Wastewater Facilities

Questions Received:

2. Verify that a bid bond will not be required to be submitted with our bid.

Response: It will not be required if it comes in below our bidding threshold.

3. Is there an amount for liquidated damages for the project?

Response: Contractor is responsible for work, no LDs defined for this project.

4. Is there an amount for retainage for this project?

Response: No retainage for this project.

5. What is the warranty period for the project?

Response: Warranty period for coatings included in revised specification attached to this addendum.

6. Is this project tax exempt?

Response: A request for tax exemption will be made once the project is awarded.

7. What year was this built? Is there any lead?

Addendum

00 00 11 - 2 RIVAN 190497

Response: The record drawings we have on file show a date of 1987 so construction approximately took place sometime in 1988. Based on the date of construction, lead paint is not anticipated to be present.

8. Is this a wage rate project?

Response: Wage rates do not apply to this project.

9. What month do you anticipate that the notice to proceed will be issued and work begin?

Response: The timeline should be stated in the contract docs, We have a period during the summer while the school is not in full session. June and July are the months we are able to perform the work.

10. Will a third-party inspector be used? If so, who or who is being considered?

Response: Our consulting firm SEH will be inspecting the work.

Note: Receipt of this Addendum No. 1 (dated May 8, 2026) shall be acknowledged on the submitted Quote Form. Failure to do so may subject Bidder to disqualification.

END OF ADDENDUM

RA-1b RWSA Bid Form

Rivanna Water and Sewer Authority

REQUEST FOR QUOTE NO. 1135

Stone Robinson Water Resource Recovery Facility Tank Repair and Rehabilitation

DATE: April 21, 2026

PROJECT TITLE: Stone Robinson Water Resource Recovery Facility Tank Repair and

Rehabilitation

Purpose

The Rivanna Water & Sewer Authority (the “Authority”) is seeking quotes to repair and rehabilitate the existing water resource recovery facility tankage.

Scope and Construction Notes

1. Scope of work includes temporary pumping and hauling of wastewater, removal of existing process equipment from the water resource recovery facility (WRRF), sand blasting of interior metal surfaces and exterior surfaces extending 6” below grade, installation of metal fabrications for deteriorated steel of interior walls, coatings installation for interior walls, re-installation of existing process equipment as originally shown, 7-day operational performance review of existing process equipment, reestablishment of wastewater flow throughout the facility, restoration work and all associated project work.

2. The Contractor shall provide temporary wastewater pumping and hauling during the duration that the WRRF is offline. The Contractor shall submit a temporary pumping and hauling plan for review and comment at least 15 Working Days prior to the WRRF being taken offline for this work to begin. Refer to section 01 12 16 - Work Sequence

3. Contractor is responsible for secure and proper storage of all existing process equipment that is removed to prevent damage or weathering of the equipment. Any process equipment that is damaged shall be replaced as new by the Contractor.

4. The Contractor shall notify the Authority once all existing process equipment has been removed.

5. Once repair and rehabilitation have been completed and prior to wastewater flow reestablished to the WRRF, all existing process equipment removed shall be reinstalled as originally shown. The existing process equipment shall operate without the need for operator intervention for a minimum of 7 continuous days to be considered operational.

Wastewater flow shall not be reestablished until the Authority reviews the reinstalled equipment and the existing process equipment is considered operational.

6. Work to be performed shall be inclusive of any labor, equipment, and materials necessary to remove existing process equipment and reinstall equipment once rehabilitation work is completed.

7. Metal fabrications shall be installed to repair deteriorated steel of interior walls as indicated and as determined following sandblasting of the tank. Refence section 05 50 00

- Metal Fabrications.

8. Coatings shall be installed throughout entirety of interior surfaces and exterior surfaces

RA-1b RWSA Bid Form extending 6” below grade of the water resource recovery facility once sand blasting and metal repairs are completed. Reference section 09 97 20 - Coating Systems for

Wastewater Facilities.

9. Restoration of any damaged process equipment, electrical instrumentation, disturbed pavement, lawns, grass, or other existing features shall be incidental to the pricing provided in the quote. All property disturbed or damaged shall be restored to pre-existing conditions at no additional cost to the Authority. All process equipment or electrical instrumentation disturbed or damaged shall be replaced as new.

10. Substantial Completion shall be achieved by July 15th, 2026. Substantial Completion is defined as having finished the work and submitted all acceptance testing to RWSA, as well as having completed all restoration work at the project site.

11. Regular allowable work hours for this project shall be from 8 AM – 5 PM, Monday –

Friday, unless otherwise authorized in writing by the Owner and Engineer. Work on weekends and Authority holidays will not be permitted for this project unless otherwise authorized in writing by the Owner and Engineer. It is expected given the short project time frame that night and weekend work may be necessary and authorization shall not be unreasonably withheld.

12. If awarded, Contractor will be issued a purchase order for the work (Attachment C).

13. If awarded, Contractor shall provide proof of adequate insurance (Attachment D).

14. If awarded, Contractor shall participate in a Safety Meeting with the Owner’s Safety

Manager. The checklist provided (Section 01 80 00) shall be completed and submitted to

Owner for review at least 3 business days prior to the meeting. Please note that both the

Contractor Company Safety Representative, and the Contractor On-Site Safety

Representative, must have an OSHA 10 Certification at a minimum. The On-Site Safety

Representative may have another role in the crew (i.e. – Superintendent, Foreman, etc.), but must be on site at all times during the work.

All technical questions and requests for site visit assistance, may be directed to Dyon

Vega at (434) 977-2970 ext. 170 or dvega@rivanna.org. All quotes shall be submitted and signed by an authorized agent of the company.

All quotes are due by 3:00 PM local prevailing time on May 18th, 2026. Quotes received after this deadline will not be considered. Quotes may be mailed, or hand delivered, e-mailed, or submitted on the eVA Procurement Website, https://eva.virginia.gov/. Quotes shall be submitted to:

Administration – Procurement

Rivanna Water and Sewer Authority

695 Moores Creek Lane

Charlottesville, Va 22902 dvega@rivanna.org

Attachment A – Plans & Specifications

Attachment B – Quote Form

Attachment C – General Purchase Order Provisions

Attachment D – Supplementary Provisions to the General Purchase Order Provisions

Attachment E – Section 01 80 00 Safety Requirements https://eva.virginia.gov/

Quote Form

RIVAN 184584 00 41 00 - 1

The Quote is to be submitted on copies of this Quote Form and the attachments provided

DOCUMENT 00 41 00

QUOTE FORM

Date of Quote

Contractor’s Name and VA License No.

PROJECT IDENTIFICATION: RFQ 1135 – Stone Robinson Water Resource Recovery Facility Tank Repair and Rehabilitation

Rivanna Water & Sewer Authority SEH No. RIVAN 190497

QUOTATIONS TO BE DELIVERED TO OWNER: May 18th, 2026

TABLE OF ARTICLES

Article 1 – Quote Recipient Article 2 – Basis of Quote Article 3 – Time of Completion Article 4 – Quoter’s Representation and Certifications Article 5 – Quoter Qualification Article 6 – Quote Submittal

ARTICLE 1 – QUOTE RECIPIENT

1.01 This Quote is submitted to:

Rivanna Water & Sewer Authority Attention: Dyon Vega, PE 695 Moores Creek Lane

Charlottesville, VA 22902

Quote may be mailed, or hand delivered, e-mailed, or be submitted on the eVA Procurement Website, https://eva.virginia.gov

ARTICLE 2 – BASIS OF QUOTE

2.01 Quoter will complete the Work in accordance with the Contract Documents for the following price(s):

LUMP SUM QUOTE PRICE

Lump Sum Quote Price: $__________________ Lump Sum Quote Price for all work at the Stone Robinson Water Resource Recovery Facility involved with the repair and rehabilitation of the existing facility tankage which includes temporary hauling of wastewater, removal of existing process equipment, sand blasting of interior walls, installation of metal fabrications for repair of deteriorated steel on interior walls, coatings installation for interior walls, installation of existing process equipment as originally shown, 7-day operational performance review of existing process equipment, reestablishing wastewater flow to the facility, restoration work and all associated project work.

ARTICLE 3 – TIME OF COMPLETION

3.01 Quoter agrees that the Work will be substantially complete and completed and ready for final payment in accordance with the Supplementary Provisions to the General Purchase Order Provisions on, or before, the dates or within the number of calendar days indicated therein.

https://eva.virginia.gov/

00 41 00 - 2 RIVAN 184584

ARTICLE 4 – QUOTER’S REPRESENTATION AND CERTIFICATIONS

4.01 Quoters Representations

A. In submitting this Quote, Quoter represents that:

1. Quoter has examined and carefully studied the Quotation Documents, and any data and reference items identified in the Quotation Documents.

2. Quoter hereby acknowledges receipt of the following Addenda:

Addendum No. Addendum Date

3. Quoter has visited the site, conducted a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfied itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

4. Quoter is familiar with and is satisfied as to all Laws and Regulations that may affect cost, progress and performance of the Work.

5. Quoter has considered the information known to Quoter itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Quotation Documents; and any Site-related reports and drawings identified in the Quotation Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Quoter, and

(3) Quoter’s safety precautions and programs.

6. Based on the information and observations referred to in the preceding paragraph, Quoter agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

7. Quoter is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Quotation Documents.

8. Quoter has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Quoter has discovered in the Quotation Documents, and confirms that the written resolution thereof by Engineer is acceptable to Quoter.

9. The Quotation Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work.

10. The submission of this Quote constitutes an incontrovertible representation by Quoter that without exception the Quote and all prices in the Quote are premised upon performing and furnishing the Work required by the Quotation Documents.

4.02 Quoter certifies that:

A. The Quoter certifies the following:

1. This Quote is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;

2. Quoter has not directly or indirectly induced or solicited any other Quoter to submit a false or sham Quote;

3. Quoter has not solicited or induced any individual or entity to refrain from quoting; and

RIVAN 184584 00 41 00 - 3

4. Quoter has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 5.02.A:

a. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the quoting process;

b. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the quotation process to the detriment of Owner, (b) to establish Quote prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;

c. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Quote prices at artificial, non-competitive levels; and

d. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the quotation process or affect the execution of the Contract.

e.

ARTICLE 5 – QUOTER QUALIFICATION

5.01 In submitting this Quote, Quoter provides the following history of Quoter company experience.

A. Have you ever failed to complete any work awarded to you:

Yes _____ No _____. If so, attach a statement detailing where and why.

B. Have you ever defaulted on a contract:

Yes _____ No _____. If so, attach a statement detailing where and why.

C. What is your organization’s plan to complete the project? What equipment will be utilized?

D. Additional information may also be submitted if desired.

00 41 00 - 4 RIVAN 184584

ARTICLE 6 – QUOTE SUBMITTAL

6.01 This Quote submitted by:

If Quoter is:

An Individual

Name (typed or printed):

By: (SEAL) (Individual’s signature)

Doing business as:

A Partnership

Partnership Name: (SEAL)

By:

(Signature of general partner - attach evidence of authority to sign)

Name (typed or printed):

A Joint Venture

Name of Joint Venturer:

First Joint Venturer Name: (SEAL)

By:

(Signature of first joint venture partner - attach evidence of authority to sign)

Name (typed or printed):

Title:

Second Joint Venturer Name: (SEAL)

By:

(Signature - attach evidence of authority to sign)

Name (typed or printed):

Title:

(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is a party to the joint venture should be in the manner indicated above.)

RIVAN 184584 00 41 00 - 5

A Corporation

Corporation Name:

State of Corporation:

Name (General Business, Professional, Service, Limited Liability):

By:

(Signature - attach evidence of authority to sign)

Name (typed or printed):

Title:

(CORPORATE SEAL)

Attest:

(Signature of Corporate Secretary)

Date of Qualification to do business in is ____/____/____.

(State Where Project is Located)

Contact Information

Quoter’s Business Address:

Phone: ___________________ Facsimile: _________________ E-mail: ___________________________

Submitted on ______________________________, 20_____.

State Contractor License No. ________________.

END OF DOCUMENT

Coating Systems for Wastewater Facilities

RIVAN 190497 09 97 20 - 1

SECTION 09 97 20

COATING SYSTEMS FOR WASTEWATER FACILITIES

PART 1 GENERAL

1.01 SUMMARY

A. Provide surface preparation and application of high performance industrial coatings.

B. Related Sections:

1. Section 05 50 00 – Metal Fabrications

1.02 REFERENCES

A. ASTM - American Society for Testing Materials

1. ASTM D4263

2. ASTM F1869

B. International Association of Corrosion Engineers (NACE)

1. SSPC-PA2

2. NACE RP0188

C. International Concrete Repair Institute (ICRI)

D. Society for Protective Coatings (SSPC):

1. Volume 1: Good Painting Practice

2. Volume 2: Systems and Specifications

1.03 DEFINITIONS

A. Applicator: Person applying the product in the field at Site.

B. Dry Film Thickness (DFT): Minimum dry coating thickness.

C. SFPG: Square feet per gallon.

D. VOC: Volatile Organic Compounds.

E. Regional: The state in which the Project is located and surrounding states.

F. LEL: Lower Explosion Limit.

G. Containment: Equipment, supports, screens, tarps, or shrouds that prevent airborne debris generated during surface preparation and coating application from entering the environment and also facilitates controlled collection of debris for disposal in compliance with current regional and federal regulations.

H. Moderate Service: Surfaces subject to normal exposure and moderate humidity. Includes concrete, concrete masonry, structural steel, miscellaneous metals, doors, and frames.

I. Severe Service: Surfaces subject to frequent splashing, spilling, and exposure to high humidity and condensation. Includes structural steel, miscellaneous metals, piping, valves, and equipment.

J. Immersion Service: Surfaces subject to immersion, or constant exposure to high humidity and condensation.

09 97 20 - 2 RIVAN 190497

1.04 SUBMITTALS

A. Manufacturers’ current Product Data sheets.

1. Coatings

2. Abrasive(s)

3. Additives (as applicable)

4. Containment System

5. All miscellaneous fillers, caulks, sealants and resurfaces, etc.

B. Provide a list of equipment to be used on this Project for review by Engineer.

C. Safety Data Sheets (SDS) for each product specified.

D. Samples:

1. Color chips of available colors.

2. Recommended colors for color code marking.

E. Post-construction Contract Closeout:

1. Daily application records using Engineer’s provided format, or Contractor’s form pre-approved by Engineer.

F. Written plan for containment of fugitive airborne particles compliant with current state and/or federal regulations.

G. Printed warranty shall be provided within 10 days of commencement of the warranty period.

1.05 WARRANTY

A. Manufacturer agrees to repair or replace components that fail(s) in material or workmanship within specified warranty period.

1. Standard Warranty Period: Two (2) years from date of Substantial Completion, regardless of date of shipment or duration of storage on site.

B. Warranty Inspection

1. At the Owner’s option, an inspection of the coating system may be held within 24 months from the date of Substantial Completion.

2. Owner’s Responsibilities:

a. Establish date and time for inspection.

b. Provide minimum 14 days’ notice to Contractor.

c. Determine inspection method.

d. Provide suitable access.

e. Advise Contractor of any coating failures, and the required corrective measures.

1) Coating failures shall be interpreted to include:

a) Peeling.

b) Blistering or bubbling.

c) Cracking.

d) Rusting or rust staining.

3. Contractor’s Responsibilities:

a. Repair all coating failures as follows:

1) Coordinate Work schedule with Owner.

2) Perform corrective measures in accordance with this Section.

3) Complete Work within 30 days of receipt of Owner’s notice.

4) Complete Work at no cost to Owner.

1.06 QUALITY ASSURANCE

A. Single Source Responsibility: Provide coating products from a single manufacturer.

B. Applicator Qualifications:

RIVAN 190497 09 97 20 - 3

1. Contractor shall provide a written statement from the coating manufacturer’s authorized representative attesting that the on-site Contractor Superintendent has been instructed on proper preparation, mixing, and application procedures for all the coatings specified for this project.

2. Contractor shall provide all necessary equipment to monitor and record the information required on the Daily Application Record.

a. Equipment shall be in good condition.

b. Operational within its design range.

c. Calibrated as required by the specified standard for use of each device.

3. Applicator to establish quality control procedures and practices to monitor phases of surface preparation, storage, mixing, application, and inspection throughout the duration of the project.

Contractor to provide a full-time, on-site person whose dedicated responsibilities will include quality control of the corrosion protection linings.

4. Applicators’ quality control procedures and practices must include the following items:

a. Training of personnel in the proper surface preparation requirements.

b. Training personnel in the proper storing, mixing, and application and quality control testing of the linings.

C. Pre-Installation Conference:

1. Before applying any materials, the Contractor, Installer and qualified technical representative of the corrosion protection lining manufacturer shall meet on-site with Engineer to discuss approved products and workmanship to ensure proper application of the corrosion protection lining components and substrate preparation requirements.

2. The contractor ran meeting shall include an observation of the substrate to verify that the specified coatings are suitable for the environmental conditions and substrate.

3. Review foreseeable methods and procedures related to the corrosion protection lining of coating Work including but not necessarily limited to the following:

a. Review Project requirements and the Contract Documents.

b. Review required submittals, both completed and yet to be completed.

c. Review status of substrate Work, including approval of surface preparations and similar considerations.

d. Review requirements of on-Site quality control testing and requirements for preparing Site

Quality Control Report as specified herein.

e. Review availability of materials, tradesmen, equipment and facilities needed to make progress and avoid delays.

f. Review required inspection and testing.

g. Review environmental conditions, other Project conditions, and procedures for coping with unfavorable conditions.

h. Review regulations concerning code compliance, environmental protection, health, safety, fire and similar considerations.

i. Review procedures required for the protection of the corrosion protection lining during the remainder of the construction period.

4. Contractor Shall Record the discussions of the Pre-Installation Conference and the decisions and agreements or disagreements reached and furnish a copy of the minutes to each party attending.

Record any revision or changes agreed upon, reasons therefore, and parties agreeing or disagreeing with them.

5. Contractor shall document and distribute meeting minutes to all attendees.

6. Reconvene the conference at the earliest opportunity if additional information must be developed to conclude the subjects under consideration.

D. Performance Criteria: The surfaces to receive the protective lining shall be capable of withstanding under constant exposure to raw wastewater, permeation from hydrogen sulfide and other sewer gases, and attack from organic acids generated by microbial sources. Products must have sufficient field history to substantiate product viability for these exposures.

E. Source Quality Control: Provide each component of protective lining produced by a single manufacturer; including recommended repair mortar, repair overlay (resurfacer), base coat and topcoat materials.

09 97 20 - 4 RIVAN 190497

F. Reference Standards: Comply with applicable provisions and recommendations of all standards listed in Section 1.2 except as otherwise shown or specified.

G. Qualifications:

1. Applicator shall have minimum of 5 years application experience on projects of similar size and scope.

2. Provide written statement from coating manufacturer’s authorized representative attesting that Applicator has been instructed on proper preparation, mixing, and application procedures for coating specified.

3. Provide regional references for coating contractor for a minimum of 5 different projects of similar size and scope completed in the last 5 years, including:

a. Contact person and phone number.

b. Project location.

c. Cost of coating work.

d. Start/finish dates.

1.07 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials to Site in original, factory-sealed containers bearing manufacturer’s intact name and legible label with the following information.

1. Material identification by name or number.

2. Manufacturer’s stock number, batch number, and date of manufacture.

3. Color name and number.

B. Storage:

1. Store materials in an environmentally controlled location as recommended by coating manufacturer’s product information guidelines.

2. Store materials not in actual use in tightly covered containers.

3. Comply with health and fire regulations of governing authorities having jurisdiction.

C. Handling:

1. Handle materials in a manner that precludes the possibility of contamination or incorrect product catalyzation.

2. Do not open containers or mix components until surface preparation has been completed and approved by Engineer.

3. Maintain containers used for storage, mixing, and application in a clean condition, free of foreign materials and residue.

1.08 PROJECT CONDITIONS

A. Site Facilities:

1. As necessary to maintain required ambient conditions and contract scheduling, the contractor shall provide all required equipment for supplemental heating, dehumidification and power.

2. Maintain environmental conditions, including temperature, dew point and humidity within range recommended by coating manufacturer.

3. Do not use heat sources that emit carbon dioxide or carbon monoxide into areas being coated.

4. Properly locate and vent all such heat sources to the exterior such that coating systems are unaffected by exhaust products.

5. Provide lighting to the satisfaction of Engineer to illuminate the complete workspace during blasting, coating, and inspection operations.

B. Environmental Conditions:

1. Coating shall not be applied in rain, snow, fog, or mist.

2. Conduct surface preparation and coating operations only when the following conditions are met.

a. Ambient air temperature is within limits recommended by coating manufacturer.

b. Steel surface temperature is more than 5 degrees above the dew point of the ambient air.

c. Surfaces to be painted are clean and completely dry.

RIVAN 190497 09 97 20 - 5

3. Immersion Service: Continuous forced ventilation in accordance with manufacturer’s recommendation.

a. At a minimum provide 3 to 5 air exchanges per hour for 12 hours after application of the prime coat and for the first 24 hours following final finish coat application.

b. Maintain exhaust in compliance with state standards.

c. Provide containment during abrasive blasting operations to prevent emission of abrasives, existing coatings, and contaminants onto adjacent property, street, structures, or equipment.

C. Drawings do not purport to show actual field dimensions, but are intended only to establish location and scope of Work. Field-verify dimensions and assume full responsibility for their accuracy.

1.09 SEQUENCING AND SCHEDULING

A. Schedule blasting, cleaning, and painting so that contaminants from cleaning process will not come in contact with wet, newly painted surfaces.

B. Do not apply coatings until surface preparation has been approved by Engineer.

C. Do not apply finish coats until:

1. All prime coat application is completed.

2. All surfaces have been cleaned.

3. All surfaces have been approved for coating by Engineer.

PART 2 PRODUCTS

2.01 MANUFACTURERS

A. Coatings:

1. Acceptable Manufacturer: Subject to compliance with specified requirements, acceptable manufacturers and products are:

a. BASF www.basfbuildingsystems.com

b. CIM Industries (CIM) www.cimind.com

c. General Polymers Corporation (GPC) www.generalpolymers.com

d. L&M Construction (LMC) www.lmcc.com

e. Sherwin Williams (SWC) www.sherwin.com

f. Tnemec (TCI) www.tnemec.com

B. Sealant Caulking:

1. Thiokol Polysulfide Caulk

2. Or approved equivalent if approved by the single source manufacturer of all other submitted and approved coatings for this project.

C. Corrosion Inhibitor

1. Holdtight 102 by HoldTight, Houston, TX www.holdtight.com

D. Lead Abatement Additive

1. Blastox by TDJ Group, Cary, IL www.blastox.com

E. Substitutions: Manufacturer of comparable products submitted in compliance with Section 01 25 13.

F. Substitution of fast-cure products or acceleration additives must receive prior approval by Engineer.

2.02 MATERIALS

A. Regulatory Requirements:

1. Products shall comply with the United States Clean Air Act for maximum VOC content.

2. Products shall comply with state environmental and health standards.

3. All products shall be lead, chromate, mercury and heavy metals free.

http://www.basfbuildingsystems.com/ http://www.cimind.com/ http://www.generalpolymers.com/ http://www.lmcc.com/ http://www.sherwin-williams.com/ http://www.tnemec.com/ http://www.holdtight.com/ http://www.blastox.com/

09 97 20 - 6 RIVAN 190497

B. Thinners: Use thinners approved by coating manufacturer and within their recommended limits.

C. Abrasives:

1. Abrasive materials must be in compliance with state environmental and health standards.

2. Properly size abrasives to provide the specified surface profile.

3. The use of abrasives exceeding 1 percent free silica is prohibited.

PART 3 EXECUTION

3.01 EXAMINATION

A. Examine substrates, areas, and conditions for compliance with requirements for application and notify Engineer in writing of conditions detrimental to proper and timely completion of Work. Do not proceed with Work until unsatisfactory conditions have been corrected.

B. Notify Engineer in writing of anticipated problems using specified systems with substrates primed by others.

C. Prepare existing materials or substrates to be coated to meet the requirements of specified coating system.

D. Starting of painting Work will be construed as Contractor’s acceptance of surfaces and conditions within any particular area.

3.02 PREPARATION

A. Coating manufacturer shall verify surface preparation is completed prior to coating placement.

B. Any residue or buildup should be thoroughly cleaned from the surface being coated prior to placement of coatings as to prevent residue from affecting the ability of the coating to adhere.

C. Remove hardware, hardware accessories, machined surfaces, plates, and similar items not to be painted, or provide surface-applied protection prior to surface preparation and painting. Following completion of painting, reinstall removed items.

D. Clean and remove all rust, slag, weld splatter, weld scabs, mill scale, loose paint, and surface contaminants

C. Chip or grind off flux, spatter, slag or other laminations left from welding. Grind welds and other sharp projections smooth.

D. Re-blast all Surfaces:

1. Where rusting has recurred.

2. That do not meet the requirements of this Section.

E. Feather edges of existing coating to form a smooth transition prior to spot priming.

F. Scarify previously applied coatings in accordance with coating manufacturer’s recommendations.

G. All substrates: Prepare surface profiles in accordance with manufacturer’s recommendations.

H. Prime all bare metal and touch-up damaged shop-applied prime coat with specified primer. Prepare and coat in accordance with this Section.

I. Mix corrosion inhibitor and apply in accordance with manufacturer’s recommendations.

J. Concrete:

1. Allow new concrete to cure 28 days.

RIVAN 190497 09 97 20 - 7

2. Verify dryness by testing in accordance with ASTM D4263.

a. Floors: If moisture is detected, perform Moisture Vapor Emission Testing in accordance with

ASTM F1869.

b. Moisture content not to exceed 3 pounds per 1,000 square feet in a 24-hour period.

K. Fill cracks and voids according to coating manufacturer’s recommendations.

L. Extents of Metal Refinishing: All interior surfaces of tank as well as an area extending 6” below existing grade on the exterior of the tank.

M. Surface Preparation Classifications:

1. P1: SSPC-SP1 - Solvent Cleaning.

a. Scarify surface by sanding.

b. Brush blast if recommended by coating manufacturer.

2. P2: SSPC-SP2 - Hand Tool Cleaning.

3. P3: SSPC-SP3 - Power Tool Cleaning

4. P4: SSPC-SP13 - Surface Preparation of Concrete

a. Prepare concrete, concrete block, cement plaster, and drywall by removing all efflorescence, chalk, dust, dirt, grease, and other oils, and by roughening as required to remove glaze.

b. Scrape and grind fins and protrusions flush with surface.

c. Rake mortar joints clean.

d. Brush blast if recommended by coating manufacturer.

5. P5: SSPC-SP5 - White Metal Blast Cleaning.

6. P6: SSPC-SP6 - Commercial Blast Cleaning.

7. P7: SSPC-SP7 - Brush Off Blast Cleaning.

8. P9:

a. Clean wood surfaces to be painted of all dirt, oil, or other foreign substances with scrapers, mineral spirits, and sandpaper, as required.

b. Sandpaper smooth those finished surfaces exposed to view.

9. P10: SSPC-SP10 - Near White Blast Cleaning.

10. P11: SSPC-SP11 - Power Tool Cleaning to Bare Metal.

11. P12: SSPC-SP12 - LP-WC/WJ-4: Pressure Wash

12. P13: SSPC-SP13 - Surface Preparation of Concrete:

a. 4.3.1.: Abrasive Blast.

b. 4.3.2.: High Pressure Water Cleaning.

13. P14: SSPC-SP16 - Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel, Stainless Steels, and Non-Ferrous Metals

14. P15: NAPF 500-03-04 Abrasive Blast Cleaning.

N. Re-blast all Surfaces:

1. Where rusting has recurred.

2. That do not meet the above requirements.

3.03 MATERIALS PREPARATION

A. Mix and prepare materials in accordance with manufacturer’s directions.

B. Maintain containers used in mixing and application in a clean condition, free of foreign materials and residue.

C. The following is prohibited:

1. Field mixing of partial containers.

2. Field mixing of lead abatement additive.

3. Field tinting.

3.04 APPLICATION

A. Surface preparation and coating system are as indicated in the “Coating Schedule” at the end of this Section, or noted on Drawings.

09 97 20 - 8 RIVAN 190497

B. Use equipment and techniques best suited for substrate and type of material being applied.

C. Apply in accordance with manufacturer’s directions.

1. Do not apply in snow, rain, fog, mist, or damp surfaces.

2. Allow wet surfaces to dry thoroughly and attain the temperature and conditions specified before proceeding with or continuing the painting operation.

3. Work may continue during inclement weather only if areas and surfaces are enclosed and temperatures within the area can be maintained within limits specified during application and drying periods.

D. Avoid degradation and contamination of surfaces and avoid intercoat contamination.

1. Surfaces shall be free from grease, oil, abrasives, and other contaminants that may have an adverse affect on coating application, bonding, curing, or performance.

2. Clean contaminated surfaces before applying next coat.

3. Do not paint over dirt, rust, scale, grease, moisture, scuffed surfaces, or conditions otherwise detrimental to formation of a durable system.

E. Brush-apply primer or intermediate on all welds and edges prior to general application of finish coat.

F. Apply caulking to flange interfaces, gaps, and intermittent weld seams.

G. Provide finish coats that are compatible with primers used. Prime and intermediate coats shall be lighter than subsequent coat.

H. Provide application thickness to specific mil requirements. Mil thicknesses referenced are in dry mil thickness.

I. All paint systems are “full coverage.” Where discrepancies between manufacturer’s square foot coverage and mil thickness occur, use mil thickness requirements.

J. Where voids are present exposing the substrate or undercoats, apply additional coats until a uniform color and finish is obtained. Give special attention to insure that surfaces, including edges, corners, crevices, welds, and exposed fasteners receive a dry film thickness equivalent to that of flat surfaces.

K. Do not apply additional coats until Engineer has had the opportunity to inspect and approve previous coat.

L. Unless otherwise indicated, match color of adjacent walls or equipment when painting conduit, miscellaneous brackets, hangers, and supports.

M. Smooth out runs or sags immediately, or remove and recoat entire surface.

N. Allow preceding coats to dry before recoating. Recoat within time limits specified by coating manufacturer.

O. Do not apply coatings to the following surfaces:

1. Factory or installer-finished items.

2. Anodized aluminum, stainless steel, or other pre-finished metal.

3. Moving parts of operating devices.

4. Sprinkler heads or other fire detection/suppression elements.

5. Code required labels or equipment nameplates.

3.05 QUALITY CONTROL

A. Contractor shall provide all necessary equipment to monitor and record the information required on the Daily Application Record.

1. Equipment shall be in good condition.

2. Operational within its design range.

RIVAN 190497 09 97 20 - 9

3. Calibrated as required by the specified standard for use of each device.

B. Maintain a copy of the following information at the site:

1. Product Data Sheets.

2. Safety Data Sheets (SDS).

3. Contract Document and submittals.

4. Daily Application Record.

a. Record information (in English) on form located at the end of this Section.

C. Owner’s representative may be on site to observe the application of each coating, and the preparation of each substrate.

D. Provide safe and complete access to all surfaces for observation by Owner and/or Engineer.

E. Prepare rigging so that all surfaces are within arm’s reach of observer.

F. Measure wet paint with wet film thickness gages.

G. Provide DFT measurements for all coatings in accordance with SSPC-PA2.

H. Perform Holiday testing in accordance with NACE RPO 188 as directed by Engineer.

I. Correct any deficiencies observed or detected by field testing as directed by Engineer.

3.06 CLEANING AND PROTECTION

A. During progress of Work, remove discarded materials, rubbish, cans, and rags at end of each workday from the Site.

B. Furnish drop cloths, shields, and protective methods to prevent spray or droppings from disfiguring other surfaces.

C. Upon completion of Work:

1. Clean window glass and spattered surfaces.

2. Remove spattered paint by washing and scraping, using care not to scratch or otherwise damage finished surfaces.

D. Protect Work of other trades against damage. Correct any damage by cleaning, repairing or replacing, and repainting.

E. Provide “Wet Paint” signs as required to protect newly-painted finishes. Remove temporary protective wrappings provided for protection of Work, after completion of painting operations.

F. At completion of Work of other trades, touch-up and restore damaged or defaced surfaces.

3.07 SCHEDULES

A. See the following pages.

09 97 20 - 10 RIVAN 190497

Coating Schedule

SYSTEM

NUMBER

TYPE

SUBSTRATE /

SERVICE

SURFACE

PREP

MFG

FIRST

COAT

DFT

(Mils)

SECOND

COAT

DFT

(Mils )

FINISH

COAT

DFT

(Mils)

NOTES

S4 Epoxy

Chemical Resistant

Steel Immersion (Municipal wastewater & H2S Vapor Exposure)

P10

SW Duraplate 6000 60.0 - 80.0 - - - - SW Duraplate 235 may be used as hold primer

Tnemec Series N140 3.0 - 5.0 Series G435 30.0 – 40.0 - -

S4E Epoxy

Chemical Resistant

Steel Immersion (Municipal wastewater, H2S Vapor, and Exterior Exposure)

P10

SW Duraplate 6000 60.0 - 80.0 SW Duraplate 235 may be used as hold primer

Tnemec Series N140 3.0 - 5.0 Series G436 60.0 – 80.0

S7 Epoxy/Acrylic

Urethane Steel Exterior Exposure P6

SW Macropoxy 646 3.0 - 6.0 Macropoxy

3.0 - 6.0 Acrolon Ultra 2.0 – 3.0

Tnemec Series N69 3.0 - 5.0 Series N69 2.0 – 3.0 Series 1095 2.0 – 3.0

RIVAN 190497

DAILY APPLICATION RECORD

DATE

---------------------------------------------------------------------------------RECORD EVERY 3 HOURS-----------------------------------------------------------------------------

Surface Temperature

(Deg. F.)

Air Temperature

(Deg. F.)

Material Temperature

(Deg. F.)

Relative Humidity

Dew Point

(Deg. F.)

Weather Conditions

TIME START AM PM

AM PM

AM PM

AM PM

AM PM

TIME STOP AM PM

Area Prepared

Area Coated

Type of Material & Quantity Applied:

SIGNED

PROJECT NAME: SEH FILE #:

OWNER: CONTRACTOR:

This Page Left Blank Intentionally